Durrett Construction Co. v. Caldwell County

244 S.W. 409, 196 Ky. 158
CourtCourt of Appeals of Kentucky
DecidedOctober 20, 1922
StatusPublished
Cited by5 cases

This text of 244 S.W. 409 (Durrett Construction Co. v. Caldwell County) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Durrett Construction Co. v. Caldwell County, 244 S.W. 409, 196 Ky. 158 (Ky. Ct. App. 1922).

Opinion

Opinion op the Court by

Judge Moorman —

Affirming on original and cross appeals.

The opinion on the first appeal of this ease is reported in 180 Ky. 594. It was there held that the trial court erred in sustaining a demurrer to the 'answer, eonniterclaim and cross petition as amended, and also in refusing to permit a second amended answer, counterclaim and cross petitioii, tendered on June 4, 1917, to be filed. ¡On the return of the case to the circuit court, the issues were made conformable to the opinion of this court, the proof taken, and the case submitted. Judgment was rendered in favor of the Durrett Construction Company for $850.00, with interest thereon from June 1, 1916, at the rate of six per cent, per annum until paid. The Durrett Construction Company is prosecuting an appeal from that judgment, claiming that it is entitled to a judgment for $2,695.48, and Caldwell county, on cross appeal, is - asking a reversal of the judgment against it, and for [160]*160judgment against the construction company on its counterclaim.

It is the claim of the construction company that it contracted with the county for the construction, according to specifications set out in the petition, of a macadam road on what is known as the Cadiz-Princeton pike, at an estimated cost of $6,250.00, one-half thereof to be paid by the state; and that it was stipulated in the agreement that the work should be suspended, and the contract considered performed, when sufficient work was done to con-, sume the $6,250.00 appropriated on the contract. The construction company also claims that it has fully performed its contract, but has received therefor only $3,-336.59, whereas it is entitled to and there is still due it the additional sum of $2,837.45. By the answer and cross petition as amended the alleged completion of the contract was put in issue, and a counterclaim for damages on account of defects in the construction, aggregating $2,540.00, was asserted. As a further defense the county averred that the contract was made contrary to section 157 of the Constitution, in that the indebtedness thereby incurred was in excess of the county’s revenue for the year 1915. On the claims of the parties, thus briefly recited, the issues were made, and judgment was rendered. It is evident, from the character of judgment entered, that the trial court disallowed the county’s claim for defective construction, and also disallowed the defense asserted under section 157 of the Constitution. These questions we will briefly-consider before proceeding to discuss the issues on which «the court apparently based its decision.

With regard to the defectiveness of the construction, the evidence is somewhat conflicting’. There wias some evidence introduced by the county tending to show that the. work did not comply with the specifications, and especially that the rock put on the road was not of the specified dimensions, and was not properly rolled. Two or three witnesses testified on the latter point to the effect that in the spring following the putting down of part of the macadam the road showed evidence of instability. On the other hand, the proof for appellant clearly indicates that the specifications were strictly followed, and, furthermore, it appears that the county, road engineer and an inspector from the office of the State Highway Commissioner both, observed the work as it progressed [161]*161and apparently were satisfied with it. Whatever capacity they may have possessed with reference to determining the yardage of dirt that was moved and the quantity of macadam placed,' it cannot he denied that they had ample opportunity to examine appellant’s work as it progressed, and, having some practical knowledge of road building, were manifestly competent to determine whether the construction conformed to specifications. It is our opinion, therefore, that the counterclaim for defective construction should have been denied.

Nor have we been able to observe any merit in the defense that the fiscal court, in letting the contract, exceeded its authority under section 157 of the Constitution. The determination of that question depends on the facts in evidence, for it is certainly true, that if the appropriation for the work, whatever amount was done, exceeded the expendable revenues of the county for the year, to that extent there can be no recovery on the contract. Nevertheless, it was obligatory on the county to establish its defense in this respect, as it will be presumed that the fiscal court acted within its authority in letting the contract. And it may be stated here that the defense cannot be established by merely showing what the county received and expended for the year, but the state of the county finances at the date when the contract was made must also be shown. To meet this requirement it was necessary for the county to show what indebtedness it had incurred prior to the making of the contract, and also the total of the county’s fixed constitutional and statutory expenses for the balance of the year. Furthermore, in arriving at the income of the county for the year, it was necessary to prove what revenue would be collected under the highest tax rate allowed by law, and under the final assessment of all assessable property in the county, together with any other revenues that the county would receive during the year, including the cash that it then had on hand. City of Providence v. Providence Electric Light Co., 122 Ky. 237; Lawrence County v. Lawrence Fiscal Court, 130 Ky. 587; Mitchell v. Knox County Fiscal Court, 165 Ky. 543; and Carter, etc., v. Krueger & Son, etc., 175 Ky. 399. The exhibit filed by the county clerk, showing the amount of taxes collected and the expenditures made, is wholly insufficient to meet these requirements, and this is true, even if the alleged indebtedness of approximately $19,000.00, brought over [162]*162from preceding years, be considered in arriving at the fixed expenses for the year 1915. It is not shown in the statement of expenditures for that year when the appropriations for the expenditure's were made, with reference to the date of the contract in question, and, therefore, the priority of right as between them and the indebtedness in dispute here is unascertainable. In view of these deficiencies in the proof, the presumption that the fiscal court acted within its constitutional authority is conclusive.

It appears from the record that on November 24, 1915, the construction company submitted to the fiscal court an estimate of the work then performed. This estimate was approved by the county engineer and the state road inspector. It amounted to $2,695.48. There was then issued to the construction company a warrant for $2,156.39 in full payment for the work, less twenty per cent, which the county had the right to retain under the contract. A similar statement, approved by the same officers, was submitted on December 29, 1915, amounting to $1,475.25, and thereupon there was issued to the construction company a warrant for $1,180.20 in full payment for the work, less the retained percentage. Thereafter the construction company did other work, and, conceiving that it had done sufficient work to consume the entire amount appropriated on the contract, it submitted a bill for $2,003.31. That bill, however, was not approved by the county engineer or the state inspector, both declining to approve it on the ground that it, with the previous estimates, represented a great deal more work than had actually been done.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rowan County v. Banksmiller Supply Co.
95 F.2d 904 (Sixth Circuit, 1938)
Masonic Widows' & Orphans' Home v. City of Corbin
17 S.W.2d 215 (Court of Appeals of Kentucky (pre-1976), 1929)
Pulaski County v. Richardson, Co. Treasurer
9 S.W.2d 523 (Court of Appeals of Kentucky (pre-1976), 1928)
Cahill-Swift Manufacturing Co. v. City of Bardwell
294 S.W. 171 (Court of Appeals of Kentucky (pre-1976), 1927)
City of Covington v. O. F. Moore Co.
290 S.W. 1066 (Court of Appeals of Kentucky (pre-1976), 1927)

Cite This Page — Counsel Stack

Bluebook (online)
244 S.W. 409, 196 Ky. 158, Counsel Stack Legal Research, https://law.counselstack.com/opinion/durrett-construction-co-v-caldwell-county-kyctapp-1922.