E. J. Smith Construction Co. v. Burton

277 A.2d 84, 262 Md. 62, 1971 Md. LEXIS 906
CourtCourt of Appeals of Maryland
DecidedMay 11, 1971
Docket[No. 341, September Term, 1970.]
StatusPublished
Cited by8 cases

This text of 277 A.2d 84 (E. J. Smith Construction Co. v. Burton) is published on Counsel Stack Legal Research, covering Court of Appeals of Maryland primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. J. Smith Construction Co. v. Burton, 277 A.2d 84, 262 Md. 62, 1971 Md. LEXIS 906 (Md. 1971).

Opinion

Smith, J.,

delivered the opinion of the Court.

Appellee, William G. Burton t/a William G. Burton Nurseries (Burton), sued appellant E. J. Smith Construction Company, Inc. (Smith) for sums said to be due for “services, labor and materials” rendered Smith on two different jobs. Smith counterclaimed, contending that *64 Burton’s services were rendered “in a negligent unworkmanlike and unacceptable manner”. The case was tried without a jury by Judge Turner in the Circuit Court for Queen Anne’s County to which it had been removed. We shall affirm the judgment.

On appeal Smith assigns error on the entry of judgment against it, in the dismissal of its counterclaim, on the failure by the court to include the dismissal of the counterclaim in the written order appended to the memorandum opinion, and, finally, poses the question:

“Did the Court commit material and prejudicial error detrimental to the defendant appellant in the area of admissibility of evidence by relaxing or waiving strict rules of evidence in the one instance and applying a stricture in another instance, but in all instances detrimental to the appellant defendant corporation ?”

The trial judge in his opinion made the following findings of fact:

“It appears to the Court that the following essential facts were established by a preponderance of the evidence to the satisfaction of the Court, who heard the case sitting as a jury:
“(Facts below involve Friends House work Count One of Declaration)
“1. That there was an oral agreement to do certain work at the Friends House for about $6,-400; that Mr. Burton agreed to substitute hydro-seeding for the regular method of seeding, at no additional cost, so long as the yardage to be done remained the same. Mr. Burton had this work half done when requested by Defendant, E. J. Smith Construction Co., although it was November and Mr. Burton said ‘it was a bad time to seed,’ but Smith said, ‘do it as he wanted to finish and get out.’ Some seed did not come up, apparently.it did not germinate as had been predicted by Plaintiff.
*65 “2. That Plaintiff hydroseeded an area beyond that originally orally agreed upon; that Plaintiff, Mr. Burton, had attempted to obtain written plans for the Friends House job a year before the job was begun.
“3. That Defendant’s attorney authorized extras of the value of $855 for which Plaintiff had not been paid.
“4. That Plaintiff did use a mixture of seed containing rye, fescue, and blue grass purchased from Bolgianos, a most reputable seedsman.
“5. That Plaintiff has billed Defendant since April 17, 1968 for the Friends job; had no complaints about the work done until he started asking for payment for the job.
“6. That the work was properly done by the plaintiff, who for 35 years had been engaged in this type work. He employed approximately 60 men in nursery work. He has 5 hydroseeders with men who know how to operate them.
“7. That Plaintiff has not been paid the balance due on the Friends House job in the amount of $7,703.08.
“(Facts below involve Blow-Pierce job Count Two of Declaration)
“1. That the total contract for the Blow-Pierce School job was $12,300, and that Plaintiff had been paid on account $4,797; that extra sod was supplied at a reasonable cost of $675.
“2. That the job was 95% complete and that Mr. Wood had at one point agreed to that proportion of completion of the job that had been billed for by Mr. Burton.
“3. That Mr. Wood for the Defendant had importuned Mr. Smith not to pay the $5,000 on this job; and that Mr. Wood said that the failure to complete the Blow-Pierce job was not the fault of Mr. Burton.
*66 “4. That there is due and owing the sum of $7,563 on this job and that such amount is reasonable in the light of all the circumstances involved here as shown by the testimony and exhibits.
“It appears to the Court, from what Mr. E. J. Smith, Defendant, testified to, that he held back paying the Blow-Pierce job due to a dispute over the work on the Friends House job. Mr. Smith also promised in the course of these depositions, which were taken July 8, 1969, to furnish Mr. Burton an itemized statement of accounts between them within two weeks after the depositions were taken or about July 22, 1969. This was not done as promised and agreed by Defendant, Smith. Such conduct appears to this Court to be evading payment of the debt.”

(i)

JUDGMENT AGAINST SMITH

As Judge McWilliams put it for the Court in Blank v. Dubin, 258 Md. 678, 267 A. 2d 165 (1970), in speaking of a trial judge in a non-jury case:

“He was the trier of facts; he saw the witnesses; he heard them testify. Rule 886 a requires us to give ‘due regard’ to his ‘opportunity * * * to judge * * * [their] credibility.’ We cannot say his election to believe Dubin was clearly erroneous. Styka v. Styka, 257 Md. 464 (1970).” Id. at 680-81.

A careful review of the record persuades us that there was evidence from which Judge Turner could properly have made the findings he made. Accordingly, there was no error.

*67 (Ü)

DISMISSAL OF SMITH’S COUNTERCLAIM

On the issue of dismissal of the counterclaim Smith poses the question:

“Did the Court clearly err in dismissing the Counter-claim of the defendant appellant corporation in light of the relative positions of the parties herein as shown by the testimony and in consideration of the necessity of applying premise of truth to allegations and resolving all reasonable inferences in favor of the party against whom the Motion to Dismiss was made ?”

At the conclusion of the evidence of the defendant Smith—therefore, at the conclusion of the evidence of the counterplaintiff—and without presentation of evidence to rebut the counterclaim, the record reflects:

“MR. GORDON: Your Honor, I would like to make a motion to the counter-claim at this point.
“There is a counter-claim filed by the E. J. Smith Construction Company in which they claim that Mr. Burton acted in an unworkmanlike manner and an unacceptable manner, causing damage to the defendant and they ask for $12,000. Your Honor, I say they have proven nothing in their counter-claim, they have shown nothing.
“THE COURT: The Court agrees with you, and the counter-claim will be dismissed.”

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Montoya v. S.C.C.P. Painting Contractors, Inc.
589 F. Supp. 2d 569 (D. Maryland, 2008)
Imbesi v. Carpenter Realty Corp.
744 A.2d 549 (Court of Appeals of Maryland, 2000)
State v. Horsley
792 P.2d 945 (Idaho Supreme Court, 1990)
Higgins v. Barnes
530 A.2d 724 (Court of Appeals of Maryland, 1987)
First National Bank v. Shpritz
493 A.2d 410 (Court of Special Appeals of Maryland, 1985)
Baltimore Federal Savings & Loan Ass'n v. Gordon
321 A.2d 157 (Court of Appeals of Maryland, 1974)
Smith v. Johns Eastern Co.
305 A.2d 460 (Court of Appeals of Maryland, 1973)

Cite This Page — Counsel Stack

Bluebook (online)
277 A.2d 84, 262 Md. 62, 1971 Md. LEXIS 906, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-j-smith-construction-co-v-burton-md-1971.