Dudley Construction, LTD. v. Cross Roads Concrete Services, INC.

CourtCourt of Appeals of Texas
DecidedOctober 2, 2025
Docket10-24-00225-CV
StatusPublished

This text of Dudley Construction, LTD. v. Cross Roads Concrete Services, INC. (Dudley Construction, LTD. v. Cross Roads Concrete Services, INC.) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dudley Construction, LTD. v. Cross Roads Concrete Services, INC., (Tex. Ct. App. 2025).

Opinion

Court of Appeals Tenth Appellate District of Texas

10-24-00225-CV

Dudley Construction, Ltd., Appellant

v.

Cross Roads Concrete Services, Inc., Appellee

On appeal from the 272nd District Court of Brazos County, Texas Judge John L. Brick, presiding Trial Court Cause No. 22-000952-CV-272

JUSTICE SMITH delivered the opinion of the Court.

MEMORANDUM OPINION

Dudley Construction, Ltd. appeals from the trial court’s judgment,

rendered after a trial before the court, in this breach of contract suit brought

by Cross Roads Concrete Services, Inc. In six issues, Dudley complains of the

trial court’s findings of fact and conclusions of law, the award of prejudgment

interest, and the trial court’s failure to properly interpret Dudley’s contractual

rights and to incorporate the terms of the parties’ Rule 11 Agreement into the judgment. Because we agree the award of prejudgment interest is erroneous,

we modify the judgment to delete that award. We affirm as modified.

BACKGROUND

Dudley, as general contractor, contracted with the City of College Station

on a project to build an athletic complex. Cross Roads, a subcontractor on the

project, did not construct box culverts in accordance with the requirements for

the project. Rather than removal and replacement of the defective box

culverts, the City accepted an alternative repair technique. However, the City

initially wanted Dudley to furnish an eight-year extended warranty to correct

any future issues, backed up with a bond. Dudley demanded that Cross Roads

provide the warranty and bond. Cross Roads completed the alternative

repairs, but did not provide a warranty secured by a bond.

Concerned about Dudley’s potential liability to the City, Dudley withheld

payment to Cross Roads, waiting for Cross Roads to obtain a bond. Cross

Roads filed suit against Dudley for breach of contract and breach of fiduciary

duty due to nonpayment of amounts owed to Cross Roads. Dudley filed a

counterclaim for breach of contract.

A trial before the court was held in January 2023. The parties signed a

Rule 11 Agreement in February 2023 addressing Dudley’s concerns about

potential liability to the City. In the Agreement, Dudley agreed to provide

Dudley Constr., Ltd. v. Cross Roads Concrete Servs., Inc. Page 2 Cross Roads and the City a video of Dudley’s inspection of the culverts, and

Cross Roads agreed to obtain specified documents from the City. Cross Roads

was also to submit a maintenance agreement to the City for its approval. The

maintenance agreement was to be secured by a bond and was to end

on June 2, 2027, eight years after the box culvert was completed. The Rule 11

Agreement provided that, if the City failed to execute all of the documents

and/or does not accept the maintenance agreement, the parties will provide the

trial court with a report on the documents and any arrangements on the

maintenance agreement. Finally, the Rule 11 Agreement provided that “[t]he

Court will consider this written report in its ruling for judgment.”

In October 2023, the trial court granted Cross Roads’s motion to sever

and entered an order severing all of Dudley’s claims and causes of action

asserted in this matter against Cross Roads.

On January 8, 2024, the trial court signed a judgment in favor of Cross

Roads, ordering that Cross Roads recover from Dudley a total of $85,504.44

owed pursuant to the contract, prejudgment interest of 1.5% each month from

the date each of three payments was due until the date of the judgment,

attorney’s fees of $54,332.00, plus court costs, postjudgment interest, and

conditional attorney’s fees on appeal.

Dudley Constr., Ltd. v. Cross Roads Concrete Servs., Inc. Page 3 On January 11, 2024, Dudley filed a proposed final judgment, which the

court signed on January 31, 2024. In that judgment, the court again found in

Cross Roads’s favor and awarded it $85,504.44 pursuant to the contract but

awarded attorney’s fees of $35,792.00. This judgment awarded prejudgment

interest at the rate of 8.5%, beginning September 21, 2022, court costs, and

postjudgment interest at 8.5%, as well as conditional appellate attorney’s fees.

