East Moline Co. v. Weir Plow Co.

95 F. 250, 37 C.C.A. 62, 1899 U.S. App. LEXIS 2461
CourtCourt of Appeals for the Seventh Circuit
DecidedJune 6, 1899
DocketNo. 551
StatusPublished
Cited by6 cases

This text of 95 F. 250 (East Moline Co. v. Weir Plow Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Seventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
East Moline Co. v. Weir Plow Co., 95 F. 250, 37 C.C.A. 62, 1899 U.S. App. LEXIS 2461 (7th Cir. 1899).

Opinion

BUÜSTN, District Judge,

upon this statement of the case, delivered the opinion of the court.

The principal contention in the case is whether the court erred in not giving judgment for the defendant below for the amount ' claimed as stipulated damages. The finding of facts being in favor of the defendant and against the plaintiff, it seems evident that nom[255]*255inal damages might have been awarded to the defendant upon its counterclaim. The requirement lor nominal damages, however, would he satisfied with a judgment for one cent, and the case might' he reversed for not so awarding, if the rendering of a judgment for costs had depended thereon. But, so long as judgment for costs was given in favor of the defendant, we cannot reverse the judgment because one cent or five cents did not go with the judgment for costs, as nominal damages. It is presumable, under_ the circumstances, that the failure to allow nominal damages with the judgment for costs was the result of inadvertence. Laubenheimer v. Mann, 19 Wis. 519; Eaton v. Lyman, 30 Wis. 41; Hibbard v. Telegraph do., 33 Wis. 558; Smith v. Machine Co., 26 Ohio St. 562; Mahoney v. Robbins. 49 Ind. 146; Palmer v. Degan, 58 Minn. 505, 60 N. W. 342.

But on the main question, of giving judgment for the $50,000 provided for in the contract, we think there was no error. The ease is clearly one coming within the rule long ago laid down by the English and American courts, that where the agreement secures the performance or omission of various acts, together with one or more acts in respect to which the damages on a breach of the covenants are certain and readily ascertainable, and there is a sum stipulated as damages to he paid by each party to the other for a breach of any of the covenants, such sum is a penalty merely. Astley v. Weldon, 2 Bos. & P. 346-353; 3 Pars. Cont. (8th Ed.) 161, and cases cited in footnote; Bagley v. Peddie, 5 Sandf. 192; Trower v. Elder, 77 Ill. 452; Lyman v. Babcock, 40 Wis. 517.

The supreme court of Illinois, in Trower v. Elder, supra, laid down the rule as follows:

“Vi here there are several covenants or stipulations in an agreement, the damages tor the nonperformance of some of which are readily ascertainable by a jury, and the damages for the nonperformance of the, others are not measurable by any exact pecuniary standard, and a ‘sum is named as damages for a breach of any of the covenants or stipulations, such a sum is held to be a penalty.”

This principle, we think, is fairly applicable to the case at bar. Here are a great number of stipulations upon the part of either party, of varying importance, in regard to some of which the damages for nonperformance are readily ascertainable by a court or jury, while some are clearly of the contrary character, with one general provision for damages, equally applicable to each and all the various covenants. Take the one on plaintiffs part, for instance, providing that the buildings shall be kept insured for three-fourths their insurable value. The damages for a breach of such a stipulation are readily ascertainable by a court or jury. The same rule holds in regard to the provision for employing a certain number of men. Suppose a lesser number than 300 were employed; could it he supposed that the parties intended that the damages for employing only 275 men at the plant, instead of 300, should be $50,000? There are also various provisions on the part of the defendant below, like those in regard to providing street-car service, water supply, lighting station, and switching facilities, where the damage could no doubt he separately assessed in case of a breach, and where it would do violence to suppose that the parties could ever have intended that $50,000 should [256]*256be the stipulated sum to be paid for a breach of any one of these minor provisions. Where there are so many and various separate covenants upon either part to be performed, of varying importance, if the parties intend to stipulate thq same large sum to be paid upon any breach, without any regard to the degree of importance it may have in the general scheme of the parties, certainly they should be required to make their meaning plain; and, if they do not make it clear that such was the intent, it is the more reasonable construction to construe such provision for damages as a penalty. This leaves each party free to prove the damages actually sustained. Again, if the intention in such a case is to make the agreed damages apply to some particular main provision of the contract, and not to all, this, also, should be made manifest by express terms.

In Taylor v. Sandiford, 7 Wheat. 13, Chief Justice Marshall lays down the rule somewhat more broadly than the subsequent English and American decisions would warrant, as follows:

“In general, a sum of money in gross, to be paid for the nonperformance of an agreement, is considered as a penalty, the legal operation of which is to cover the damages which the party in whose favor the stipulation is made may have sustained from the breach of contract by the opposite party.”

While that case was, no doubt, correctly decided, the general doctrine there laid down does not seem to take proper account of the cases where it is evident that the damages for a breach would be uncertain in their nature, and impossible of ascertainment by a jury. In these cases it is entirely proper for the parties to agree upon the amount of damages, and such agreements are upheld by, and are not in disfavor in, the courts. In such cases the rule is properly laid down by the appellate court of Illinois in Burk v. Dunn, 55 Ill. App. 25, as follows:

“When the damages are considerable, are not capable of exact ascertainment, and rest mainly in estimation, and are based upon matters which are more or less uncertain, and where there is no fraud in procuring the contract, the amount fixed by the parties ought to be the guide for the court.”

But we know of no cases recognizing an exception to the rule laid down as above in Parsons and in Bagley v. Peddie and Trower v. Elder, where there are various stipulations, under some of which the damages could be readily estimated, and others not, and where the provision for damages, as in the case at bar, applies to all alike. There can be no doubt, if the provision for damages had by agreement of parties been made to apply only to a main breach on the part of the plaintiff below in not erecting and completing the plant by a day certain, the damages for such a breach being entirely uncertain and speculative in character, that the provision would properly be construed as one for stipulated damages.

The counsel for plaintiff in error has, in his reply brief, contended for an exception to the rule he thinks applicable to the case, and for authority quotes from 1 Suth. Dam. § 294, as follows:

“Where an agreement contains several stipulations, differing in importance, and a sum is mentioned as liquidated damages to be paid in case of a breach, and of such amount as is apparently appropriate to a total breach, it will be intended to fix the damages only for such a breach; .and an intention will not [257]*257be imputed to make it payable for breach of minor and unimportant parts, in the absence of language very clearly expressing it.”

But, upon examination of this statement in Sutherland, we And it wholly unsupported by any authority. The only case cited by him is Hoagland v. Segur, 38 N. J. Law, 230, which does not hold to sucli a doctrine.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

United States v. New Amsterdam Casualty Co.
41 F.2d 917 (First Circuit, 1930)
Northwestern Terra Cotta Co. v. Caldwell
234 F. 491 (Eighth Circuit, 1916)
Sledge v. Arcadia Orchards Co.
137 P. 1051 (Washington Supreme Court, 1914)
Elyria v. Cleveland, S. & C. Ry.
34 Ohio C.C. Dec. 406 (Lorain Circuit Court, 1912)
Merica v. Burget
75 N.E. 1083 (Indiana Court of Appeals, 1905)
Chicago House-Wrecking Co. v. United States
106 F. 385 (Seventh Circuit, 1901)

Cite This Page — Counsel Stack

Bluebook (online)
95 F. 250, 37 C.C.A. 62, 1899 U.S. App. LEXIS 2461, Counsel Stack Legal Research, https://law.counselstack.com/opinion/east-moline-co-v-weir-plow-co-ca7-1899.