Caldwell County v. Durret Construction Co.

203 S.W. 291, 180 Ky. 594, 1918 Ky. LEXIS 98
CourtCourt of Appeals of Kentucky
DecidedMay 17, 1918
StatusPublished
Cited by2 cases

This text of 203 S.W. 291 (Caldwell County v. Durret Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals of Kentucky primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Caldwell County v. Durret Construction Co., 203 S.W. 291, 180 Ky. 594, 1918 Ky. LEXIS 98 (Ky. Ct. App. 1918).

Opinion

Opinion of the Court by

Judge Miller

Reversing.

In 1915, the fiscal court of Caldwell county determined to construct so much of a turnpike road leading from Cadiz to Princeton as was located in Caldwell county, at an estimated expense of $6,250.00, one-half thereof to be paid by the State.

The contract for the. construction of the road was awarded to the Durret Construction Company under the provisions of the act of 1914, commonly known as the State Aid Act, and constituting section 4356X of Carroll’s Kentucky Statutes. The plans, profiles, and specifications for the improvement, and the contract with the Chicago Bonding & Surety Company as surety thereon, were submitted to and approved by the state commissioner of public roads as required by sections 10 and 11 of the statute, supra.

The contract provided that the contractor should be paid 80% of the contract price of his work as it progressed; and further that when the cost of the work which had been finished amounted to as much as $6,250.00, the sum available for road purposes, the work should cease. Pursuant to section 14 of the statute, the state road commissioner appointed Barnum Davis as [596]*596state road inspector to represent the state’s interest in Caldwell county.

The Durret Construction Company began work on the road in October, 1915, and continued the work, with some intermissions during the winter, until June, 1916, when it ceased work, claiming it had completed its contract. On November 24, 1915, pursuant to section 15 of the statute, the state road inspector and the county road engineer certified to the fiscal court, in writing, that the construction company had performed certain portions of its work under its contract, and that there was then due it for said work the aggregate sum of $2,695.48, of which 20% ($539.09) should be retained under the terms of the contract.

Again, on December 29, 1915, a similar certificate was issued to the court showing the contractor had further performed work of the aggregate value of $1,475.25, of which 20% ($295.05) should be retained. The fiscal court paid these two estimates; but the record fails to show what orders were entered upon its records, if any, in that connection. At that time the contractor had about finished the excavation and grading work, and was proceeding’ with the work of macadamizing the road by putting on the rock, rolling it, etc.

The construction company proceeded with the work of surfacing the road until sometime in June, 1916, when it claims it had- done work of the value of $2,003.32, in addition to that embraced in the two estimates .above referred to; and as these three items consumed the $6,250.00 which had been appropriated for this purpose the company ceased work. Up to this time there had been no dispute between the county and the contractor as to the amount of work done, or the amount of money due therefor; but when the contractor ceased -work in June, 1916, claiming it had finished its work, the county contended that it had not completed its contract, and refused to pay the construction company for the work it had done in the spring of 1916; and, it further claimed that the construction company had not performed the amount of work which it claimed it had done under the first two estimates furnished in November and December, 1915.

The state inspector and the county road engineer refused to certify to the amount of work claimed to have been performed by the contractor in the spring of 1916.

[597]*597The fiscal court entered an order reciting the fact that the construction company had not completed its contract and calling upon it to return and complete it; and a copy of this order was served upon the construction company and its surety.

The county filed an answer and counter-claim traversing the allegations of the petition as to the completion of the work as required by the contract; made it a cross-petition against the Chicago Bonding & Surety Company; and asked a judgment against the construction company and its surety for $2,540.00, in damages. By an amendment the allegations of this pleading were made more specific. The circuit court, at first, overruled demurrers to the answer, counter-claim and cross-petition; but, upon the demurrers being renewed, the court sustained them.

By a second amended answer, counter-claim, and cross-petition tendered by the county on June 4th, 1917, it charged that the construction company had practiced' fraud upon it in constructing the highway, and that the indebtedness created by the contract exceeded the county’s revenue for that year. The court refused to permit the amendment to be filed, dismissed the counterclaim and cross-petition, and entered judgment against the county for the sum of $2,837.45, prayed for.

As grounds for a reversal appellant insists: (1) that a judgment should not have been entered for the full amount found to be due to the contractor, because under the contract, 5% thereof ($321.50) would not be due until one year after the approval of the work by the state road commissioner as provided by subsection 12 of section 4356X, of the Kentucky Statutes, and by the terms of the contract; (2) that the court erred in sustaining the demurrer to the counter-claim which stated a cause of action for damages for the improper construction of the road; (3) that the court erred in sustaining the demurrer to the answer which traversed the plaintiff’s claim for work done under the contract; and, (4) that the court erred in refusing to permit it to file its amended answer and counter-claim charging fraud against the construction company.

Subsections 12 and 15 of section 4356X of the Kentucky Statutes, read as follows: [598]*598set forth in said contract, and at least five per centum of the contract price shall not be paid to the contractor until after the expiration of one year from the completion of the -work and acceptance thereof in writing by the commissioner of public roads. ’

[597]*597“12. The time and manner of payment for work done under any contract awarded under this act shall be
[598]*598“15. Where any contract provides fox partial payment based upon the amount of work done, it shall be the duty of the inspector as each payment becomes due to present to the fiscal court a certificate signed by such inspector and the county road engineer, in which certificate shall be stated as nearly as can be the amount of work done for which payment is to be made and that the same has been done in all respects in strict compliance with the contract, plans and specifications. When the work under contract shall have been fully completed the inspector and county road engineer shall prepare a detailed and itemized statement in quadruplicate of the cost, of the improvement, certifying the same, one copy of which shall be filed with the fiscal court of the county, one with the county road engineer and two with' the state commissioner of public roads.”

1.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Shreve v. Taylor County Public Library Board
419 S.W.2d 779 (Court of Appeals of Kentucky (pre-1976), 1967)
Durrett Construction Co. v. Caldwell County
244 S.W. 409 (Court of Appeals of Kentucky, 1922)

Cite This Page — Counsel Stack

Bluebook (online)
203 S.W. 291, 180 Ky. 594, 1918 Ky. LEXIS 98, Counsel Stack Legal Research, https://law.counselstack.com/opinion/caldwell-county-v-durret-construction-co-kyctapp-1918.