Duke Energy Florida, LLC v. Gary F. Clark, etc.

CourtSupreme Court of Florida
DecidedJuly 7, 2022
DocketSC20-1601
StatusPublished

This text of Duke Energy Florida, LLC v. Gary F. Clark, etc. (Duke Energy Florida, LLC v. Gary F. Clark, etc.) is published on Counsel Stack Legal Research, covering Supreme Court of Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duke Energy Florida, LLC v. Gary F. Clark, etc., (Fla. 2022).

Opinion

Supreme Court of Florida ____________

No. SC20-1601 ____________

DUKE ENERGY FLORIDA, LLC, Appellant,

vs.

GARY F. CLARK, etc., et al., Appellees.

July 7, 2022

LAWSON, J.

Duke Energy Florida, LLC (DEF), appeals a final order of the

Florida Public Service Commission (Commission) denying DEF’s

request to recover approximately $16 million from its customers for

costs DEF incurred to meet its customers’ demand for electricity

when a 420-megawatt (MW) steam-powered generating unit went

offline at its Bartow plant in 2017 and was placed back in service at

a derated capacity of 380 MW. We have jurisdiction, see art. V,

§ 3(b)(2), Fla. Const.; § 350.128(1), Fla. Stat. (2020), and for the reasons explained below reverse the Commission’s order and

remand for entry of an order awarding the costs.

I. Background

A. Summary of Dispute Below

To prevail below and recover the $16 million in costs, DEF had

to prove by a preponderance of the evidence that its actions and

decisions leading up to and in restoring the steam unit to service

were “prudent.” See § 366.06(1), Fla. Stat. (2021) (requiring that

costs be “prudently invested by the public utility company”); see

also Sierra Club v. Brown, 243 So. 3d 903, 908 (Fla. 2018) (“It is

from [section 366.06(1)] that the Commission derives its prudence

standard, which it applies to ensure that the recovered costs result

from prudent investments.”). The “standard for determining

prudence is . . . ‘what a reasonable utility manager would have

done, in light of the conditions and circumstances that were known,

or should [have] been known, at the time the decision was made.’ ”

S. All. for Clean Energy v. Graham, 113 So. 3d 742, 750 (Fla. 2013)

(quoting In re Nuclear Cost Recovery Clause, Docket No. 110009-EI,

Order No. PSC-11-0547-FOF-EI, 2011 WL 5904236, at 26 (Fla. Pub.

Serv. Comm’n, 2011)). -2- The Commission referred critical factual issues to the Division

of Administrative Hearings for a closed hearing before an

administrative law judge (ALJ) after concluding that trying these

issues would reveal confidential information that could not be

disclosed and discussed in the Commission’s open hearing. After

the closed hearing, the ALJ entered a recommended order denying

cost recovery, which the Commission adopted in the final order on

appeal.

i. The plant and its operational history

The Bartow plant consists of four natural-gas-fueled

combustion turbines (CT) and a much larger steam turbine. Each

of the four CTs compress ambient air, mix it with natural gas, and

ignite the mixture to produce a hot gas. The heated air-fuel mixture

expands through the CT blades, causing each CT to rotate its shaft.

The spinning shaft of each CT independently drives its own

generator that produces electricity. Then, hot waste gas that

exhausts from each CT is used to create steam that similarly

rotates the larger steam turbine, thereby powering the larger fifth

electrical generator.

-3- When constructing the plant, DEF purchased an “after-

market” steam turbine that Mitsubishi had originally designed for

another plant, where it was intended to run on steam created from

the exhaust of three CTs with a steam supply capable of generating

420 MW, which Mitsubishi had also listed as the nameplate

capacity of the steam turbine at the time of manufacture.

When the plant was placed online in 2009, however, DEF

operated the steam unit using steam produced from the waste heat

from all four CTs, producing electricity from the attached generator

well above the steam turbine’s nameplate capacity. Because the

steam-powered generator produced electricity using waste heat,

operating this portion of the plant in this manner would have been

cost-effective.

However, during a routine inspection in March 2012, DEF

discovered unusual wear or damage to the steam turbine’s blades,

which required DEF to replace them. The parties refer to this initial

period of operation, from June 2009 to March 2012, as Period 1.

Although the steam turbine was not routinely operated above 420

MW after Period 1, the replacement blades suffered similar damage

and had to be replaced again in 2014, twice in 2016, and again in -4- 2017 during the forced outage at issue in this case. The parties

mark the operational time between each blade replacement as a

separate period: Period 2 starts in April 2012 and ends in August

2014; Period 3 starts in December 2014 and ends in April 2016;

Period 4 starts in May 2016 and ends in October 2016; and, finally,

Period 5 starts in December 2016 and ends in February 2017.

In 2017, at the end of Period 5, DEF decided against

reinstalling any of the previous blade types—as they all experienced

damage—and installed a pressure plate which derated the steam

unit from 420 MW to 380 MW. This caused DEF to incur the

replacement power costs that it now seeks to recover. The pressure

plate remained in the steam turbine until Mitsubishi installed

redesigned turbine blades in December 2019. The blades installed

in 2019 have apparently been performing normally, without

unusual wear or damage.

ii. Factual issues tried before the ALJ

The evidence presented to the ALJ primarily focused on

whether the steam turbine’s 420 MW nameplate capacity

constituted an operational limit of the unit, such that DEF acted

imprudently in Period 1 (from June 2009 to March 2012) by -5- regularly operating the steam turbine above its nameplate capacity

without first consulting with Mitsubishi.

DEF offered testimony from its Vice President of Generation,

Jeffrey Swartz, who testified that the nameplate capacity is an

estimate of ultimate generator output and not an operational

limitation on the steam turbine. He explained that the operational

parameters for the steam turbine were supplied by Mitsubishi and

were expressed in permissible pressure and temperature

combinations, or limitations, which DEF did not exceed. 1 Mr.

Swartz further testified that Mitsubishi should have designed all

components of the steam turbine to operate without undue wear or

damage so long as the unit was being operated within the heat and

pressure parameters Mitsubishi provided to DEF when the steam

unit was being placed into service. If this were true, it would have

been prudent for DEF to operate its Bartow plant to regularly

1. DEF’s expert explained that the utility measures the heat and pressure of the steam entering the turbine, with these factors determining the mass flow of steam entering the turbine. Increased heat and pressure mean an increased steam flow into the turbine and a higher energy output to the generator, resulting in a higher electrical output from the generator. -6- produce extra low-cost electricity from the generator despite the

steam turbine’s 420-MW nameplate capacity.2

By contrast, the Office of Public Counsel (OPC) offered

testimony from a retained expert, Richard Polich, who testified that

420 MW represented the design limit of the steam turbine such that

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Commission on Ethics v. Barker
677 So. 2d 254 (Supreme Court of Florida, 1996)
Heifetz v. Dept. of Business Regulation
475 So. 2d 1277 (District Court of Appeal of Florida, 1985)
Sierra Club v. Julie Imanuel Brown, etc.
243 So. 3d 903 (Supreme Court of Florida, 2018)
Southern Alliance for Clean Energy v. Graham
113 So. 3d 742 (Supreme Court of Florida, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Duke Energy Florida, LLC v. Gary F. Clark, etc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/duke-energy-florida-llc-v-gary-f-clark-etc-fla-2022.