On February 5, 2024, the trial court signed an order setting aside the

January 8, 2024 judgment.

On March 15, 2024, the trial court signed its Findings of Fact and

Conclusions of Law. The court found and concluded that Dudley breached the

contract by failing to pay $10,025.93, $33,163.93, and $42,315.60, totaling

$85,505.46, and that Cross Roads shall recover attorney’s fees in the amount

of $54,330.00, prejudgment interest at the rate of 1.5% pursuant to Texas

Property Code Chapter 28, and conditional appellate attorney’s fees. The court

also concluded that Dudley’s actions violated Texas Property Code Sections

162.001 and 162.003.

On March 25, 2024, Dudley filed a request for amended and additional

findings of fact and conclusions of law complaining that the March 15 findings

and conclusions do not support the January 31 judgment. Although the

January 31 judgment finds in favor of Cross Roads, Dudley’s amended and

Dudley Constr., Ltd. v. Cross Roads Concrete Servs., Inc. Page 4 additional findings and conclusions would support a judgment finding Dudley

did not breach the contract, is not liable for breach of fiduciary duty, Chapter

28 does not apply to its project with the City, and Cross Roads failed to

adequately plead for prejudgment interest.

On April 18, 2024, the trial court signed an order setting aside the

January 31, 2024 judgment, noting in the order that the March 15, 2024

findings of fact and conclusions of law do not support the January 31 judgment.

The order also stated that the court will “sign the revised Judgment consistent

with the Court’s Findings of Fact and Conclusions of Law.”

Also on April 18, 2024, the trial court signed a judgment ordering that

Cross Roads recover from Dudley amounts totaling $85,504.44, accruing

prejudgment interest at the rate of 1.5% per month, attorney’s fees of

$35,792.00, court costs, postjudgment interest, and conditional appellate

attorney’s fees.

Finally, also on April 18, 2024, the trial court signed the Amended and

Additional Findings of Fact and Conclusions of Law submitted by Dudley on

March 25. As set out above, those findings and conclusions were in favor of

Dudley and therefore conflicted with the judgment of April 18.

Cross Roads filed a motion to vacate the Amended and Additional

Findings of Fact and Conclusions of Law because they do not support the relief

Dudley Constr., Ltd. v. Cross Roads Concrete Servs., Inc. Page 5 granted in the judgment. Similarly, on May 8, 2024, Dudley filed a request for

findings of fact and conclusions of law. About a week later, Dudley filed its

motion for new trial asserting that “the repeated procedural defects and

process in handling these postjudgment submissions have prejudiced Dudley’s

appellate rights.” Dudley asked the court to vacate the April 18, 2024

judgment and enter a new judgment that comports with the Amended and

Additional Findings of Fact and Conclusions of Law. The trial court rendered

no further orders, and Dudley filed its notice of appeal.

FINDINGS OF FACT AND CONCLUSIONS OF LAW

In its first issue, Dudley asserts that the judgment must be reformed or

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Benavidez v. Isles Construction Co.
726 S.W.2d 23 (Texas Supreme Court, 1987)
San Saba Energy, L.P. v. Crawford
171 S.W.3d 323 (Court of Appeals of Texas, 2005)
Pacific Employers Insurance v. Dayton
958 S.W.2d 452 (Court of Appeals of Texas, 1998)
Mantas v. Fifth Court of Appeals
925 S.W.2d 656 (Texas Supreme Court, 1996)
Johnson & Higgins of Texas, Inc. v. Kenneco Energy, Inc.
962 S.W.2d 507 (Texas Supreme Court, 1998)
Bufkin v. Bufkin
259 S.W.3d 343 (Court of Appeals of Texas, 2008)
City of Laredo v. R. Vela Exxon, Inc.
966 S.W.2d 673 (Court of Appeals of Texas, 1998)
Lezlea Ross v. St. Luke's Episcopal Hospital
462 S.W.3d 496 (Texas Supreme Court, 2015)
Waters v. Yockey
192 S.W.2d 769 (Texas Supreme Court, 1946)
Trevino v. City of Pearland
531 S.W.3d 290 (Court of Appeals of Texas, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
Dudley Construction, LTD. v. Cross Roads Concrete Services, INC., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dudley-construction-ltd-v-cross-roads-concrete-services-inc-texapp-2025.