Dubuque Boat & Boiler Co. v. Oil Screw Commander

251 F. Supp. 923, 1966 U.S. Dist. LEXIS 8101
CourtDistrict Court, W.D. Missouri
DecidedMarch 18, 1966
DocketNo. 936
StatusPublished
Cited by9 cases

This text of 251 F. Supp. 923 (Dubuque Boat & Boiler Co. v. Oil Screw Commander) is published on Counsel Stack Legal Research, covering District Court, W.D. Missouri primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dubuque Boat & Boiler Co. v. Oil Screw Commander, 251 F. Supp. 923, 1966 U.S. Dist. LEXIS 8101 (W.D. Mo. 1966).

Opinion

JOHN W. OLIVER, District Judge.

Libelant filed this action attempting to invoke the original admiralty jurisdiction [924]*924of this Court upon an alleged cause of contract, civil and maritime, against the M/V COMMANDER, in rem, and against Stanleigh R. Palmer, Jr., her owner, in personam. There is no possible federal jurisdictional base except admiralty.

Libelant alleged that certain materials, supplies and equipment were furnished and certain work done by it on the vessel during the months of May to October, 1961, for which libelant was not paid. Motions to dismiss and for summary judgment questioning the jurisdiction of this Court could not be ruled because libelant insisted throughout the pretrial proceedings that certain facts relating to, our jurisdiction were in dispute. This case was accordingly set for hearing and evidence on both the jurisdictional question and on the merits was received. We need discuss only the jurisdictional question because we have concluded that we do not have jurisdiction of this case.

The only real factual dispute is whether all of the items involved in this action were actually on the M/V COMMANDER at the time of the trial runs on June 23, 1961, or whether some of those items were placed on the vessel after respondent Palmer accepted delivery from the libelant who built her under contract.

We are not convinced that this case turns on so fine a point of fact as to whether the items were on board before or after June 23, 1961, the day of the trial runs and acceptance of the vessel, but, if important, we are convinced that the preponderance of the evidence requires a finding that they were on board before that day.1

We therefore find, in accordance with respondent’s suggested finding of fact No. 4, that the Zinc Bars, ordered May 5, 1961, were on the vessel prior to June 23, 1961; that the Transducer Opening, ordered May 8, 1961, was on the vessel prior to June 23, 1961; that the Cradles, ordered June 19, 1961, (for use in overland transportation) were fabricated prior to June 23,1961; were lying on the dock that day, and were physically placed on board the M/V COMMANDER prior to its leaving libelant’s harbor on June 24, 1961; that the Chairs, ordered June 15, 1961, were on the vessel prior to June 23, 1961; that the Bar, ordered June 21, 1961, was on the vessel June 23, 1961; that the Life Preservers, ordered June 21, 1961, were on the vessel prior to June 23, 1961; that the Grating, ordered June 22, 1961, was on the vessel prior to June 23, 1961; that the Rope and the Light Bulbs and Fixtures, all ordered June 23, 1961 were on the vessel on that day; and that all items found to be on board were on board at the time of the river trials and before respondent accepted delivery of the vessel.

We also find and determine that respondent’s suggested finding No. 5 is supported by the preponderance of the evidence. We therefore make that finding in the language suggested by respondent :

Libelant contracted with Palmer to construct a new vessel, with a base contract price of $45,250.00; COMMANDER was designed for and was intended to be put at the Lake of the Ozarks as an excursion vessel to haul passengers for hire; that all of the above items, though extra to the original contract price of the vessel, were intended for and became a part of the original equipment, and served the purpose of making the vessel safer and more useful for its intended purpose; and all of the items mentioned in paragraph 4 were installed and put in place when the vessel was still undelivered and at the Libelant’s premises.

[925]*925The language of that finding, of course, includes a construction of the contractual relationship that we have found to exist between the parties. We believe that it over-simplifies this case to say, as libelant does say, that “nowhere does respondent contend that the items covered in this suit were a part of the original construction contract” (page 9 of libelant’s reply brief).

It is true that the respondent did not make that contention; but it is equally true that our admiralty jurisdiction over this case does not turn on respondent’s ability to sustain a contention not made, nor required to be sustained by him.

The original proposal of the libelant, dated January 25, 1961, accepted contemporaneously by the respondent, provided for a base contract price of $45,-250.00 to construct the vessel 'n accordance with the specifications attached and made a part of that base contract. The evidence in this case, however, revealed the usual situation under which the parties thereafter agreed to changes and alterations, commonly called ‘extras’, all of which anticipated a later adjustment in the base contract price to be paid for the construction of the vessel.

The affidavit of R. J. Durbrow, filed July 27, 1964, in opposition to respondent’s motion to dismiss for lack of jurisdiction, for example, concedes that the Zinc Bars and the Transducer (the installation of which required the making of an opening in the bottom of the hull to accommodate the depth finder) were in fact considered and described as extra items not included in the specifications.

The correspondence between the parties, after they got into somewhat violent disagreement about matters far more significant than the mere payment of the items involved in this action, described all of the items involved in this case as “extras” to the original contract. Libelant did not even bill respondent for those items until July 31, 1961.

In a letter dated May 22, 1962, written long before the filing of this action, Mr. Durbrow, vice president of libelant, wrote the respondent stating that “we certainly would like to get our accounts in order * * * and I think that you agree the matter has dragged on much too long for either your good or ours” (Exh. 8). He also stated in that letter that “when the boat left here, everything was apparently satisfactory to everybody concerned, and the contractual price paid in full which certainly indicates approval of the vessel on your part” (Exh. 8).

He added, significantly, so far as this case is concerned, that “the balance remaining [referring to the unpaid bill for the items involved in this case] is for ‘extras’ and, quite frankly, should be paid in full” (Exh. 8).

In similar fashion, Mr. Durbrow later wrote respondent on October 11, 1962 (Exh. 9). In that letter he stated the reason why the items involved in this case were not paid for at the same time the base contract price was paid. Mr. Durbrow stated:

When this vessel was completed, you accepted it, paid the full contractual price, plus the extra for the second deck, which was also a predetermined figure, leaving only the other extras unpaid and these only because we had not at that time determined the cost involved (Exh. 9, emphasis ours).

With equal significance, Mr. Durbrow stated that “since none of the so-called ‘complaints’ involved the extras, they should accordingly be paid” (Exh. 9).

Another portion of libelant’s letter of October 11, 1962 establishes that the contract for the execution of this new vessel was executed in a manner typical of the execution of construction contracts generally. In explanation of libelant’s failure to comply with the delivery date of May 15, 1961, Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
251 F. Supp. 923, 1966 U.S. Dist. LEXIS 8101, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dubuque-boat-boiler-co-v-oil-screw-commander-mowd-1966.