E. H. Smith Contracting Co. v. City of New York

148 N.E. 655, 240 N.Y. 491, 1925 N.Y. LEXIS 758
CourtNew York Court of Appeals
DecidedJuly 15, 1925
StatusPublished
Cited by10 cases

This text of 148 N.E. 655 (E. H. Smith Contracting Co. v. City of New York) is published on Counsel Stack Legal Research, covering New York Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
E. H. Smith Contracting Co. v. City of New York, 148 N.E. 655, 240 N.Y. 491, 1925 N.Y. LEXIS 758 (N.Y. 1925).

Opinion

Andrews, J.

In March, 1913, the city of New York, acting by the Public Service Commission for the first district, entered into a contract with the appellant for the construction of over three miles of elevated railroad *494 in the borough of Queens. About four thousand feet consisted of concrete arches resting upon concrete pillars and the remainder was the ordinary steel overhead road. The contractor was to be paid at a unit price rate for the various classes of work to be done and materials to be furnished by him. The contract contained detailed specifications and referred to various drawings which accompanied it and which were said to indicate more particularly the details of the construction. Again it is stated that the dimensions and other characteristics of the railroad are more fully stated in the specifications forming a part of the contract and in the detailed drawings. The general idea, therefore, was to construct an elevated railroad in accordance with these papers. The project, however, so far as the concrete structure was concerned was an experimental one. No such railroad had been theretofore built in the city streets in that form and the Commission wisely enough reserved the right to make ' such alterations as experience might show were desirable or necessary. The commission,” article 15 of the contract states, “ further reserves the right to change the location, and to alter in any way it may deem necessary for the public interests, the drawings aforesaid in part or altogether at any time during the progress of the work without constituting grounds for any claim by the contractor for payment or allowance for damages or extra service other than as provided for items of the different classes of construction shown in the schedule, or where not susceptible of classification, then as otherwise provided herein.” Payment for work and materials that might be required by such possible alterations are regulated by article 12. “ In case any work or material shall be required to be done or furnished in or about the works — whether specified herein or indicated on the plans or not — which are not susceptible of classification under the schedule of unit prices, the contractor shall and will, if ordered by the engineer, do and perform such *495 work and furnish such materials at and for the actual and necessary net cost in money to the contractor for labor and for material, where new material is used, and in addition thereto ten per centum of such net cost for the use of tools and plant, superintendence and all other expenses incidental to the performance of such work and the furnishing of such material; and the contractor shall have no further claim in excess of the above; but this method of payment shall not apply to the performance of any work and the furnishing of any material which in part or in whole is susceptible of classification under such schedule, which work or material shall be paid for, in part or in whole as the case may be, at the unit price given in such schedule, except as herein otherwise expressly provided.”

The work was begun at once and completed in the fall of 1916. The Commission certified that it was accepted. There had been, however, many changes from the original design and when the final estimate was prepared it was rejected by the contractor. The dispute arose over these two clauses. The engineer of the Commission certified that payment should be made for these alterations at unit price rates. The actual cost of the work done and the materials furnished because of them plus ten per cent is concededly much over $100,000 above the price so fixed. The contractor claims that this work and these materials were not susceptible of classification under the unit price bid and that he is entitled, therefore, to the amount of this cost and ten per cent. That is the amount he received in the trial court, in some cases the jury finding that the work done was not so susceptible of classification and in others the court holding to the same effect as a matter of law. The Appellate Division has reversed the judgment in so far as it permitted the contractor to recover these items and has placed its reversal upon certain other provisions of-the contract. Article 24 provides: “ To prevent dis *496 putes and litigations, the engineer shall in all cases determine the amount, quality, acceptability and fitness of the several kinds of work and materials which are to be paid for under this contract; shall determine all questions in relation to the works and the construction thereof, and shall in all cases determine every question which may arise relative to the fulfillment of this contract on the part of the contractor. His determination and estimate shall be final and conclusive upon the contractor, and in case any question shall arise between the parties hereto, touching this contract, such determination and estimate shall be a condition precedent to the right of the contractor to receive any money under this contract.”

This provision, the Appellate Division says makes the engineer the final arbitrator in regard to the classification of this altered work ordered by the Commission. Such a classification does not call for a construction of the contract and there is no evidence of fraud or bad faith on the part of the engineer. Its reversal of the court below is purely on a question of law. No finding of the jury as to the facts is disaffirmed.

Without unduly extending this opinion it would be impossible for us to discuss each of the items involved in this itigation. It will be suffic ent to take three as examples and after determining the rule' applicable to them to summarily state our conclusions as to the others. We will, therefore, consider claim No. 34 for dressing the exterior surface of the concrete for which $34,734.38 is asked, claims Nos. 59, 3, 60 for steel used to build stations involving $18,988.12, and claim No. 42 for $7.16.

As has been said, some four thousand feet of this work was for a concrete elevated railroad. Various sections of the specifications must be referred to. Section 235 provides that the surfaces of the concrete masonry for ■the reinforced concrete elevated railroad shall be finished as indicated on the contract drawings, or as ordered, either with a natural cement finish rubbed, washed, *497 dressed, tooled or otherwise treated on the surface as directed, or with a mortar faced finish. * * * Immediately following the removal of the forms, followed by the removal of the projections and the filling of the voids, etc., herein provided, the entire concrete surface to be finished shall be treated in such a manner as directed, and so as to insure a uniform surface of the desired color and texture. Section 239: In order to remove the cement film and to obtain the desired surface treatment the wire brush, sand blast, pneumatic hammer or tools ordinarily used for dressing stone surfaces shall be used when required. Section 267: The work to be done under this contract upon or in connection with the reinforced concrete elevated railroad includes the furnishing and constructing complete in place of the finish of all exposed concrete surfaces * * * at the prices stipulated in items 6-B and 6-C. Item 6-B provided that the contractor should be paid seventeen and one-half cents per square yard for natural cement finish for the reinforced concrete elevated railroad in place.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

BOARD OF WATER & SEWER COM'RS v. Bill Harbert Const. Co.
870 So. 2d 699 (Supreme Court of Alabama, 2003)
Thomas Crimmins Contracting Co. v. City of New York
542 N.E.2d 1097 (New York Court of Appeals, 1989)
Thomas Crimmins Contracting Co. v. City of New York
138 A.D.2d 138 (Appellate Division of the Supreme Court of New York, 1988)
Arena Construction Co. v. Town of Harrison
71 A.D.2d 647 (Appellate Division of the Supreme Court of New York, 1979)
Savin Brothers, Inc. v. State
62 A.D.2d 511 (Appellate Division of the Supreme Court of New York, 1978)
Arc Electrical Construction Co. v. George A. Fuller Co.
247 N.E.2d 111 (New York Court of Appeals, 1969)
Joseph Davis, Inc. v. Merritt-Chapman & Scott Corp.
27 A.D.2d 114 (Appellate Division of the Supreme Court of New York, 1967)
Johnson, Drake & Piper, Inc. v. State
41 Misc. 2d 804 (New York State Court of Claims, 1964)
Tufano Contracting Corp. v. Port of New York Authority
36 Misc. 2d 1073 (New York Supreme Court, 1962)
Westcott v. State
264 A.D. 463 (Appellate Division of the Supreme Court of New York, 1942)

Cite This Page — Counsel Stack

Bluebook (online)
148 N.E. 655, 240 N.Y. 491, 1925 N.Y. LEXIS 758, Counsel Stack Legal Research, https://law.counselstack.com/opinion/e-h-smith-contracting-co-v-city-of-new-york-ny-1925.