Eagle Hill Corp. v. Commission on Hospitals & Health Care

477 A.2d 660, 2 Conn. App. 68, 1984 Conn. App. LEXIS 616
CourtConnecticut Appellate Court
DecidedMarch 6, 1984
Docket(2422)
StatusPublished
Cited by30 cases

This text of 477 A.2d 660 (Eagle Hill Corp. v. Commission on Hospitals & Health Care) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Eagle Hill Corp. v. Commission on Hospitals & Health Care, 477 A.2d 660, 2 Conn. App. 68, 1984 Conn. App. LEXIS 616 (Colo. Ct. App. 1984).

Opinion

*70 Borden, J.

The defendant commission on hospitals and health care appeals 1 from the judgment of the trial court modifying a decision of the commission which denied a major part of a capital expenditure increase sought by the plaintiff, Eagle Hill Corporation (Eagle Hill). Eagle Hill operates an alcoholism treatment facility in Newtown.

The commission, after a hearing, found the following facts. On September 11,1976, the commission approved Eagle Hill’s request to construct the facility, providing a mix of fifty-six acute, intensive and intermediate care beds, at a cost not to exceed $2,700,441. In the fall of 1978, Eagle Hill applied for and on January 9, 1979, the commission approved a capital expenditure increase of $1,594,559, bringing the total approved cost to $4,295,000. This increase was made necessary by the inflationary effect of delays and by building standards, applicable to Eagle Hill, developed by the federal department of housing and urban development, which was financing the construction of the facility. At that time Eagle Hill projected a per diem patient rate of $114.

On February 6,1980, Eagle Hill applied to the commission for approval of initial rates of $127 per day. On February 15, 1980, the staff of the commission responded that the requested rate was based on a rental expense 2 which was inconsistent with rental information previously filed. On February 19,1980, Eagle Hill explained that the new rental expense was based on a capital cost at least $351,000 higher than the *71 $4,295,000 approved, due to certain cost overruns during construction.

In February, 1980, Eagle Hill had indicated that it would begin to operate on April 1, 1980, but had not yet obtained the required local zoning and building approvals. On March 25,1980, the commission, finding that Eagle Hill had not timely submitted its rate application, denied the proposed initial rate and ordered a hearing to address both the cost overruns and the per diem rate. On April 8, 1980, Eagle Hill informed the commission that the cost overruns, previously indicated at $351,000, were in fact $555,000, plus an additional $96,500 for relocation of offices required by local zoning authorities for which it planned to request approval.

A first hearing was held on April 15,1980, on Eagle Hill’s application for initial rates and approval of cost overruns. This application requested rates of $130 per day, and at the hearing Eagle Hill increased its cost overrun estimate to $705,358, which included $101,720 for increased financing costs and $96,500 for offices. After the hearing Eagle Hill withdrew this application.

On April 23,1980, Eagle Hill submitted a new application, which generated the hearing leading to the commission’s decision in this case. Eagle Hill requested approval of a total increased capital expenditure of $705,036, which included a more precise estimate of the office relocation cost. On April 30,1980, Eagle Hill requested a per diem rate of $133.50. Eagle Hill broke down the cost overrun figure into three general categories: increased construction costs, consisting of six subcategories, totaling $557,340; additional recreation area work costs totaling $45,976; and additional financing costs of $101,720.

The increased construction costs consisted of the following. (1) $152,131 for excavation and removal of ledge and bedrock which was not disclosed by a precon *72 struction soil survey; (2) $113,015 for changes in four buildings resulting from price increases, improvements for operating efficiency, changes required by safety codes, environmental improvements, and changes required by local authorities because of square footage increases made by Eagle Hill; (3) $34,006 for lighting and other electrical changes required because of the inadequacy of the original lighting plan; (4) $93,690 for wells and changes in specifications for the pumping house required because of inadequacies in the original design; (5) $68,320 for site work changes required because of errors in the original site plan; and (6) $96,178 for relocation of the corporate offices required because, after securing local approval, Eagle Hill made internal square footage changes of which the local authorities did not approve. The increased cost for additional recreation areas was required because of errors in the original plan. The additional financing cost, which would be incurred when additional funds were borrowed, resulted from increased debt to finance the other increases.

