Earl Faulkner and Faye Faulkner v. Tom Emmett Construction Company

CourtCourt of Appeals of Tennessee
DecidedNovember 18, 2010
DocketE2010-00361-COA-R3-CV
StatusPublished

This text of Earl Faulkner and Faye Faulkner v. Tom Emmett Construction Company (Earl Faulkner and Faye Faulkner v. Tom Emmett Construction Company) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Earl Faulkner and Faye Faulkner v. Tom Emmett Construction Company, (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE October 4, 2010 Session

EARL FAULKNER, ET AL. v. TOM EMMETT CONSTRUCTION COMPANY

Appeal from the Chancery Court for Knox County No. 170184-2 Michael W. Moyers, Chancellor

No. E2010-00361-COA-R3-CV - FILED NOVEMBER 18, 2010

Earl and Faye Faulkner (“Plaintiffs”) hired Tom Emmett Construction Company (“Defendant”) to construct a new driveway at their home in Knox County. Plaintiffs refused to pay $8,000 of the total $18,000 contract price because they were dissatisfied with the workmanship of the driveway. Plaintiffs sued Defendants seeking as damages what it would cost to remove and replace the allegedly defective driveway. Defendant asserted that the driveway was properly constructed and filed a counterclaim for the remaining $8,000 balance owed on the oral contract. Following a bench trial, the Trial Court concluded that any problems with the driveway were not sufficient to require that it be removed and replaced. Because there was a problem with how the concrete on one portion of the driveway had been poured, the Trial Court required Plaintiffs to pay Defendant only $5,000 of the remaining $8,000 owed on the contract. Plaintiffs appeal. We affirm as modified.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed as Modified; Case Remanded

D. M ICHAEL S WINEY, J., delivered the opinion of the court, in which H ERSCHEL P. F RANKS, P.J., and C HARLES D. S USANO, J R., J., joined.

George F. Legg and Charles D. Waller, Knoxville, Tennessee, for the Appellants, Earl and Faye Faulkner.

Daniel Kidd, Knoxville, Tennessee, for the Appellee, Tom Emmett Construction Company. OPINION

Background

Plaintiffs hired Defendant to install a concrete driveway at their home located in Knox County. Plaintiffs claimed the driveway was defectively installed, and this lawsuit seeking damages eventually was filed. The agreed upon amount for the installation initially was $15,000. According to the complaint:

The work undertaken by the Defendant was done extremely poorly and has resulted in very poor overall quality of the driveway and concrete finish. To wit, and including, but not limited to: (a) there exist ridges, humps, screed marks, boot prints, and unfinished slurry on top of the concrete finish; (b) the contraction joints placed in the concrete by the Defendant are of very poor quality and are misplaced; (c) the Defendant has improperly divided the concrete slab into long rectangles instead of squares with contraction joints no further apart than 20 feet as required by the Building Code Requirements for Structural Concrete which will result in additional cracks in the concrete slab; (d) the Defendant failed to place expansion material between the concrete slab and the wall of the Plaintiffs’ home; (e) an existing railroad tie which is part of the Plaintiffs’ lawn edging was improperly used by the Defendant as an end form for the concrete slab; (f) the Defendant has improperly placed the concrete slab directly on top soil instead of upon a proper uniform stone base resulting in the concrete slab settling and cracking due to compression of the top soil; (g) there exist great variations in slab thickness. In some areas the concrete slab is 4 inches thick and in other areas the slab is only 2 inches thick which has produced weak areas and strong areas all over the surface area of the concrete slab; (h) the Defendant has improperly installed the welded wire fabric and rebar reinforcement in the concrete slab. The welded wire fabric and rebar were not placed on stakes to hold it in place when the slab was poured, but was allowed to lie directly on the ground. The result is that the welded wire fabric and rebar are totally ineffective to reinforce the integrity of the concrete slab in that it is not properly imbedded into the concrete slab, and; (i) the

-2- welded wire fabric is not overlapped which will result in cracks developing in the locations where it was not overlapped.

