Dunlop Tire Corp. v. I.M.E. of Miami, Inc

CourtCourt of Appeals for the Tenth Circuit
DecidedOctober 6, 2000
Docket00-5007
StatusUnpublished

This text of Dunlop Tire Corp. v. I.M.E. of Miami, Inc (Dunlop Tire Corp. v. I.M.E. of Miami, Inc) is published on Counsel Stack Legal Research, covering Court of Appeals for the Tenth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dunlop Tire Corp. v. I.M.E. of Miami, Inc, (10th Cir. 2000).

Opinion

F I L E D United States Court of Appeals Tenth Circuit UNITED STATES COURT OF APPEALS OCT 6 2000 FOR THE TENTH CIRCUIT PATRICK FISHER Clerk

DUNLOP TIRE CORPORATION,

Plaintiff-Appellant, No. 00-5007 v. (D.C. No. 98-CV-456-H(E)) (N.D. Okla.) I.M.E. OF MIAMI, INC.,

Defendant-Appellee.

ORDER AND JUDGMENT *

Before BRORBY , PORFILIO , and MURPHY , Circuit Judges.

After examining the briefs and appellate record, this panel has determined

unanimously to grant the parties’ request for a decision on the briefs without oral

argument. See Fed. R. App. P. 34(f); 10th Cir. R. 34.1(G). The case is therefore

ordered submitted without oral argument.

Plaintiff Dunlop Tire Corporation appeals from an order of the district

court denying its motion for a new trial. We reverse and remand.

* This order and judgment is not binding precedent, except under the doctrines of law of the case, res judicata, and collateral estoppel. The court generally disfavors the citation of orders and judgments; nevertheless, an order and judgment may be cited under the terms and conditions of 10th Cir. R. 36.3. In February 1997, Dunlop contracted with I.M.E. to rebuild a tire press

Dunlop planned to use on a new production line. The contracted delivery date

was June 23, 1997. On May 20, I.M.E. notified Dunlop it was anticipating delays

in the delivery of necessary parts. Although remaining optimistic that it could

complete the project on time, I.M.E. requested a later delivery date. On June 19,

Dunlop sent I.M.E. a letter invoking the penalty clause of the contract as of

June 27, but giving I.M.E. until July 12 to complete the project. 1 On July 1,

1997, Dunlop terminated the contract in anticipation of I.M.E.’s inability to meet

the July 12 completion date. Dunlop obtained possession of the press and hired

another company to complete the project.

Dunlop then commenced this action seeking the costs it incurred to have

the job completed, as well as liquidated damages. I.M.E. counterclaimed for the

work it had completed but for which it was not paid. The case was tried to a

jury, which found for I.M.E. Dunlop moved for a new trial on the ground that

the jury ignored the overwhelming weight of the evidence and based its verdict

on sympathy, prejudice or issues not before it. The court denied the motion and

Dunlop appeals.

1 The district court held that this letter constituted a novation of the contract setting a new delivery date of July 12. Neither party challenges this legal determination.

-2- On appeal, Dunlop argues the district court erred in not granting its motion

for a new trial. Dunlop asserts that in order to find for I.M.E., the jury had to

determine that Dunlop was the sole cause of I.M.E.’s failure to complete the

contract on time. Dunlop maintains the evidence shows that it was not

responsible for I.M.E.’s delay.

We review the trial court’s denial of a motion for a new trial on the ground

that the jury’s verdict is against the weight of the evidence for “a manifest abuse

of discretion.” Blanke v. Alexander , 152 F.3d 1224, 1235 (10th Cir. 1998) ;

see also Gasperini v. Center for Humanities, Inc. , 518 U.S. 415, 433 (1996)

(federal trial judge has “discretion to grant a new trial if the verdict appears to

[the judge] to be against the weight of the evidence.”). We will hold that the

district court abused its discretion in denying a motion for a new trial where

“the verdict is clearly, decidedly, or overwhelmingly against the weight of the

evidence.” Black v. Hieb’s Enter., Inc. , 805 F.2d 360, 363 (10th Cir. 1986).

-3- Relevant Instructions

Each party asserted the other was in breach of the contract. 2 See

Appellant’s App. at 55, 56. The jury instructions outlined the competing claims

in some detail. Dunlop’s cause of action was explained as follows:

Dunlop claims that it is entitled to damages from I.M.E. due to breach of contract, because I.M.E. failed to deliver the tire press to Dunlop as provided in their agreement. Dunlop further claims that as a result, it cancelled its contract with I.M.E. in accordance with the terms of the agreement.

Dunlop claims that it was justified in cancelling the contract with I.M.E. once it concluded that the Defendant was unable to meet the July 12, 1997 completion date. If you find that Dunlop’s conduct was not the sole cause of I.M.E.’s inability to meet the July 12 deadline , and that it was reasonable for Dunlop to conclude that the equipment could not be completed by July 12, then you must find for Dunlop .

Id. at 57 (emphasis added).

I.M.E.’s counterclaim was then explained:

I.M.E. claims that it is entitled to damages from Dunlop due to breach of contract. In particular, I.M.E. claims that Dunlop breached the implied covenant of good faith and fair dealing in the contract. . . . This covenant embodies an implicit understanding that neither party will intentionally do anything to prevent the other party from carrying out its part of the agreement.

2 The jury instructions stated: “A contract is breached or broken when a party does not do what it promised to do in the contract. When one party has breached a contract, subsequent failure of the other party to do what it promised under the contract does not constitute a breach.” Appellant’s App. at 58.

-4- In this case, I.M.E. claims that Dunlop’s conduct was such as to interfere with I.M.E.’s ability to complete the contract in a timely manner. If you find that the [sic] Dunlop’s conduct was the sole cause of I.M.E.’s delay, then you must find in favor of I.M.E.

Id. at 56 (emphasis added).

As the emphasized passages in the instructions reflect, Dunlop’s cause of

action turned on negating the very premise of I.M.E.’s counterclaim, i.e., that

Dunlop’s conduct was the sole cause of I.M.E.’s inability to perform on time.

In light of this overlap, the parties agreed to reverse the usual order of

deliberations. Consequently, the jury was instructed that “[b]ecause of the way

the law applies to the facts of this case, it is necessary for you to decide I.M.E.’s

[counter]claim first.” Id. at 55.

Evidence

Evidence was adduced at trial that, at least facially, supported I.M.E.’s

basic allegation that Dunlop had breached the contract. Specifically, Dunlop had

been late paying I.M.E. a substantial interim invoice, had been late in providing

necessary approval of certain items (though Dunlop offered evidence in excuse

of this delay), and had terminated the contract prior to the completion date of

July 12. Indeed, this evidence appears to be the focus of the district court’s order

denying Dunlop’s motion for new trial, in which the court stated “that there was

sufficient evidence adduced at trial to support the jury’s conclusion that Dunlop

-5- breached the contract. Therefore, the Court concludes that this is not an

exceptional case in which the verdict is clearly, decidedly, or overwhelmingly

against the weight of the evidence.” Id. at 114.

However, I.M.E.’s counterclaim and defense to Dunlop’s cause of action,

as outlined in the instructions , clearly required more than a mere breach by

Dunlop. I.M.E.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Dunlop Tire Corp. v. I.M.E. of Miami, Inc, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dunlop-tire-corp-v-ime-of-miami-inc-ca10-2000.