Eastern Brass & Copper Co. v. General Electric Supply Corp.

101 F. Supp. 410, 1951 U.S. Dist. LEXIS 2038
CourtDistrict Court, S.D. New York
DecidedNovember 30, 1951
StatusPublished
Cited by2 cases

This text of 101 F. Supp. 410 (Eastern Brass & Copper Co. v. General Electric Supply Corp.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eastern Brass & Copper Co. v. General Electric Supply Corp., 101 F. Supp. 410, 1951 U.S. Dist. LEXIS 2038 (S.D.N.Y. 1951).

Opinion

DIMOCK, District Judge.

Plaintiff sues to recover damages for delay in delivery of electrical equipment sold and delivered by defendant. Defendant counterclaims for the agreed price of the equipment. Defendant makes this motion for summary judgment dismissing the complaint and granting recovery on the counterclaims.

The delivery of the goods and the amount of the agreed price are conceded so that there is no opposition to the counterclaims.

The suit presents the following questions: (1) at what time did the agreement require delivery; (2) was delivery made within that time; (3) if delivery was not made within the time fixed therefor did an exculpatory clause in the agreement protect the seller against recovery of damages for the delay?

I have come to the conclusion that there exists a question of fact as to whether delivery was made within the time required by the contract. Such a question of fact ought not to be determined on a motion for summary judgment. If such an exculpatory clause were all embracing, however, it would be unnecessary to decide whether delivery was made on time and summary judgment might be directed against the plaintiff on its claim for damages on the strength of the exculpatory clause alone. I have come to the further conclusion that the exculpatory clause in this case is not all embracing and I must, therefore, deny the motion for summary judgment dismissing the plaintiff’s claim for damages.

My reasons for these conclusions follow.

In the presentation of the motion most emphasis was laid upon the question whether an alleged oral' guarantee fixing the time of delivery was part of the contract between the parties.

The contract was not integrated in a single formal writing. Under date of April 10, 1946, defendant gave the plaintiff its quotation Number 3926 covering four 10-horse power electric motors, four starters for them and four push button stations.

Under the same date the defendant gave the plaintiff its quotation Number 3905 covering two 3-horse power motors, two starters for them, two 5-horse power motors and two starters for them.

Quotation Number 3926 covering the larger motors bore the notation, “Shipping promise after receipt of order at factory” and quotation Number 3905 covering the smaller equipment bore the notation, “Shipment: 36 weeks”.

Each quotation bore an endorsement stating : “All orders are subj ect to the acceptance of our district or branch office serving the purchaser.”

It was after these quotations were made and before any order was given that the oral statement is alleged to have been made. There is testimony that a representative of defendant guaranteed that the material would be delivered between July 25, 1946 and November 8, 1946.

Under date of April 15, 1946, plaintiff ordered from defendant by purchase order Number A-4961 all of the material covered by quotation Number 3926, at the prices which had been quoted, and in addition a reversing starter and push button station which did not appear on the quotation and for which no prices were stated in the order.

Under the same date, plaintiff ordered from defendant by purchase Number A-4963 all of the material covered by the quotation Number 3905, at the prices which had been quoted, and four push button stations which did not appear on the quotation and for which no prices were stated in the order.

. Order Number A-4961 for the larger equipment referred to “Your quotation No. 3926” and order Number A-4963 for the smaller equipment referred to “Your quotation No. 3905”. Neither fixed any date of delivery and each contained the request: “Please * * * • acknowledge receipt of order stating date of delivery”.

The steps by which the contract was formed were the submission of the quotations by defendant, the submission by plaintiff of orders which refer to those quotations and the final acceptance of the orders by defendant. The date when the orders were finally accepted does not appear with precision in the papers but they must have [412]*412been accepted at least as early as January 13, 1947, on which date defendant wrote plaintiff a letter expressing regret that the material could not be delivered until the latter part of March, 1947.

The material was not all' delivered until long after November 8, 1946, the final date fixed in the alleged oral promise.

Whether or not the quotations and the orders embodied the entire agreement between the parties it is unnecessary to decide. It is clear, however, that the quotations in the orders embodied the entire agreement of the parties on the subject of the date of delivery of the material and damages for any delay in such delivery. The orders by referring to the quotations embodied in the terms of the orders all of the provisions in the quotations. As was said by Judge Woodruff in Beach v. Raritan & Delaware Bay R. R. Co., 37 N.Y. 457, 464: “ * * * where a proposition on one side is submitted, whether verbal or written, calling for an answer based on such proposal, the answer, though in writing, need not necessarily recite all the terms and conditions embodied in the proposal. It is to be read in connection with the proposal to which it is a reply, and the whole together constitutes the contract between the parties.”

The fact that there were a few items ordered that did not appear on the quotations merits some notice. When plaintiff indicated on the face of the orders that the orders referred to the designated quotations, defendant was entitled to assume that the general terms of the quotations would be applicable to the whole order whether or not any particular item which was being ordered had been quoted.

To determine the provisions of the contract as to delivery dates I must look to the written terms of the quotations and orders and to those only. The alleged guarantee fixing November 8, 1946 as the latest date for delivery is in direct contradistinction of the terms of the quotations and the orders since the quotation for the larger equipment provided, “Shipping promise after receipt of order at factory” and the quotation for the smaller equipment provided, “Shipment: 36 weeks”. In the latter case the 36 weeks from the date of the quotation would have run out in the middle of January, 1947.

The next question is whether there was a breach of the provisions of the agreement as to date of delivery. The chronology is that the orders were dated April 15, 1946 and were accepted at least as early as January 13, 1947 and that the last of the equipment was not delivered until November 18, 1947.

Following the signature on each of the quotation forms there appear in large type the words: “See reverse side for standard conditions applying.” On the reverse side under the heading “Standard conditions applying to all transactions” appears, among others, the following provision: “Shipping dates given in advance of actual shipment are estimated, and deliveries will be made subject to prior orders on file with us; we shall not be liable for delays resulting from causes beyond our reasonable control or caused by fire, labor difficulties, or delays in our usual sources of supply. Shipping dates are subject to delays resulting from preference ratings or priority shipments ordered or requested by the United States Government or by any department, commission, or agent thereof, and the Corporation shall not be liable for any such delays.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

In re Lehman Bros. Holdings Inc.
544 B.R. 62 (S.D. New York, 2015)

Cite This Page — Counsel Stack

Bluebook (online)
101 F. Supp. 410, 1951 U.S. Dist. LEXIS 2038, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eastern-brass-copper-co-v-general-electric-supply-corp-nysd-1951.