Drum Lodge, LLC v. Martel Construction, Inc.

CourtCourt of Appeals for the Ninth Circuit
DecidedJune 6, 2025
Docket24-2833
StatusUnpublished

This text of Drum Lodge, LLC v. Martel Construction, Inc. (Drum Lodge, LLC v. Martel Construction, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drum Lodge, LLC v. Martel Construction, Inc., (9th Cir. 2025).

Opinion

NOT FOR PUBLICATION FILED UNITED STATES COURT OF APPEALS JUN 6 2025 MOLLY C. DWYER, CLERK U.S. COURT OF APPEALS FOR THE NINTH CIRCUIT

DRUM LODGE, LLC, No. 24-2833 D.C. No. Petitioner - Appellant, 2:24-cv-00219-WBS-JDP v. MEMORANDUM* MARTEL CONSTRUCTION, INC.,

Respondent - Appellee.

Appeal from the United States District Court for the Eastern District of California William B. Shubb, District Judge, Presiding

Argued and Submitted April 1, 2025 Pasadena, California

Before: M. SMITH and VANDYKE, Circuit Judges, and MAGNUS-STINSON, District Judge.**

Petitioner Drum Lodge, LLC (Drum Lodge) appeals from a final judgment of

the district court dismissing Drum Lodge’s petition to vacate an arbitration award in

favor of Martel Construction, Inc. (Martel) and the accompanying award of

* This disposition is not appropriate for publication and is not precedent except as provided by Ninth Circuit Rule 36-3. ** The Honorable Jane Magnus-Stinson, United States District Judge for the Southern District of Indiana, sitting by designation. attorneys’ fees. We have jurisdiction under 28 U.S.C. § 1291, and we affirm.

Because the parties are familiar with the facts and background of this case, we

provide only the information necessary to give context to our ruling. Martel and

Drum Lodge entered into arbitration before a three-member tribunal to resolve

disputes related to a construction project. The tribunal ultimately decided in favor

of Martel, concluding that Drum Lodge had breached the parties’ contract and was

liable for damages. The tribunal further ordered Drum Lodge to pay Martel’s

attorneys’ fees pursuant to Rule 48(d)(ii) of the Construction Rules of the American

Arbitration Association, which was incorporated into the parties’ contract. Drum

Lodge filed a petition to vacate the arbitration award and award of attorneys’ fees,

but the district court dismissed the petition. Drum Lodge raises two challenges to

this dismissal, both of which fail.

1. Drum Lodge first argues that the award of attorneys’ fees should be

vacated pursuant to 9 U.S.C. § 10(a)(4) because the tribunal exceeded its authority

in awarding attorneys’ fees to Martel. We do not agree. Section 10(a)(4) presents

“a high standard for vacatur.” HayDay Farms, Inc. v. FeeDx Holdings, Inc., 55 F.4th

1232, 1240 (9th Cir. 2022) (quoting Lagstein v. Certain Underwriters at Lloyd’s,

London, 607 F.3d 634, 641 (9th Cir. 2010)). To satisfy this standard, “it is not

enough to show that the arbitrator committed an error—or even a serious error.” Id.

(alterations omitted) (quoting Lagstein, 607 F.3d at 641). Instead, “[a]rbitrators

2 24-2833 exceed their powers . . . not when they merely interpret or apply the governing law

incorrectly, but when the award is completely irrational, or exhibits a manifest

disregard of law.” U.S. Life Ins. Co. v. Superior Nat’l Ins. Co., 591 F.3d 1167, 1177

(9th Cir. 2010) (alteration in original) (quoting Schoenduve Corp. v. Lucent Techs.,

Inc., 442 F.3d 727, 731 (9th Cir. 2006)).

That standard is not met here for two reasons. First, the tribunal reasonably

interpreted Construction Rule 48(d)(ii) to authorize the award of attorneys’ fees here

in light of the facts that (1) Martel requested prevailing party fees and (2) Drum

Lodge requested attorneys’ fees, at a minimum, pursuant to the contract’s

indemnification provision. Contrary to Drum Lodge’s focus on whether it asked for

prevailing-party attorneys’ fees, Construction Rule 48(d)(ii) can be reasonably

interpreted to apply when all parties request some form of attorneys’ fees—which

indisputably occurred here. There is thus no basis to disturb the arbitrator’s decision.

See HayDay Farms, 55 F.4th at 1241 (“[A]n arbitrator does not exceed its authority

if the decision is a plausible interpretation of the arbitration contract. Accordingly,

the court must defer to the arbitrator’s decision as long as the arbitrator even

arguably construed or applied the contract.” (citation omitted) (quoting U.S. Life Ins.

Co., 591 F.3d at 1177)).

Second, even if we were to accept Drum Lodge’s argument that a request for

fees under the contract’s indemnification provision is insufficient to trigger the

3 24-2833 application of Construction Rule 48(d)(ii), Drum Lodge’s challenge still fails. The

tribunal made a finding that, when questioned, Drum Lodge orally represented that

it was seeking attorneys’ fees and “did not condition or limit its affirmative answer

to success on its indemnity counterclaim.” Our review of arbitration decisions is

limited, and “[w]hether or not the panel’s findings are supported by the evidence in

the record is beyond the scope of our review.” Bosack v. Soward, 586 F.3d 1096,

1105 (9th Cir. 2009). We must accept the tribunal’s finding on this point, see

HayDay Farms, 55 F.4th at 1241, and, in light of that finding, an award of attorneys’

fees pursuant to Construction Rule 48(d)(ii) was permissible.

2. Drum Lodge next argues that the arbitration award must be vacated on

grounds of evident partiality pursuant to 9 U.S.C. § 10(a)(2) because the award was

infected by a conversation that occurred between Martel’s counsel and the tribunal

members about the possibility of the members serving on future tribunals in

Montana. Again, we disagree.

To begin, Drum Lodge waived this issue. The waiver doctrine precludes a

party from seeking vacatur of an arbitration award on the grounds of evident

partiality “where [the] party . . . has constructive knowledge of a potential conflict

but fails to timely object.” Fid. Fed. Bank, FSB v. Durga Ma Corp., 386 F.3d 1306,

1313 (9th Cir. 2004); see also Monster Energy Co. v. City Beverages, LLC, 940 F.3d

1130, 1134 (9th Cir. 2019). Here, as shown in the relevant declarations, Drum Lodge

4 24-2833 had actual knowledge of “the key fact that triggered the specter of partiality,”

Monster Energy, 940 F.3d at 1135, but concededly failed to raise any partiality

argument before the arbitrators. The issue is thus waived.

Even if we were to reach the issue, we would reject Drum Lodge’s arguments.

In the absence of actual bias, the possible conflict at issue must be undisclosed to

give rise to an evident-partiality claim. See Lagstein, 607 F.3d at 645–46. But, here,

Drum Lodge’s counsel was in the same room when the allegedly improper

conversation occurred. It is hard to see how the bald assertion by Drum Lodge’s

counsel that he “was under the impression that neither [Martel’s counsel] nor the

arbitrators were aware of [his] presence” during the conversation could be sufficient

to show that the conversation was undisclosed. Moreover, the conversation at issue

here was simply too general and abstract to give rise to “[a] reasonable impression

of bias.” Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Drum Lodge, LLC v. Martel Construction, Inc., Counsel Stack Legal Research, https://law.counselstack.com/opinion/drum-lodge-llc-v-martel-construction-inc-ca9-2025.