Drywall Systems, Inc. v. A. Arnold of Kansas City

CourtCourt of Appeals of Kansas
DecidedSeptember 27, 2019
Docket119091
StatusPublished

This text of Drywall Systems, Inc. v. A. Arnold of Kansas City (Drywall Systems, Inc. v. A. Arnold of Kansas City) is published on Counsel Stack Legal Research, covering Court of Appeals of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drywall Systems, Inc. v. A. Arnold of Kansas City, (kanctapp 2019).

Opinion

No. 119,091

IN THE COURT OF APPEALS OF THE STATE OF KANSAS

DRYWALL SYSTEMS, INC., Appellant,

v.

A. ARNOLD OF KANSAS CITY, LLC, EVAN BRANN, BMJ BUILDING MANAGEMENT, LLC, BANK OF BLUE VALLEY,

and

MORRILL & JANES BANK AND TRUST COMPANY, Appellees.

SYLLABUS BY THE COURT

1. The goal of the Kansas Fairness in Private Construction Contract Act, K.S.A. 16- 1801 et seq., is to encourage prompt payments of undisputed amounts as they come due under the contracts of the parties.

2. The Kansas Fairness in Private Construction Contract Act provides incentives to the three tiers of a construction contract—owners—contractors—subcontractors.

3. In any action to enforce the rights created by the Kansas Fairness in Private Construction Contract Act, the court shall award costs and reasonable attorney fees to the prevailing party. K.S.A. 16-1806.

1 4. Ownership is the bundle of rights allowing one to use, manage, and enjoy property, including the right to convey it to others. Ownership implies the right to possess a thing, regardless of any actual or constructive control. Ownership rights are general, permanent, and heritable. A tenant under a lease is not an owner as defined by the Kansas Fairness in Private Construction Contract Act.

5. Short-term leases with options to buy are treated as leases, rather than sales contracts.

6. When a lease contains a stipulation that the renters shall have the right to purchase the premises, if they shall so elect, there is no completed sale. Renters do not acquire any estate in the land beyond the leasehold interest until they have elected to accept the offer and have paid or tendered the purchase price stipulated in the contract.

Appeal from Johnson District Court; KEVIN P. MORIARTY, judge. Opinion filed September 27, 2019. Affirmed.

James F. Freeman III, of Swanson Bernard, LLC, of Kansas City, Missouri, for appellant.

Frederick G. Thompson IV, of Gould, Thompson & Bucher, PC, of Kansas City, Missouri, for appellee A. Arnold of Kansas City, LLC.

Before HILL, P.J., LEBEN, J., and WALKER, S.J.

HILL, J.: Drywall Systems, Inc., appeals the district court's denial of its request for prejudgment interest and attorney fees from A. Arnold of Kansas City, LLC. Because the court found A. Arnold was not an "owner" as defined by the Kansas Fairness in Private

2 Construction Contract Act, K.S.A. 16-1801 et seq., it denied Drywall's request. We agree with the district court—under the plain language of the Act, A. Arnold is not an "owner" and was thus not legally obliged to pay interest and attorney fees under this Act. Simply put, the Act did not apply here. We affirm.

A company rents part of a building in Olathe.

The moving and storage company, A. Arnold, entered into a five-year lease for a part of a building in Olathe owned by BMJ Building Management LLC. When the lease was signed there were tenants already using other parts of the building. For that reason, A. Arnold needed a partition wall built before it could move into the building. The company needed its space separated from the areas rented to the other tenants so it could securely store the property it was moving.

Building the wall was when Drywall became involved. Drywall submitted a bid to A. Arnold to build the wall. A. Arnold accepted the bid and Drywall finished the work. But when Drywall was not paid, it sued A. Arnold, BMJ Building Management, LLC, and others. It brought claims for breach of contract, a mechanic's lien foreclosure, and unjust enrichment.

The district court found for Drywall on its breach of contract claim against A. Arnold. But the court refused to award prejudgment interest and attorney fees to Drywall because BMJ, the property owner, was not a party to the construction contract, and A. Arnold was not an owner as the Act contemplated.

The district court based its ruling mostly on the lease. Under the lease, A. Arnold was specifically prohibited from making alterations, modifications, or changes to the property without BMJ's prior written consent. Relying on this provision, the district court found that A. Arnold contracted with Drywall to build the wall without the right to do so.

3 A. Arnold does not appeal the district court's finding that it was liable to pay Drywall for the work under the contract. Drywall appeals the district court's denial of prejudgment interest and attorney fees.

The Act encourages prompt payment of undisputed amounts.

The Act focuses on the three tiers of responsibility in ordinary construction projects—the owners—the contractors—and the subcontractors. The Legislature recognizes that it is good public policy to promote the flow of money through those three tiers. Prompt payment of undisputed amounts is the goal of the Act. To help achieve this goal, the Act gives incentives for owners, contractors, and subcontractors to pay promptly all undisputed amounts due under construction contracts.

Promptness is defined by 30-day and 7-day limits created in the statute.

 If an owner does not pay the contractor within 30 days of any undisputed amount, then the owner is liable for 18 percent interest on the unpaid amount. K.S.A. 2018 Supp. 16-1803(e).  If a contractor does not pay a subcontractor within seven days of any undisputed amount, then the contractor is liable for 18 percent interest on the unpaid amount. K.S.A. 2018 Supp. 16-1803(f) and (g).  If a subcontractor fails to pay within seven days any undisputed amount to another subcontractor, then the subcontractor is liable for 18 percent interest. K.S.A. 2018 Supp. 16-1803(h).

There is no mention in the law of any other party who may have an interest in the real estate, such as those who hold a mortgage on the premises, or those who have a leasehold. But lienholders, at least for work or materials used during the construction project, are recognized in the Act because they necessarily must be either a contractor or 4 subcontractor. In other words, they are in one of the three tiers of responsibility for the project.

More incentives for prompt payment are found later in the Act where costs and attorney fees can be recovered under K.S.A. 16-1806. It states that "[i]n any action to enforce K.S.A. 16-1803, 16-1804, 16-1805 . . . the court . . . shall award costs and reasonable attorney fees to the prevailing party." If a party is seeking to enforce any of those rights, then if they prevail the court shall award them costs and attorney fees. But the party must be seeking the rights designated in those three statutory sections. We look at all three.

The first—K.S.A. 2018 Supp. 16-1803—has three elements. It begins by banning three contract provisions from all private construction contracts covered by the Act that would make certain existing rights unenforceable.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Board of Johnson County Comm'rs v. Greenhaw
734 P.2d 1125 (Supreme Court of Kansas, 1987)
Bras v. Sheffield
49 Kan. 702 (Supreme Court of Kansas, 1892)
Miller v. Bankers Mortgage Co.
287 P. 618 (Supreme Court of Kansas, 1930)
Ullery v. Othick
372 P.3d 1135 (Supreme Court of Kansas, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
Drywall Systems, Inc. v. A. Arnold of Kansas City, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drywall-systems-inc-v-a-arnold-of-kansas-city-kanctapp-2019.