Earl W. Baker & Co v. City of Hollis

1934 OK 525, 36 P.2d 757, 169 Okla. 253, 1934 Okla. LEXIS 318
CourtSupreme Court of Oklahoma
DecidedOctober 16, 1934
Docket22614
StatusPublished

This text of 1934 OK 525 (Earl W. Baker & Co v. City of Hollis) is published on Counsel Stack Legal Research, covering Supreme Court of Oklahoma primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earl W. Baker & Co v. City of Hollis, 1934 OK 525, 36 P.2d 757, 169 Okla. 253, 1934 Okla. LEXIS 318 (Okla. 1934).

Opinion

PER CURIAM.

The parties will be herein designated as they appeared in the lower court.

This action was brought by Earl AV. Baker & Company, as plaintiff, against the city of Hollis, a municipal corporation, as defendant, to recover an amount alleged to be due for extra labor and materials furnished in addition to the price fixed under two certain contracts for the construction of certain extensions to the waterworks and sewage system of that municipality. The defendant city denies the claim of the plaintiff and alleges overpayment under the terms of the contracts, and, in addition, seeks to recover for certain items paid by it which were not furnished, certain other items of material appropriated by the plaintiff, and damages for failure to construct in accordance with the contract.

The cause was tried to a jury, resulting in a verdict in favor of the defendant and against the plaintiff upon the answer of the defendant seeking affirmative relief for the sum of $7,500. Judgment being entered on the verdict and a motion for new trial being overruled, the cause is in this court on appeal.

Briefly stated, the facts, as shown by the record, are as follows:

On May 18, 1928, the plaintiff and defendant entered into two written contracts, one for the construction of certain sewer extensions and the other for the construction of certain waterworks extensions, both according to plans and specifications furnished by the defendant city. Both contracts were on the cost-plus plan, but with a provision that the defendant might, at any time it elected, require the plaintiff contractor to complete the entire jobs according to plans and specifications for specified lump sums. The work was performed and the materials furnished in pursuance of the contracts, the city electing to exercise its option to pay for the same in lump sums under the provisions of the contracts. The entire contract price was paid on each of the two contracts, and, in addition thereto, the plaintiff presented its bill for extra labor and material furnished in the amount of $3,233.40, a portion of which was paid by the defendant April 6, 1929, but the remaining portion was unpaid, the reason assigned being that the fund was exhausted and no levy had been made to provide for the remainder.

The defendant contends by its answer and in the trial that no funds had been appropriated for the fiscal year 1929 with which to pay for the materials, and labor, and, for the purpose of securing affirmative relief, alleges that the final payment of the contract price was made under the representation that all materials and work had been furnished and completed in accordance with the contracts; that such representations were made by the plaintiff and by the engineer employed by the defendants; that payment of the amounts fixed by the contracts was made, relying upon the statements of the plaintiff and of the defendant’s engineer; that such representations were false; that there were various omissions in the construction and alleged faulty construction, as well as certain materials appropriated by the plaintiff, and the defendant seeks to recover damages therefor on the theory that the al- *254 loged acceptance of the work by the defendant was secured through fraud and misrepresent» lion.

Plaintiff contends that the testimony is insufficient to sustain the verdict for damages on the grounds of fraud. The defendant earnestly contends that the familiar rule should apply to the effect that, if there be any testimony whatsoever to sustain the verdict of the jury, it should not be disturbed. In view of our opinion with reference to the instructions given by the trial court as hereinafter set forth, it is unnecessary to pass upon this phase of the case.

The plaintiff complains because the following instruction was given:

“Should you find from a fair preponderance of the testimony that the plaintiff did not construct the Imhoff disposal tank materially as called for in the plans and specifications as adopted therefor in the original contract, or if you find that changes in the plans had been agreed on, then substantially according to such altered or changed plans as agreed upon, then your verdict upon the issues raised in defendant’s cross-petition, in substance, that the said disposal tank has not been constructed according to contract, should be in favor of defendant in such sum as you find to be the difference in the fair and reasonable cash value of the tank as actually constructed and such value if the same had been constructed according to contract.’’

There is testimony in the record tending to prove that the disposal tank had not been constructed in accordance with the plans and specifioaiions, but there is no testimony as to its value as actually constructed, or as to its value if it had been constructed according to the specifications.

The plaintiff further complains because the following instruction was given:

“You are instructed that should you find by a fair preponderance of the testimony that plaintiff had agreed to construct for defendant 127 manholes, or any other number of manholes, in the sewer system of defendants at ¡560 per manhole, and that plaintiff constructed a lesser number of manholes, than agreed upon, then it will be your duty to find for the defendant, the excess payment, that is, for the sum paid out to plaintiff for manholes not constructed, not to exceed the amount claimed, to wit, $3,-540, unless you find by a fair preponderance of the testimony that the reduction of said manholes was agreed to by the defendants or its engineer and that the defendant city accepted other work in lieu of the manholes not constructed, in which case your finding upon the issues submitted in this paragraph should bo In favor of plaintiff.”

Here it majr be said that there is no competent testimony in tbe record even tending to prove that tbe plaintiff agreed to construct manholes “at $60 per manhole.”

Again the plaintiff complains because the following instruction was given :

“Should you find by a fair preponderance of the testimony that the plaintiff used and laid less pipe in the construction of the sewer than that called for in the opntract and plans and specifications or changes and alterations as agreed to, then you should return a verdict in favor of the defendant for the contract price for such unlaid pipe, to wit: 65 cents per foot, and not to exceed the amount asked in said petition, to wit, $2,044.15.
“But, should you find that the defendant, acting through its council and engineer, agreed to said change and in the use of less pipe and accepted other material or work in lieu therefor, then your verdict should be in favor of the plaintiff upon the issues raised in this paragraph.”

There is no competent testimony in the record tending to prove that the plaintiff agreed to furnish and lay sewer pipe for the price of 65c per foot, or any other fixed price.

Complaint is made of other instructions, which it is not considered necessary to note here.

In considering whether the foregoing instructions were properly submitted to the jury, attention may he given to a certain exhibit which forms a part of the evidence in this case, and upon which it seems obvious the lower court relied as a foundation for the giving of the above instruction.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oklahoma Producing & Refining Corp. of America v. Freeman
1923 OK 55 (Supreme Court of Oklahoma, 1923)
Chas. T. Derr Construction Co. v. Gelruth
1911 OK 344 (Supreme Court of Oklahoma, 1911)
Shawnee Gas & Electric Co. v. Hunt
1912 OK 276 (Supreme Court of Oklahoma, 1912)
St. Louis S. F. R. Co. v. Criner
1913 OK 750 (Supreme Court of Oklahoma, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
1934 OK 525, 36 P.2d 757, 169 Okla. 253, 1934 Okla. LEXIS 318, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earl-w-baker-co-v-city-of-hollis-okla-1934.