D.S.A., Inc. v. Hillsboro Independent School District

999 S.W.2d 887, 1999 Tex. App. LEXIS 6675, 1999 WL 682062
CourtCourt of Appeals of Texas
DecidedAugust 31, 1999
DocketNo. 10-99-012-CV
StatusPublished
Cited by5 cases

This text of 999 S.W.2d 887 (D.S.A., Inc. v. Hillsboro Independent School District) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
D.S.A., Inc. v. Hillsboro Independent School District, 999 S.W.2d 887, 1999 Tex. App. LEXIS 6675, 1999 WL 682062 (Tex. Ct. App. 1999).

Opinion

OPINION

BILL VANCE, Justice.

This is the second appeal concerning a poorly-constructed elementary school. We must determine whether our holding in the [889]*889prior appeal is binding in light of the Supreme Court’s opinion reversing our judgment.

BACKGROUND & PROCEDURAL HISTORY

Hillsboro Independent School District (HISD) contracted with D.S.A., Inc. (DSA), a construction management firm, to oversee the construction of the Jane Lane Elementary School. The completed building had significant structural problems. The roof suffered wind damage and numerous leaks. Poor water drainage beneath and around the school caused the soil in the crawlspace to expand, damaging the plumbing and sewage lines. See D.S.A. v. Hillsboro Indep. Sch. Dist., 973 S.W.2d 662, 662 (Tex.1998).

HISD sued DSA for breach of contract, negligent misrepresentation, and violations of the Deceptive Trade Practices Act (DTPA). The jury found against DSA on each of the three causes of action and awarded identical actual damages on each claim: $170,000 to replace the roof, $13,661 to repair the plumbing under the foundation, and $37,000 to provide drainage of the foundation.1 The jury found that DSA engaged in the DTPA conduct “knowingly.” The jury awarded $170,000 in exemplary damages and attorney’s fees.

In the original appeal, DSA brought 21 points of error complaining that the court erred in entering judgment on each of the three causes of action. D.S.A., Inc. v. Hillsboro Indep. Sch. Dist., 975 S.W.2d 1 (Tex.App.—Waco 1997). We upheld the negligent representation claim but determined that the DTPA claims were barred by the statute of limitations. Id. at 4-7.

Regarding the contract claims, the jury had answered the following questions:

Question 9:
Did D.S.A., Inc. fail to comply with its agreement with the Hillsboro Independent School District dated August 22, 1985?
Answer: Yes.
Question 10:
What sum of money, if any, if paid now in cash, would fairly and reasonably compensate Hillsboro Independent School District for its damages, if any, that resulted from such failure to comply?
[[Image here]]
The reasonable and necessary costs to replace the roof of the Jane Lane Elementary School.
Answer: $ 170,000
The reasonable and necessary costs to repair the plumbing under the foundation.
Answer: $ 13,661
The reasonable and necessary costs to provide drainage of the foundation.
Answer: $ 37,000

(Emphasis added.) DSA complained of these jury findings in Point 18: “The trial court erred in entering judgment against DSA on the breach of contract issues (questions nine and 10) because no evidence supports the jury’s finding that DSA failed to comply with its contract.” We stated: “We agree with DSA on the drainage complaint, but not on either the roofing or plumbing grounds.” Id. at 7.

We then reviewed the legal sufficiency of the evidence as to each element of dam[890]*890ages of the breach-of-contract action. Id. at 9-16. We found legally-sufficient evidence as to the roof and plumbing damages. As to the “excavation of the parking lots,” however, we found “no evidence to support the jury’s finding that DSA breached its contractual duties to HISD with respect to the construction of the parking lots.” Id. at 16. Thus, we sustained point eighteen in part and overruled it in part.

We ordered a remittitur of $416.67 on the roof damages. Id. at 17. Having upheld the negligent representation claims, we reformed the judgment to provide that HISD recover $220,244.33, which reflected $169,583.33 for the roof replacement, $13,-661.00 for the plumbing repairs, and $37,-000 for the drainage repairs. Id. at 21. Our judgment also provided for $170,000 in exemplary damages; attorney’s fees; and prejudgment interest. Id.

DSA appealed to the Texas Supreme Court,2 which held that HISD’s negligent-misrepresentation claim failed for lack of any independent injury. The Court struck the exemplary-damages award. D.S.A., 973 S.W.2d at 663. The Court then stated:

DSA further asserts that there was no evidence that it breached its contract with respect to the roofing or foundation defects. We conclude that there was legally sufficient evidence that DSA neglected its contractual obligation to “endeavor to protect [HISD] against defects and deficiencies in the work.”

Id. at 664 (emphasis added). The Court concluded: “[W]e reverse the judgment of the court of appeals and remand the case to the trial court to recalculate damages on HISD’s contract cause of action.” Id. at 665.

On remand, HISD filed a Motion for Entry of Judgment with a proposed judgment which awarded HISD “$169,583.33 for roof repairs, $37,000 for the drainage of the foundation, and $13,661 for the plumbing repairs for a total of $220,-244.33.” DSA filed a response, asking the court to omit the $37,000 for the drainage of the foundation because of this Court’s prior determination that there was “no evidence” of a contractual breach on that issue.

At the hearing, DSA argued that our prior holding on the drainage damages is the “law of the case” because HISD had not appealed that holding to the Supreme Court. HISD responded that, because it had fully recovered its damages in this Court on its alternative theory of negligent representation, it had no reason to have complained of this Court’s judgment. Further, HISD argued that the Supreme Court had reversed this Court’s judgment, and thus the Supreme Court’s opinion is the “law of the case.”

The trial court signed a judgment on December 22, 1998, which included an award of $37,000 in damages to repair the foundation drainage.3 The new judgment also increased the time period used for calculating prejudgment interest.

THIS APPEAL

DSA appeals on two issues. First, that HISD “is not entitled to recover damages for foundation drainage disposed of by an unchallenged finding of the court of ap[891]*891peals.” Second, that “the unchallenged time period used to calculate prejudgment interest in the judgment of the trial court must be incorporated into the new final judgment.”

RECOVERY FOR FOUNDATION DRAINAGE

Was HISD required to challenge our holding?

DSA argues that, under the “law of the case,” the court erred in awarding $37,000 for foundation drainage damages because HISD failed to challenge our prior finding that there was “no evidence” of those damages under its breach-of-contract theory.

Prior to the adoption of the Appellate Rules,4 the Supreme Court required any party seeking a “more favorable judgment” than that of the court of appeals’ judgment to file an application for writ of error or cross-point. Archuleta v. Int’l Ins. Co.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
999 S.W.2d 887, 1999 Tex. App. LEXIS 6675, 1999 WL 682062, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dsa-inc-v-hillsboro-independent-school-district-texapp-1999.