Eagle Rock Timber, Inc. v. Teton County

531 P.3d 488, 172 Idaho 172
CourtIdaho Supreme Court
DecidedJune 13, 2023
Docket49373
StatusPublished
Cited by5 cases

This text of 531 P.3d 488 (Eagle Rock Timber, Inc. v. Teton County) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle Rock Timber, Inc. v. Teton County, 531 P.3d 488, 172 Idaho 172 (Idaho 2023).

Opinion

IN THE SUPREME COURT OF THE STATE OF IDAHO

Docket No. 49373

EAGLE ROCK TIMBER, INC., an Idaho ) corporation, ) ) Boise, February 2023 Term Plaintiff-Appellant, ) ) Opinion filed: June 13, 2023 v. ) ) Melanie Gagnepain, Clerk TETON COUNTY, IDAHO, a political ) subdivision of the State of Idaho, ) ) Defendant-Respondent. )

Appeal from the District Court of the Seventh Judicial District of the State of Idaho, Teton County. Stevan H. Thompson, District Judge.

The decisions of the district court are affirmed in part and reversed in part.

Holden, Kidwell, Hahn & Crapo, PLLC, Idaho Falls, for Appellant. D. Andrew Rawlings argued.

Hopkins Roden Crockett Hansen & Hoopes, PLLC, Idaho Falls, for Respondent. Steven Brown argued. _______________________________________________

MOELLER, Justice. This appeal concerns a dispute over a public works contract involving 1.6 miles of road reconstruction in Teton County, Idaho. After submitting the winning bid, Eagle Rock Timber, Inc. (“Eagle Rock”), contracted with Teton County to reconstruct a stretch of road known as “Chapin Lane.” During the course of the project, Eagle Rock claims it discovered unsuitable base material under portions of the road. Eagle Rock maintains that Teton County’s agent, Darryl Johnson (“Johnson”), directed Eagle Rock to remove the material and said that the county would “make it right.” However, when Eagle Rock attempted to recover an amount in excess of the original Contract Price, Teton County denied Eagle Rock’s request, stating that it had not authorized any changes to the Contract. When the parties could not resolve this dispute over the amount owed, Eagle Rock brought suit.

1 Teton County moved twice for summary judgment. The district court denied the first motion, concluding that genuine issues of material fact existed concerning whether Johnson orally waived the writing requirement and whether Johnson had authorized Eagle Rock to remove the unsuitable base material, which could support an equitable remedy. However, when Teton County filed a subsequent motion for summary judgment, the district court granted it, ruling that since Teton County’s agent did not have actual or apparent authority to bind Teton County, the claims asserted by Eagle Rock failed as a matter of law. Eagle Rock appealed, asserting that the district court erred because there are still genuine issues of material fact that should be resolved by a jury. Additionally, Eagle Rock claims that the district court’s refusal to grant leave to amend its complaint to assert a separate cause of action against Johnson personally was an abuse of discretion. Eagle Rock further argues that since Teton County should not have prevailed below, the district court’s award of attorney fees should be vacated. For the reasons stated herein, we reverse the district court’s grant of summary judgment and denial of leave to amend. Accordingly, we also vacate the award of attorney fees to Teton County. However, we affirm the district court in not considering the ratification issue because it was beyond the scope of the pleadings at the time it was presented. I. FACTUAL AND PROCEDURAL BACKGROUND In early 2018, Teton County opened bidding to licensed contractors on a public works road reconstruction project. The project entailed a 1.6-mile stretch of a county roadway near Victor, Idaho, called Chapin Lane. The plans for the project were designed by Jorgensen Associates, PC. Darryl Johnson, a licensed engineer previously employed by Jorgensen Associates, PC, from 2007 to 2014, played a role in preparing many of the design documents in advance of Teton County soliciting bids for the project. However, by the time bidding was opened, Darryl Johnson had been hired by Teton County as its Public Works Director and County Engineer. He played a key role in the bidding process. After completing the bidding process, Eagle Rock’s bid was selected and it entered into a contract with Teton County for the project. According to both parties at oral argument, Johnson prepared the Contract documents. Per the terms of the agreement, the full Contract included: an eight-page agreement; performance bond; payment bond; a document entitled “General Conditions – Divisions 100 of the Idaho Standards for Public Works Construction”; supplementary conditions, drawings, and specifications; addenda; the contractor’s bid as an exhibit; and any subsequent

2 change orders or work change directives (these documents will be collectively referred to herein as the “Contract”). The Contract required that a project “Engineer” be designated to play a key role in specified functions of the Contract—including taking certain measurements, making recommendations, and holding authority to make certain minor changes as defined in the Contract. Jorgensen Associates was designated as the Engineer in the Contract. During construction, Eagle Rock asserts it discovered unsuitable base material under portions of the road in such amounts as could not be fully ascertained until it was removed. However, Eagle Rock was able to determine that it would require the removal of more material than originally estimated in the Contract. The original bid submitted by Eagle Rock, and incorporated into the Contract, was based on a projection of only 200 cubic yards of unsuitable material excavation, which was priced at a removal rate of $112 per cubic yard. Eagle Rock claims the discovery of the unsuitable base material was reported to Johnson on at least two occasions. In both instances, Eagle Rock claims Johnson instructed Eagle Rock, or its subcontractors, to go ahead and remove the unsuitable material and that Teton County would “make it right.” Teton County and Johnson deny that this ever occurred. After removal of the unsuitable base material, Eagle Rock submitted a change order. This change order, which included a corresponding price increase of $111,440 for the material used to infill where the unsuitable base material had been removed, was approved by Teton County. Eagle Rock then filed an “application for payment” for the removal of the unsuitable base material at the unit price contemplated in the Contract. Due to the unanticipated amount of material that had to be removed, the additional costs of removal exceeded the Contract Price by $649,600. Teton County denied Eagle Rock’s request, stating it had not authorized any changes in the Contract related to the removal of the unsuitable material. Teton County cited express provisions of the Contract that required any change in Contract Price or modification of the Contract to have prior written authorization approved by Teton County. Eagle Rock attempted to meet with Teton County and negotiate a unit price for the excess unsuitable base material, but Teton County maintained that Eagle Rock had been paid all it was due under the Contract. When the parties could not resolve this dispute over the amount owed, Eagle Rock brought suit. Teton County moved for summary judgment twice. In the first motion, Teton County argued that Eagle Rock “did not adhere to the contractual requirements for securing a Change Order and no Change Order exist[ed].” Teton County asserted that since the Contract Price could 3 not be changed absent a change order, Eagle Rock’s complaint should have been dismissed. The district court disagreed and denied the first motion due to the court’s concerns that genuine issues of material fact existed regarding whether Johnson orally waived the writing requirement and whether he gave authorization to Eagle Rock for the removal, which could implicate an equitable remedy. However, as summarized by the district court, “[i]n the first summary judgment decision, the [district court] did not delve into the scope of Johnson’s authority.” Less than two months after the district court issued its decision on the first motion, Teton County moved for summary judgment again.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Streamline Builders, LLC v. Chase
Idaho Supreme Court, 2024
Kelso v. Applington
548 P.3d 363 (Idaho Supreme Court, 2024)

Cite This Page — Counsel Stack

Bluebook (online)
531 P.3d 488, 172 Idaho 172, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-rock-timber-inc-v-teton-county-idaho-2023.