East Sacramento Partnerships for a Livable City v. City of Sacramento

5 Cal. App. 5th 281, 209 Cal. Rptr. 3d 774, 2016 Cal. App. LEXIS 963
CourtCalifornia Court of Appeal
DecidedNovember 7, 2016
DocketC079614
StatusPublished
Cited by31 cases

This text of 5 Cal. App. 5th 281 (East Sacramento Partnerships for a Livable City v. City of Sacramento) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Sacramento Partnerships for a Livable City v. City of Sacramento, 5 Cal. App. 5th 281, 209 Cal. Rptr. 3d 774, 2016 Cal. App. LEXIS 963 (Cal. Ct. App. 2016).

Opinion

Opinion

DUARTE, J.

East Sacramento Partnerships for a Livable City (ESPLC), a neighborhood group, appeals from denial of its petition for a writ of mandate and complaint for declaratory and injunctive relief to set aside the City’s approval of the Project. ESPLC contends the City violated the California Environmental Quality Act (CEQA) (Pub. Resources Code, § 21000 et seq.) 1 when it approved the Project because (1) the Project description is defective; (2) there was illegal piecemealing; (3) the EIR failed to analyze significant health risks; (4) the EIR ignored significant traffic impacts; and (5) the EIR failed to disclose or mitigate methane migration. Further, ESPLC contends the Project is inconsistent with the City’s general plan.

We find merit in only the fourth contention. ESPLC challenges the threshold of significance used in the EIR to determine whether traffic impacts are significant. The City relied on policies in its general plan that permit congested traffic conditions within the core area of the City, thus finding no significant impact of congested traffic on neighborhood streets. As we explain in part IE.2., compliance with a general plan policy does not conclusively establish there is no significant environmental impact, and the City failed to explain why it found none in this circumstance. We reverse the judgment and remand for the City to correct this deficiency in the EIR.

BACKGROUND

The Project

The Project, as finally approved, is a 336-unit residential development with a community recreation center and three parks on a 48.75-acre site. The Project is residential infill, designed to be consistent with the quality and character of the adjoining East Sacramento and McKinley Park neighborhoods. The Project site is roughly football shaped and sandwiched between Interstate 80 Business Route (Capital City Freeway) to the north and the Union Pacific Railroad tracks to the south. The site meets the City’s definition of land targeted for infill development.

To the north of the Project, across the freeway, is the former 28th Street Landfill, now designated Sutter’s Landing Regional Park. To the southwest is a residential neighborhood in midtown Sacramento. To the south, across the railroad tracks, is the Cannery Business Park on C Street. Across C Street is a residential neighborhood in East Sacramento.

*288 There will be two points of access to the Project. The first is the upgrade of the existing A Street Bridge, which will connect the Project to 28th Street in midtown. The second is a new underpass under the Union Pacific railroad embankment to C Street, between 40th Street and Tivoli Way. Both access points will accommodate vehicular, bicycle, and pedestrian traffic.

The EIR

The EIR studied and analyzed the Project’s impacts compared to two baselines, the existing conditions (existing plus project) and future or cumulative conditions (cumulative plus project). The cumulative conditions were based on a build-out of the City’s 2030 general plan. The EIR found no project-specific or cumulative impacts that could not be avoided; all impacts could be mitigated to a less than significant level.

In response to concerns about the health risks to residents of the Project, a health risk analysis accompanied the EIR. This study determined the potential cancer risk to future residents due to diesel particulate matter emissions from diesel trucks and locomotives. The study concluded the cancer risk for the majority of residents was 80 in one million; at one residence, the risk was 120 in one million. These values were within accepted levels.

The primary issue was traffic. The EIR analyzed traffic impacts using the level of service (LOS) method, with a scale of A to F. LOS A is free-flowing traffic and LOS F is congested, “stop and go” traffic. The EIR studied 32 intersections and 19 roadway segments. It found significant traffic impacts at some intersections under cumulative plus project conditions and included a number of traffic mitigation measures to reduce those impacts to less than significant.

City Approval and Subsequent Challenge

On April 29, 2014, by a vote of six to three, the City certified the EIR for the Project, adopted the findings of fact, adopted mitigation measures within the City’s responsibility and jurisdiction, and adopted the mitigation monitoring program.

The following month, ESPLC filed a petition for writ of mandate and complaint for declaratory and injunctive relief, challenging the City’s decision to approve the Project. ESPLC contended there were numerous violations of CEQA, and approval of the Project violated the City’s general plan. ESPLC sought a declaration that the Project approval was invalid and an injunction against any further action on the project.

*289 The trial court denied the petition and ESPLC appealed.

DISCUSSION

I

Alleged CEQA Violations

A. Standard of Review

Section 21168.5 provides that a court’s inquiry in an action to set aside an agency’s decision under CEQA “shall extend only to whether there was a prejudicial abuse of discretion. Abuse of discretion is established if the agency has not proceeded in a manner required by law or if the determination or decision is not supported by substantial evidence.” The CEQA guidelines 2 define “substantial evidence” as “enough relevant information and reasonable inferences from this information that a fair argument can be made to support a conclusion, even though other conclusions might also be reached.” (CEQA Guidelines, § 15384, subd. (a).)

In applying this substantial evidence standard to an action to set aside an agency’s decision under CEQA, we resolve reasonable doubts in favor of the agency’s decision. (Laurel Heights Improvement Assn. v. Regents of University of California (1988) 47 Cal.3d 376, 393 [253 Cal.Rptr. 426, 764 P.2d 278] (Laurel Heights).) “A court may not set aside an agency’s approval of an EIR on the ground that an opposite conclusion would have been equally or more reasonable. [Citation.] A court’s task is not to weigh conflicting evidence and determine who has the better argument when the dispute is whether adverse effects have been mitigated or could be better mitigated.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

LaForest v. City of Mount Shasta CA3
California Court of Appeal, 2025
Sierra Club v. Del Puerto Water District CA5
California Court of Appeal, 2025
Upland Community First v. City of Upland
California Court of Appeal, 2024
People v. Campbell CA2/2
California Court of Appeal, 2024
Upland Community First v. City of Upland CA4/2
California Court of Appeal, 2024
Save Our Capitol v. Dept. of General Services
California Court of Appeal, 2022
We Advocate Through etc. v. County of Siskiyou
California Court of Appeal, 2022
Hammond Landowners Assn. v. City of Weed CA3
California Court of Appeal, 2022
Sierra Watch v. County of Placer
California Court of Appeal, 2021
Sierra Watch v. Placer County CA3
California Court of Appeal, 2021

Cite This Page — Counsel Stack

Bluebook (online)
5 Cal. App. 5th 281, 209 Cal. Rptr. 3d 774, 2016 Cal. App. LEXIS 963, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-sacramento-partnerships-for-a-livable-city-v-city-of-sacramento-calctapp-2016.