Adkison Corp. v. American Building Co.

690 P.2d 341, 107 Idaho 406, 39 U.C.C. Rep. Serv. (West) 98, 1984 Ida. LEXIS 549
CourtIdaho Supreme Court
DecidedOctober 23, 1984
Docket14396
StatusPublished
Cited by25 cases

This text of 690 P.2d 341 (Adkison Corp. v. American Building Co.) is published on Counsel Stack Legal Research, covering Idaho Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Adkison Corp. v. American Building Co., 690 P.2d 341, 107 Idaho 406, 39 U.C.C. Rep. Serv. (West) 98, 1984 Ida. LEXIS 549 (Idaho 1984).

Opinion

ON DENIAL OF PETITION FOR REHEARING

DONALDSON, Chief Justice.

This suit was brought by two Idaho plaintiffs, Adkison Corporation, an Idaho contracting company, and Ronald Corrado, an Idaho aircraft mechanic, against American Building Company (ABC), a manufacturer of metal buildings, headquartered in Georgia with a manufacturing plant located in Nevada. The plaintiffs brought suit against ABC for damages resulting from the alleged late delivery of a defective building. Plaintiffs’ claim for liability and damages is based on several theories including agency, contract, implied warranty and negligence. The trial court directed a verdict against the plaintiffs on each of the above counts. On appeal, we address whether the plaintiffs presented sufficient evidence to allow a jury to conclude that the defendant was liable on each of the above theories. We affirm in part, reverse in part and remand.

In mid-1978, Corrado wanted to build a hangar, shop, office space and other facilities for his new aircraft repair business at the Grangeville airport. Corrado entered into a written contract with plaintiff Adkison Corporation to have these facilities constructed. ABC was to be the supplier of a metal hangar and lean-to components which were to be erected by Adkison as a part of Adkison’s contract with Corrado.

Adkison supplied information regarding the design of the hangar to ABC’s dealer, Rural Systems, Inc. (RSI). Adkison ordered the hangar from RSI, who in turn submitted an order to ABC. All the parties understood that the building would be manufactured and supplied by ABC.

*408 RSI made a mistake in placing the order by specifying that the common wall between the hangar building and the first lean-to should be an open wall. Adkison discovered the mistake and notified RSI, and RSI then informed ABC of it. ABC agreed to furnish the additional material to erect the missing wall at no additional cost. There were other fabrication and shipping mistakes, and further delays in shipping additional materials required to complete the building. Such delays and mistakes were directly attributable to ABC.

The plaintiffs are each seeking recovery of economic losses due to ABC’s alleged failure to deliver a complete building package, alleged errors in fabrication of its building components, and alleged delays in correcting errors and supplying missing parts.

RSI was originally included as a defendant, but was dismissed from this suit because it declared bankruptcy. The case went to trial and at the conclusion of the plaintiffs’ case in chief, the trial court granted ABC’s motion for a directed verdict on all of the plaintiffs’ counts. The plaintiffs made a motion for a new trial which the trial court subsequently denied. This appeal followed.

On appeal, we must determine whether the trial court erred in granting defendant’s motion for a directed verdict on each of plaintiff’s theories which are as follows:

(1) The defendant ABC was liable to the plaintiffs based on the theory that an apparent agency existed between ABC and RSI;
(2) The defendant ABC was liable to the plaintiffs based on the theory that plaintiffs were third-party beneficiaries of the ABC-RSI agreement;
(3) The defendant ABC was liable to the plaintiffs for economic losses based on the theory of breach of implied warranties in tort;
(4) The defendant ABC was liable to the plaintiffs for economic losses based on the theory of negligence;
(5)The defendant ABC was liable to the plaintiffs based on a theory of direct contract between the plaintiffs and ABC.

Before we separately address each of the above theories, we first note our standard of review.

“A directed verdict should only be granted when the evidence is so clear and undisputed that all reasonable minds must reach the same conclusion. On a motion for directed verdict pursuant to I.R.C.P. 50(a), the moving party admits the truth of the adverse evidence and every inference that may be legitimately drawn from it. Where there is substantial competent evidence tending to establish plaintiff’s case, or where reasonable minds may differ as to the conclusion to be reached from the evidence, the cause should be submitted to a jury.”