Based on the foregoing allegations, Plaintiffs claimed the driveway was not completed in a workmanlike manner and was defectively installed in such a way that Plaintiffs will have no choice but to have the driveway completely removed and replaced. Plaintiffs explained that they paid Defendant $10,000 of the original $15,000 contract price, and Defendant thereafter improperly filed a lien against Plaintiffs’ property for the balance it claimed they owed. Plaintiffs sought damages in the amount of $55,000, as well as removal of the lien.

Defendant answered the complaint and generally denied any liability to Plaintiffs. Defendant denied that the driveway was defectively installed. According to Defendant’s answer:

The defendant . . . defend[s] against this action on the basis of unclean hands and/or equitable estoppel in that the plaintiffs refused to enter into a written contract and at all times were intimately involved in the entire process of the driveway’s installation and the plaintiffs made various decisions against the sound advice of the defendant and insisted the defendant perform according to their demands and requests and furthermore, the plaintiffs voiced no complaints concerning the driveway or the quality of workmanship until the defendant requested payment on the outstanding bill.

Defendant requested that the complaint be dismissed and, in a counterclaim 1 , requested that it be awarded the remaining balance owed on the contract price.

This case was tried in August 2009, with the first witness being plaintiff Earl Faulkner (“Faulkner”). Faulkner decided to use Tom Emmett Construction Company to build the driveway after looking through the yellow pages. He first met Tom Emmett (“Emmett”) in November of 2006. Faulkner told Emmett that he wanted a four-inch driveway on a gravel base with rebar and wire mesh. Emmett’s initial estimate was $18,000, but it later was reduced to $15,000. They later changed the size of the new driveway to make

1 When Plaintiffs filed their complaint in the Knox County Chancery Court, they already had been sued by Defendant in the Knox County General Sessions Court. These lawsuits were consolidated and Defendant’s sessions court lawsuit was treated as a counterclaim in Chancery Court.

-3- it closer to the house, but Faulkner stated that during this entire process, he never agreed to an increase in the $15,000 contract price.

Faulkner testified that while the driveway was being constructed, he observed several things that he thought were being done improperly. According to Faulkner, the wire mesh was placed under the rebar, but was supposed to be on top of the rebar. In various places, the rebar improperly was placed on the ground instead of being put on chairs. Faulkner allegedly voiced his concerns to Emmett, but nothing was done to correct these problems. Faulkner stated that gravel never was brought to the site or used in the driveway before the concrete was poured. The concrete was poured up to the house and no expansion joints were used. Faulkner also testified that the surface area of the concrete was not smooth and in some places, the concrete was only 2½ inches thick, as opposed to the agreed-upon 4 inches. Faulkner paid Defendant $10,000 and refused to pay the balance due to the alleged poor quality of the driveway. Faulkner denied ever agreeing to an increase in the amount of the original agreement from $15,000 to $18,000 due to the size of the driveway increasing. Faulkner described the overall general appearance of the driveway as “horrible” and stated that the whole driveway needed to be replaced. Approximately one month after the driveway was completed, Faulkner filed a complaint against Defendant with the contractor’s board in Nashville.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
Southern Constructors, Inc. v. Loudon County Board of Education
58 S.W.3d 706 (Tennessee Supreme Court, 2001)
Business Men's Assurance Co. of America v. Graham
891 S.W.2d 438 (Missouri Court of Appeals, 1994)
GSB Contractors, Inc. v. Hess
179 S.W.3d 535 (Court of Appeals of Tennessee, 2005)
McClain v. Kimbrough Const. Co., Inc.
806 S.W.2d 194 (Court of Appeals of Tennessee, 1990)
Loftis v. Finch
491 S.W.2d 370 (Court of Appeals of Tennessee, 1972)
Buice v. Scruggs Equipment Co.
267 S.W.2d 119 (Court of Appeals of Tennessee, 1953)
Town of Fifield v. State Farm Mutual Automobile Insurance Co.
349 N.W.2d 684 (Wisconsin Supreme Court, 1984)
Beaty v. McGraw
15 S.W.3d 819 (Court of Appeals of Tennessee, 1998)
Sholodge Franchise Systems, Inc. v. McKibbon Bros., Inc.
919 S.W.2d 36 (Court of Appeals of Tennessee, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
Earl Faulkner and Faye Faulkner v. Tom Emmett Construction Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/earl-faulkner-and-faye-faulkner-v-tom-emmett-const-tennctapp-2010.