Eastern Cyclone Industries Inc. v. State

37 Ill. Ct. Cl. 197, 1984 Ill. Ct. Cl. LEXIS 29
CourtCourt of Claims of Illinois
DecidedJuly 26, 1984
DocketNo. 82-CC-2208
StatusPublished
Cited by1 cases

This text of 37 Ill. Ct. Cl. 197 (Eastern Cyclone Industries Inc. v. State) is published on Counsel Stack Legal Research, covering Court of Claims of Illinois primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Cyclone Industries Inc. v. State, 37 Ill. Ct. Cl. 197, 1984 Ill. Ct. Cl. LEXIS 29 (Ill. Super. Ct. 1984).

Opinion

Roe, C.J.

The Claimant, Eastern Cyclone Industries, brought this claim seeking damages for breach of contract, fraud, and tortious misrepresentation. The facts, as stipulated by the parties, are essentially as follows.

The Claimant is in the business of installing pneumatic conveyors and laundry equipment. On May 16, 1977, the parties contracted for the sale and installation of a pneumatic laundry conveyor and chute system for soiled linen and trash at the University of Illinois Replacement Hospital (“the hospital”) in Chicago, Illinois. The contract was numbered 7-1487-4 by the Respondent. The Claimant installed the laundry conveyor and chute system and has been paid in toto for that portion of its work.

On July 17, 1978, the Respondent’s construction management company, Morse/UBM Joint Venture, asked the Claimant to “proceed with construction” of revisions to the pneumatic linen and trash lines in the basement of the hospital (“relocation work”). The Claimant agreed to do the relocation work for $13,200.00. About a year later the user agency, the University of Illinois, also asked for the Claimant to sell to it and install a Model 140 Linen Collector and the Claimant did furnish and install it at the hospital.

On March 5,1980, the Claimant submitted a request for proposal and change order on the linen collector for a $34,000.00 contract sum increase. By July 8, 1980, all recommendation and approval signatures had been obtained on the change order except for the final signature of the Respondent (CDB approval) in Springfield, Illinois. Because of the amount of the change order, CDB approval was required. Robert Pierce, the CDB’s manager of its northern regional office, sent the change order to D. Springer, the CDB’s Change Order Administrator in Springfield on July 8, 1980. On or about July 15, 1980, Mr. Springer returned the change order to Mr. Pierce unsigned because a drawing had not been submitted with it, even though the user agency, the construction manager, the architect, the engineer and/or the Respondent had a drawing on hand at the time which showed the work related to the change order.

In September of 1980, the Claimant completed the relocation work and by November of 1980 the installation of the linen collector had been completed.

During September and November of 1980 there were sufficient unobligated funds to approve and pay the Claimant the $34,000.00 for the linen collector and the $13,200.00 for the relocation work.

It was not until December 29,1980, that the change order for the linen collector was resubmitted to the CDB’s Springfield office with the drawing for final approval. A week later the Claimant submitted the change order for the relocation work. Sometime in January of 1981, the change order for relocation work had been approved by the user agency’s Ken Belford and had been recommended for approval by both the project’s architect and construction manager. One Brian O’Connor’s signature was stipulated to be the final signature necessary prior to submittal of the change order to the CDB’s Springfield office. Mr. O’Connor never signed the change order and it was never submitted for reasons that the parties agree are unknown.

In January of 1981 there were still ample unobligated appropriated funds in the hospital project construction account to approve and pay the Claimant for the work performed pursuant to both change orders.

On June 4, 1981, the Claimant submitted to the Respondent a contractor’s affidavit and sworn statement for $47,200.00 for payment for the work covered by both change orders.

At the end of fiscal year 1981 there was $59,571.32 of unobligated funds on hand in the construction account for the hospital project.

On July 29, 1981, the CDB wrote to the Claimant that:

“All appropriate parties have authorized your final payment. However, your change orders Nos. PC-1 and PC-2 (the Relocation Work and Linen Collector, respectively) have yet to be approved due to lack of funds remaining for this project. We regret any inconvenience or hardship this may cause your firm and intend to approve your contract changes as funds become available. .Until that time, we can pay you the current balance remaining in your account.
“Should you find the delay in the change order approval unacceptable, your recourse is in the Court of Claims.” (Parenthetical explanation added by the stipulation.)

In conclusion, the stipulation states that all problems have been corrected under warranty and the Respondent represented that the amount of released funds which currently are unobligated in the hospital project are $1,807.47.

The Claimant in its complaint and amendment thereto has raised three theories of recovery including breach of contract, fraud, and tortious misrepresentation. The claim is before the Court on the Claimant’s motion for summary judgment. Based on the record before us we are unable to say that the Claimant is entitled to judgment as a matter of law.

Essentially, the argument that the contract was breached by the Respondent is simply that the Claimant performed its part of the agreement for the changes and that the Respondent did not pay the Claimant. The Respondent seeks to deny the existence of the agreement. The Respondent cited Section 7-01 of Article 7 of the general conditions of the contract which Respondent stated provided as follows:

“GENERAL. CDB may, at any time, without notice to the sureties, order changes in the contract time or in work germane to the Contract. The Contractor may initiate requests for changes. Upon issuance of a change order, the Contractor shall promptly proceed with the work as changed. No work shall be changed without written approval of CDB.”

The Respondent argues there was no written approval by a person who had authority and it is well-settled law that when dealing with an agent of the State, one is bound to know the extent of his authority, citing Wilder Mobile Homes, Inc. v. State (1979), 33 Ill. Ct. Cl. 227. Further, Respondent argues that undue delay in approval of the change orders, if any, is no excuse for the Claimant to have proceeded on its own without approval.

A careful and thorough examination of the entire record in this matter reveals no such language in Article 7 of the contract nor is there even an Article 7. The copy of the contract amended to the complaint and elsewhere in the record contains only two pages consisting of four Articles. The Claimant did not comment on this argument. A genuine issue of material fact is thus presented and thus we are unable to find that the Claimant is entitled to judgment as a matter of law as to this issue.

Aside from the merits of the breach issue on the contract is the Respondent’s interposition of the insufficiency or lack of funds defense. At this time it is abundantly clear to this Court that there are now insufficient funds remaining with which to pay this claim. Regardless of the merits of the Claimant’s theory of recovery based on breach of contract we are constrained by law to deny recovery on that basis.

Section 30 of “an Act in relation to State Finance” (Ill. Rev. Stat. 1981, ch. 127, par. 166) provides as follows:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Counties of McLean v. State
47 Ill. Ct. Cl. 92 (Court of Claims of Illinois, 1994)

Cite This Page — Counsel Stack

Bluebook (online)
37 Ill. Ct. Cl. 197, 1984 Ill. Ct. Cl. LEXIS 29, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-cyclone-industries-inc-v-state-ilclaimsct-1984.