E. Materials Corp. v. Mitsubishi Plastics Composites Am., Inc.

307 F. Supp. 3d 52
CourtDistrict Court, E.D. New York
DecidedApril 4, 2018
Docket2:17–cv–01034 (ADS)(AYS)
StatusPublished
Cited by9 cases

This text of 307 F. Supp. 3d 52 (E. Materials Corp. v. Mitsubishi Plastics Composites Am., Inc.) is published on Counsel Stack Legal Research, covering District Court, E.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. Materials Corp. v. Mitsubishi Plastics Composites Am., Inc., 307 F. Supp. 3d 52 (E.D.N.Y. 2018).

Opinion

SPATT, District Judge:

The Plaintiffs Eastern Materials Corporation ("Eastern"), and Island Exterior Fabricators, LLC ("Island") (together, the "Plaintiffs") commenced this action against the Defendant, Mitsubishi Plastics Composites America, Inc. (the "Defendant" or "Mitsubishi") alleging claims of breach of contract, breach of warranty and negligence regarding materials supplied for a construction project in New York City.

Presently before the Court is a motion by the Plaintiffs, pursuant to Federal Rule of Civil Procedure (" FED. R. CIV. P. " or "Rule") 15 to amend the Plaintiffs' claims for breach of contract and breach of warranty, in accordance with this Court's Memorandum and Order dated September 19, 2017 (the "Order"). For the following reasons, the Plaintiffs' motion to amend is granted with respect to the breach of contract claim and denied with respect to the breach of warranty claim. As such, the Plaintiffs may only proceed with the breach of contract claim against Mitsubishi.

I. BACKGROUND

A. The Factual Background

As the Court has already detailed the factual allegations at issue in this motion in its Order, and the parties are familiar with the facts of this case, they will not be repeated here.

B. The Relevant Procedural History

On January 27, 2017, the Plaintiffs commenced this action by filing the complaint *56in the Supreme Court of the State of New York, Suffolk County. The complaint set forth three causes of action: breach of contract, negligence and breach of warranty.

On February 23, 2017, the Defendant filed a Notice of Removal, removing the action to this Court.

On March 20, 2017, the Defendant filed a motion to dismiss all of the Plaintiffs' claims pursuant to Rule 12(b)(6). In the Plaintiffs' opposition memorandum, the Plaintiffs agreed to withdraw their negligence claim.

In the Court's Order, dated September 19, 2017, the Court dismissed the Plaintiffs' First Amended Complaint ("FAC") without prejudice, finding both the breach of contract and breach of warranty claim insufficient. Specifically, the Court found that the breach of contract claim "failed to properly specify what the agreement ... consisted of and which provisions of any such agreement were violated." Order at 11-12. Further, the Court concluded that the Plaintiffs' consequential damages claim was conclusory. Id. at 12-15. With respect to the breach of warranty claim, the Plaintiffs failed to "provid[e] allegations as to the existence of an express promise or representation." Id. at 15-16. The Plaintiffs were granted leave to file a motion to amend the FAC in a manner consistent with FED. R. CIV. P. 15 within thirty days of the Order. Id. at 20.

On October 18, 2017, the Plaintiffs filed a motion to amend the FAC. Attached to the motion was a proposed Second Amended Complaint ("SAC"). As this motion was filed within thirty days of the Order, the Court deems it timely. The Plaintiffs claim that the breach of contract claim is addressed by identifying the contract, the terms at issue, and the nature of the breaches. Allegedly, the SAC "specifically pleads that consequential damages were both reasonably foreseeable and specifically contemplated by the parties at the time of contracting." Docket Entry ("DE") 15-1 at 5. The SAC also purportedly includes the warranty, the terms at issue, as well as the nature of the breaches. See id. at 4-5. The Defendant maintains that the Plaintiffs fail to correct the deficiencies of the FAC.

II. DISCUSSION

A. Standard of Review

FED. R. CIV. P. 15(a), which typically governs a motion to amend a complaint, states, in relevant part, "A party may amend its pleading only with the opposing party's written consent or the court's leave. The court should freely give leave when justice so requires." FED. R. CIV. P. 15(a)(2). Unless there is a showing of bad faith, undue delay, futility or undue prejudice to the non-moving parties, the district court should grant leave to amend. Foman v. Davis , 371 U.S. 178, 182, 83 S.Ct. 227, 9 L.Ed. 2d 222 (1962) ; Burch v. Pioneer Credit Recovery, Inc. , 551 F.3d 122, 126 (2d Cir. 2008) (per curiam) (stating that leave to amend "should generally be denied in instances of futility, undue delay, bad faith or dilatory motive, repeated failure to cure deficiencies by amendments previously allowed, or undue prejudice to the non-moving party."); Milanese v. Rust-Oleum Corp. , 244 F.3d 104, 110 (2d Cir. 2001) (internal citations omitted); Hemphill v. Schott , 141 F.3d 412, 420 (2d Cir. 1998).

The decision on whether to grant a motion to amend rests within the sound discretion of the district court. Aetna Cas. & Sur. Co. v. Aniero Concrete Co. , 404 F.3d 566, 603-04 (2d Cir. 2005) ; Hemphill , 141 F.3d at 420. In deciding whether to grant leave to amend, prejudice to the opposing party is one of the "most important"

*57issues to consider. AEP Energy Servs. Gas Holding Co. v. Bank of America, N.A. , 626 F.3d 699, 725 (2d Cir. 2010) (internal quotations omitted).

In considering whether a proposed amendment is futile, the Court must determine whether it could withstand a Rule 12(b)(6) motion to dismiss. Lucente v. IBM Corp. , 310 F.3d 243, 258 (2d Cir. 2002). When reviewing a motion to dismiss pursuant to Rule 12(b)(6), the Court must accept the factual allegations set forth in the complaint as true and draw all reasonable inferences in favor of the Plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
307 F. Supp. 3d 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-materials-corp-v-mitsubishi-plastics-composites-am-inc-nyed-2018.