Duke Energy Corp. v. Fed. Energy Regulatory Comm'n

892 F.3d 416
CourtCourt of Appeals for the D.C. Circuit
DecidedJune 15, 2018
Docket16-1133
StatusPublished
Cited by3 cases

This text of 892 F.3d 416 (Duke Energy Corp. v. Fed. Energy Regulatory Comm'n) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Duke Energy Corp. v. Fed. Energy Regulatory Comm'n, 892 F.3d 416 (D.C. Cir. 2018).

Opinion

Opinion for the Court filed by Circuit Judge TATEL.

TATEL, Circuit Judge : To prepare for a bitterly cold day during the January 2014 "polar vortex," Duke Energy Corporation, a generator of electricity, purchased exceptionally expensive natural gas, which it ended up not needing. Claiming that its regional transmission organization, PJM Interconnection, had directed it to purchase the gas and that the governing tariff provided for indemnification, Duke sought reimbursement for its losses. PJM rejected Duke's claim, as did the Federal Energy Regulatory Commission (FERC). For the reasons set forth in this opinion, we deny Duke's petition for review.

I.

The United States electrical grid has been described as "the most complex machine ever made." Phillip F. Schewe, The Grid: A Journey Through the Heart of Our Electrified World 1 (2007). Fortunately, only a few details are necessary to understand this case.

PJM Interconnection, L.L.C., Intervenor here, a regional transmission organization, operates the transmission system spanning all or part of thirteen mid-Atlantic and Midwestern states. PJM also manages the markets in which electricity is bought and sold within this territory.

Most electricity is traded in PJM's "day-ahead market." Generators offer electricity into that market by noon each day, including in their offers not only the price, but also the amount of notice they will need to provide the electricity. Based on predicted demand, PJM then derives a market-clearing price for all sales to be made the next day and, by 4 P.M., notifies generators whether and when they are scheduled to run. Even if a generator is scheduled to run, however, PJM may or may not call on it to provide energy, depending on demand and other variables.

PJM also manages a yearly "capacity market." "The capacity market is designed to ensure sufficient resources are available to maintain the reliability of the system." Duke Energy Corp. v. PJM Interconnection, L.L.C. , 151 FERC ¶ 61,206 , 62,279 (2015) (Initial Order). Generators bid into that market to become Generation Capacity *418 Resources-generators paid to offer all of their available capacity into the day-ahead market and to operate if called upon by PJM. As FERC explained while interpreting a similar tariff, "economic considerations are irrelevant to determining whether a unit is physically available." New England Power Generators Association, Inc. v. ISO New England Inc. , 144 FERC ¶ 61,157 , 67,902-03 (2013) (internal quotation marks omitted).

Petitioners, Duke Energy Corporation and various other related corporate entities ("Duke"), are members of the PJM Tariff, a contract between PJM and the member utilities. Duke operates the Lee Facility, located 90 miles west of Chicago, which has eight eighty-megawatt natural-gas-fired combustion turbines. In 2014, the year at issue here, Duke's Lee Facility functioned as a Generation Capacity Resource.

In January of 2014, extreme cold temperatures and wintry conditions affected much of the Eastern United States, resulting in a dramatic increase in demand for electricity. Coupled with a pipeline explosion in Canada, this "polar vortex" caused natural gas prices to spike. Duke normally obtained its gas through an agreement with Natural Gas Pipeline Company (NGPL), under which it could take gas as needed throughout the day. During the polar vortex, however, NGPL instituted several restrictions that made gas purchases both riskier and less convenient. No longer able to take gas as needed, Duke had to reserve it well in advance. This situation, combined with the extreme weather, created a perfect storm for generators like Duke.

The events at issue here took place on January 27, 2014, when PJM projected that energy demand for the next day would be 140,000 megawatts, well above previous record peaks. Such an extreme demand posed a serious risk of power outages during subzero temperatures. At 8:45 A.M., PJM issued an emergency announcement to generators, informing them of the projected emergency and issuing what the Tariff calls a "maximum emergency generation alert." Transcript of Automated Call from Kevin Etch, PJM, to Brian Murrell, Duke (Jan. 27, 2014, 08:45 EPT), Joint Appendix (J.A.) 140. Under the Tariff, that alert obliged all generators, including Duke, to "comply with all directions from [PJM] for the purpose of managing, alleviating, or ending an Emergency." PJM Tariff, Att. K § 1.7.11(a), J.A. 380.

Upon hearing the alert, Duke's Managing Director of Generation and Dispatch, Greg Cecil, faced a difficult choice: he could buy gas before noon, when it was cheapest, though he would risk losing money if the Lee units never needed to run; alternatively, he could postpone purchasing gas until he knew whether the Lee units were scheduled to run, though in that case he would risk paying more for gas. Seeking advice, Cecil called PJM's dispatch desk and spoke to Master Dispatcher Nathan Marr to discuss whether Duke should pre-purchase gas. This was the first of three back-to-back conversations that lie at the heart of the dispute before us.

In the first conversation, Cecil informed Marr that "gas is very difficult" at the Lee facility, "[b]ut, I might be able to buy some day ahead and have it scheduled ratably for tomorrow." Transcript of Telephone Call from Greg Cecil, Duke, to Nathan Marr, PJM (Jan. 27, 2014, 08:53 EPT), J.A. 141 (First Conversation). Cecil emphasized, however, that if he did purchase the gas, he needed "to be able to come on"; that is, he needed PJM to call on the Lee units to provide power. Id. Marr replied that he "[could not] anticipate what is going to be the situation," but explained that, given the emergency situation, "more than *419 likely, your units will be running. ... I can't guarantee 100% that you will be on. 99.9% you will run though." Id. , J.A. 142.

In response, Cecil explained that because gas was very expensive, "I may be able to [pre-purchase gas] for some of the [Lee units] but probably not all of them." Id. Marr replied that "[w]e want all units available for tomorrow." Id. And though Cecil objected that "[g]as is my limiting factor," Marr spoke over him: "If you can secure gas, we would advise you to secure gas for your units. We want all units available for tomorrow." Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
892 F.3d 416, Counsel Stack Legal Research, https://law.counselstack.com/opinion/duke-energy-corp-v-fed-energy-regulatory-commn-cadc-2018.