Thomas Helicopters, Inc. v. San Tan Ranches, 102 Idaho 567, 569, 633 P.2d 1145, 1147 (1981) (quoting Shields & Co., Inc. v. Green, 100 Idaho 879, 882, 606 P.2d 983, 986 (1980)). Thus, our focus on appeal is to

“determine whether plaintiff’s evidence was sufficient to survive defendant’s motion for a directed verdict and to justify submitting the case to the jury, i.e., whether, as a matter of law, plaintiff produced sufficient evidence (not a mere scintilla) from which reasonable minds could conclude that a verdict in favor of the plaintiff was proper.”

Gmeiner v. Yacte, 100 Idaho 1, 4, 592 P.2d 57, 60 (1979).

I.

Agency

Plaintiffs contend that ABC is liable to them based on an apparent agency theory. Plaintiffs argue that ABC created the impression that RSI was its agent through ABC's actions and that by virtue of the ABC-RSI agency relationship, a contractual relationship arose between the plaintiffs and ABC.

*409 Proof of implied agency is generally found in the acts and conduct of the parties, rather than from an oral or written contract which establishes the agency relationship. State v. DeBaca, 82 N.M. 727, 487 P.2d 155 (1971). See also Briggs v. Morgan, 262 Or. 17, 496 P.2d 17 (1972) (agency may be proven by circumstances and course of dealing between the parties); Land-Air, Inc. v. Parker, 103 Ariz. 1, 435 P.2d 838 (1967) (agency may be established from the relationship of the parties to each other and to the subject matter). In addition, the existence of an agency relationship is a question for the trier of fact to resolve from the evidence. Clark v. Gneiting, 95 Idaho 10, 501 P.2d 278 (1972); Thornton v. Budge, 74 Idaho 103, 257 P.2d 238 (1953) (if the existence or nonexistence of agency is a disputed question of fact it was for the jury to decide).

We turn now to examine the evidence in the case at bar. In its order, the trial court noted that

“[plaintiffs’ evidence tended to show:
(1) RSI was an authorized dealer for ABC buildingsf.]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Eagle Rock Timber, Inc. v. Teton County
531 P.3d 488 (Idaho Supreme Court, 2023)
Petrus Family Trust Dated May 1, 1991 v. Kirk
415 P.3d 358 (Idaho Supreme Court, 2018)
American West Enterprises, Inc. v. CNH, LLC
316 P.3d 662 (Idaho Supreme Court, 2013)
Partout v. Harper
183 P.3d 771 (Idaho Supreme Court, 2008)
Fenwick v. Idaho Department of Lands
160 P.3d 757 (Idaho Supreme Court, 2007)
Hayenga v. Nampa School District No. 131
123 F. App'x 783 (Ninth Circuit, 2005)
Idaho Power Co. v. Hulet
90 P.3d 335 (Idaho Supreme Court, 2004)
Leavitt v. Swain
963 P.2d 1202 (Idaho Court of Appeals, 1998)
Hill v. Sligar
920 P.2d 74 (Idaho Supreme Court, 1996)
Cannon Builders, Inc. v. Rice
888 P.2d 790 (Idaho Court of Appeals, 1995)
Hausam v. Schnabl
887 P.2d 1076 (Idaho Court of Appeals, 1994)
Oats v. Nissan Motor Corp. in U.S.A.
879 P.2d 1095 (Idaho Supreme Court, 1994)
Vickers v. Hanover Const. Co., Inc.
875 P.2d 929 (Idaho Supreme Court, 1994)
Seubert Excavators, Inc. v. Eucon Corp.
874 P.2d 555 (Idaho Court of Appeals, 1993)
Hilt v. Draper
836 P.2d 558 (Idaho Court of Appeals, 1992)
Sharp v. W.H. Moore, Inc.
796 P.2d 506 (Idaho Supreme Court, 1990)
Twin Falls Livestock Commission Co. v. Mid-Century Insurance
786 P.2d 567 (Idaho Court of Appeals, 1989)
Baldwin v. Leach
769 P.2d 590 (Idaho Court of Appeals, 1989)
Gissel v. State
727 P.2d 1153 (Idaho Supreme Court, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
690 P.2d 341, 107 Idaho 406, 39 U.C.C. Rep. Serv. (West) 98, 1984 Ida. LEXIS 549, Counsel Stack Legal Research, https://law.counselstack.com/opinion/adkison-corp-v-american-building-co-idaho-1984.