EAGLE'S NEST LTD. PARTNERSHIP v. Brunzell

669 P.2d 714, 99 Nev. 710, 1983 Nev. LEXIS 524
CourtNevada Supreme Court
DecidedSeptember 27, 1983
Docket14000
StatusPublished
Cited by1 cases

This text of 669 P.2d 714 (EAGLE'S NEST LTD. PARTNERSHIP v. Brunzell) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
EAGLE'S NEST LTD. PARTNERSHIP v. Brunzell, 669 P.2d 714, 99 Nev. 710, 1983 Nev. LEXIS 524 (Neb. 1983).

Opinion

OPINION

Per Curiam:

The instant dispute between appellant/cross-respondent property owner Eagle’s Nest Limited Partnership (Eagle’s Nest) and respondent/cross-appellant contractor Brunzell arose after difficulties developed in the course of Brunzell’s construction of condominiums ordered by Eagle’s Nest.

In 1977, Eagle’s Nest and Brunzell agreed that Brunzell *712 would construct the condominiums in question using a new technique known as the “Wham-T” system. This Wham-T system was a new construction method which utilized large precast concrete forms poured directly at the job site. If this system was effectively utilized considerable savings could be realized, because massive concrete forms did not have to be transported to the job site. In order to realize the savings possible through the use of this method, however, an appropriate number of Wham-T molds had to be available on the job site during the course of construction. These molds could only be obtained from the Wham-T parent distributor, and it was the contractual responsibility of Eagle’s Nest to provide an appropriate number of molds.

During the course of construction, difficulties arose in the operation of the Wham-T molds which resulted in substantial delays in construction. A witness for Brunzell testified that at least two large Wham-T molds would have been required to bring the job in on time. However, Eagle’s Nest provided only one large and one small mold. Further, mechanical difficulties with the small mold prevented Brunzell from using that piece of equipment at normal or expected rates of production.

As a result of delays incurred due to the difficulties with the molds, the project was completed late in 1979, several months later than anticipated. Brunzell subsequently brought an action against Eagle’s Nest to recover the additional costs and expenses incurred due to this delay. The main factual issue presented at trial was whether the use of the Wham-T system resulted in delays which were not contemplated by the parties. The district court found that Brunzell had bid on the job on the assumption that Eagle’s Nest would provide an appropriate number of molds, but that Eagle’s Nest had failed to provide sufficient molds for the contractor to bring the job in on time. The district court accordingly found that Eagle’s Nest had caused substantial delays in the completion of the project, and that under an “equitable adjustment” provision of the contract between Eagle’s Nest and Brunzell, Eagle’s Nest was liable for the extra costs which were incurred. The district court entered judgment in the amount of $544,386.78 for Brunzell, and this appeal followed.

EQUITABLE ADJUSTMENT

On appeal, Eagle’s Nest first argues that the district court erred in ruling that Brunzell was entitled to an equitable adjustment under the contract. This contention is without merit. We initially note that neither party to this appeal appears to contest the district court’s finding that delays occurred in the course of *713 construction, and that these delays were caused in large part by the failure of Eagle’s Nest to deliver the appropriate number of molds to the construction site.

Instead, appellant Eagle’s Nest argues that the district court erred because it failed to recognize that Brunzell failed to comply strictly with a contractual provision which established specific methods and procedures to be followed if the contractor wished to make a claim for an increase in the contract price. Eagle’s Nest maintains that because Brunzell failed to comply with this provision, the contractor may not later claim an increase in the agreed contract price.

The provision in question, Section 9.2.1 of the construction contract, established a procedure by which Brunzell could seek an adjustment in the guaranteed maximum contract price. That section provided:

If the contractor wishes to make a claim for an increase in the Guaranteed Maximum Price, or increase his Fee or an extension of the Contract Time Schedule, he shall give the Owner written notice thereof within a reasonable time after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceeding to execute the Work, except in an emergency endangering life or property in which case the Contractor shall act, at his discretion, to prevent threatened damage, injury or loss. Claims arising from the delay shall be made within a reasonable time after delay. . . . No such claim shall be valid unless so made. . . . Any change in the Guaranteed Maximum Price, the Contractor’s Fee or Contract Time Schedule resulting from such claim shall be authorized by Change Order.

(Emphasis added.)

It is clear from the contractual language used that this notice and claim provision was material to the parties. The issue presented is whether the district court erred in finding that Brunzell complied with this material notice and claim provision. The district court ruling that the notice and claim provision had been complied with was based on a letter sent by Brunzell to appellant some time after the contractor began experiencing mechanical problems with the small Wham-T mold. That letter provided, in pertinent part:

We are currently being delayed as a result of misalignment and unworkability of certain parts within the small Wham-T mold (affectionately called Rusty Dusty by its Maker). This equipment was damaged in transit and has *714 undergone considerable repair and modification since being shipped to the jobsite. Major repairs have been made as directed by “Wham-T” however, this work has not completely resolved this problem since the rear door closing jacks are still inoperative. Due to this and other problems we have not benefited from having this mold. We have not been able to doordinate [sic] its use with the large mold, consequently have had to bear the additional cost for lifting and erection of poured units after our equipment has moved to a different location.
For example, the large “Wham-T” molds for building No. 3 are almost finished yet due to breakdown we have only poured one small mold at this time. This will necessitate moving the crane and labor back to Building 3 site when the molds poured in “Rusty Dusty” are available. We do not believe we should be responsible for the resultant extra costs. Accordingly, it is our intent to submit our billing to you at a later date.
We trust you will consider this matter favorable in the light of the circumstances known to you.

The district court ruled this letter gave sufficient notice of additional costs and expenses which Brunzell later detailed in a “Change Order 19.” These additional charges and expenses totaled $380,537.09.

The letter clearly indicated that Brunzell was “being delayed” as a result of difficulties caused by mechanical problems with one of the Wham-T molds. Further, the letter indicated that the contractor disclaimed any liability for the resulting extra costs, and intended to bill Eagle’s Nest at a later date.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brunzell v. Lawyers Title Ins. Corp.
705 P.2d 642 (Nevada Supreme Court, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
669 P.2d 714, 99 Nev. 710, 1983 Nev. LEXIS 524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagles-nest-ltd-partnership-v-brunzell-nev-1983.