The construction change orders involved here began to accumulate in July, 1979, and had been approved by Eagle Hill’s architect, contractor and other personnel without any tallying of their sum. Between January, 1979, when the commission approved Eagle Hill’s first increase, and February 19,1980, when Eagle Hill first explained its increased rental expense, Eagle Hill did not notify the commission of any cost overruns. This was because Eagle Hill was unaware of the amount of those overruns. The cost of completing the remaining construction work as of May 15, 1980, was $63,920. Excluding the $101,720 in additional financing costs which had not yet been incurred, this left a total of $539,396 spent or committed by Eagle Hill without the commission’s approval, which was equivalent to an additional per diem patient expense of $4.25. Eagle Hill *73 has made no attempt to recover any costs flowing from original plan inadequacies for which architects and engineers were responsible. The construction project was inefficiently managed and monitored. There is no evidence that Eagle Hill attempted to identify nonessential items or areas for reduction or elimination so as to compensate for cost increases and thus to maintain the overall cost within the previously approved amount.

The commission concluded as follows. Eagle Hill failed to submit its request for approval of the $705,036 capital expenditure ninety days prior to its initiation date as required by then General Statutes (Rev. to 1979) § 19-73m. 3 Because of this failure coupled with Eagle *74 Hill’s failure to attempt to control costs, the commission determined that that portion of the request which was spent prior to or during the filing of the application, which was $539,396, should be denied. 4 In addition, the commission attached four conditions to its approval.

Eagle Hill appealed, on several grounds, to the Superior Court under then General Statutes (Rev. to 1979) § 19-73p (now General Statutes § 19a-158) and General Statutes § 4-183, which is part of the Uniform Administrative Procedure Act (UAPA). The court held that the commission had misconstrued § 19-73m; that its decision constituted a per se rule in violation of the UAPA; that the disapproved funds be approved and restored to Eagle Hill’s capital budget; and that the four conditions imposed by the commission be deleted as invalid. This appeal by the commission followed.

I

General Statutes (Rev.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Connecticut Insurance Guaranty Ass'n v. Drown
37 A.3d 820 (Connecticut Appellate Court, 2012)
CONNECTICUT INS. GUAR. ASS'N v. Drown
37 A.3d 820 (Connecticut Appellate Court, 2012)
Pierce v. Lantz
965 A.2d 576 (Connecticut Appellate Court, 2009)
Fjords North, Inc. v. Hahn
710 N.W.2d 731 (Supreme Court of Iowa, 2006)
Lombardo's Ravioli Kitchen, Inc. v. Ryan
47 Conn. Super. Ct. 540 (Connecticut Superior Court, 2002)
Abc v. State Ethics Commission of Ct, No. Cv 00 0504071 S (Dec. 12, 2001)
2001 Conn. Super. Ct. 16372 (Connecticut Superior Court, 2001)
Sweetman v. State Elections Enforcement Commission
732 A.2d 144 (Supreme Court of Connecticut, 1999)
Board of Educ. v. State Elections Enforc., No. Cv97-0569705 (Feb. 3, 1998)
1998 Conn. Super. Ct. 1519 (Connecticut Superior Court, 1998)
Soares v. Max Services, Inc.
679 A.2d 37 (Connecticut Appellate Court, 1996)
In the Matter of Reisman, (Dec. 19, 1995)
1995 Conn. Super. Ct. 14607 (Connecticut Superior Court, 1995)
Almeida v. Freedom of Information Commission
664 A.2d 322 (Connecticut Appellate Court, 1995)
Anziano v. Board of Police Commissioners
643 A.2d 865 (Supreme Court of Connecticut, 1994)
State v. Burns
642 A.2d 1230 (Connecticut Superior Court, 1994)
Anziano v. Board of Police Comm'rs, Madison, No. 33 62 21 (Nov. 5, 1993)
1993 Conn. Super. Ct. 9576 (Connecticut Superior Court, 1993)
In re Zoarski
632 A.2d 1114 (Supreme Court of Connecticut, 1993)
Marriott Retire. v. Conn., Hosp. Health, No. 30 28 83 (Sep. 24, 1992)
1992 Conn. Super. Ct. 8999 (Connecticut Superior Court, 1992)
Amsat Cable v. Woodgate at Enfield, No. Cv88-0096515 (Mar. 26, 1991)
1991 Conn. Super. Ct. 2181 (Connecticut Superior Court, 1991)
Deleo v. Environ. Prot. Bd., Stamford, No. Cv 87 0091028 S (Sep. 6, 1990)
1990 Conn. Super. Ct. 2045 (Connecticut Superior Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
477 A.2d 660, 2 Conn. App. 68, 1984 Conn. App. LEXIS 616, Counsel Stack Legal Research, https://law.counselstack.com/opinion/eagle-hill-corp-v-commission-on-hospitals-health-care-connappct-1984.