Drainage Dist. No. 7 of Poinsett County v. Sternberg

15 F.2d 41, 1926 U.S. App. LEXIS 2811
CourtCourt of Appeals for the Eighth Circuit
DecidedOctober 7, 1926
DocketNo. 7057
StatusPublished
Cited by3 cases

This text of 15 F.2d 41 (Drainage Dist. No. 7 of Poinsett County v. Sternberg) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Drainage Dist. No. 7 of Poinsett County v. Sternberg, 15 F.2d 41, 1926 U.S. App. LEXIS 2811 (8th Cir. 1926).

Opinion

STONE, Circuit Judge.

This is an action on a contract involving an accounting. Prom a decree awarding plaintiff $109,-332.66, defendants bring this appeal.

The action was by Sternberg, a contractor, against drainage district No. 7 of Poinsett county, Arkansas, and various individuals as the directors of that district. It was based upon a contract between Sternberg and the district whereby he was to do certain excavating. He alleged breach of the contract and claimed damages because of payments due under the contract and because of loss of anticipated profits which he would have made had the district performed its part of the contract and he been permitted to complete the work in accordance with the contract. The recovery for the above total of $109,332.66 was made up of payments due under the contract of $35,963.25 and anticipated profits of $73,369.41.

Appellants have filed here a motion for leave to file petition for leave to file bill in the nature of a bill of review. Also, they assign several errors, each of which will be stated and determined hereinafter.

Bill of Review.

We are asked to “hold the appeal in abeyance and render no decision thereon until the District Court may hear” a bill in the nature of a bill of review and take action thereon. Leave is asked to file such a bill directing the District Court to submit to a master or itself permit evidence of an advance payment of $15,118.88 to Sternberg and of a report of the district engineers and a resolution of the district board reducing the amount of work to be done under this contract to 200,736 cubic yards.

The far-reaching effect of permitting such evidence is alleged in the motion for leave to file to be to “involve the question of who did commit a breach of the contract, and go to show that no substantial breach of contract -by the defendant had occurred previous to the termination of the contract by Stern-berg.” In the motion proper, it is alleged that evidence of the advance “materially changes the facts upon which the master and the District Court based the finding” that the district was indebted to Sternberg at the time of the work suspension order. In such motion it is, also, stated:

“That such a state of facts materially changes the situation with reference to who breached the contract. It would also change the situation before the lower court upon the question of whether or not any breach of contract by the drainage district was substantial. and was the real cause of the termination thereof by Sternberg.
“Your petitioners respectfully state that with the fact of said payment of $15,118.88, .three years before the work began by Stern-berg on improvement No. 64, the result in the lower court would doubtless have been different, and the said omission was a material and substantial one, going to the basis of the entire decree and award.”

In short, it means a retrial of the case. In our judgment, there should be an irresistible reason to compel such an unusual and drastic result.

The only reasons stated are that “by accident, mistake and oversight” the engineers of „the district misinformed counsel in the trial of the 'ease and in the preparation of the ease after deeree. Both of the matters now sought to be brought into the case were pleaded in the answer of the district. There is no suggestion that Sternberg or his counsel, in any way, misled counsel for the district. As to the advance item, it is alleged [43]*43that appellee knew this had been paid and that to allow him to retain it without credit would be, in effect, a fraud upon the district. We have found no allegation that Sternberg knew of the other item: The reduction of work to be done under the contract. Also, it appears that this evidence was known at all times to appellants, pleaded in their answer and was not evidence newly discovered after final decree. Nor is it sought to limit the bill to introducing evidence of an undisputed item of credit for the sole purpose of reducing the recovery. The purpose is to reopen the entire case and place the entire result of the suit in the balance. It seems to us that this matter can be reduced to the bald legal proposition of whether a party who has, through oversight or mistake of its own agents (uninfluenced by any action of the opposing party), omitted to , introduce important evidence, which might affect the entire result, in the trial of a case, can, after that case is on appeal, have the trial overthrown and the case sent back for a complete trial anew.

While the ease may be a hard one as to the' advance item, if used purely in reduction of recovery and not to defeat recovery, yet we think a most dangerous precedent in an important particular of procedure would' be made if this leave were granted and the case entirely reopened. We think the leave to file should be denied. Dumont v. Railway, 131 U. S. clx. Appex., 25 L. Ed. 520; Hill v. Phelps, 101 F. 650, 41 C. C. A. 569 (this court).

Merits — Breach of Contract.

The first issue raised here is that the district did not breach the contract but that Sternberg voluntarily rescinded it. The breaches appellee relies upon are (1) nonpayment during the progress of the work as required by the contract and (2) notification to suspend work in violation of the contract. The evidence seems to sustain the claim of breach for nonpayment. Such a breach, under ,the circumstances of this contract and the character of this work, was a material breach of the entire contract (Guerini v. Carlin Co., 248 U. S. 334, 39 S. Ct. 102, 63 L. Ed. 275), and particularly so when joined with a suspension notice (A. R. Young Const. Co. v. Road District, 297 F. 127, this court). Also, we think there is a clear proof -of breach by notification to quit work. It is not disputed that such notification was given. One claim is that the contract authorized such work suspension where there was “delay or hindrance caused by any legal difficulties that may arise” and that such “legal difficulties” did arise through actions involving bonds from which the district expected to realize funds to pay for this work. In our judgment, this was not the character of legal difficulties contemplated by the contract. The contract intended such difficulties as arose out of legal actions directly affecting the work to be done under this contract. The notification was a complete breach of the contract and the appellee was entitled to treat it as such.

Next, it is contended that Sternberg did not cease work because of the notification nor the nonpayment. A plausible supporting argument is made. However, the cause for stopping work, as stated by appellee, was nonpayment. In a communication by appellee to the appellant district, made before work was stopped, appellee stated that unless the back payments were made, it would be compelled to cease work. The fact of nonpayment is established and the master and the court found that to be the cause of cessation by appellee.

Rescission of Contract.

The contention that the contract was rescinded, before breach, by appellee and, therefore, that there can be no recovery for anticipatory profits is met by what has been said above concerning breach of the contract.

Excessive Recovery.

We think appellants are right that the amount of anticipated profits recovered is excessive but not to the extent nor for the reason urged. The contract made the specifications part of the contract.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cub Fork Coal Co. v. Fairmount Glass Works
59 F.2d 539 (Seventh Circuit, 1932)
Jensen v. New York Life Ins. Co.
50 F.2d 512 (Eighth Circuit, 1931)
Youngs Rubber Corporation v. CI Lee & Co.
45 F.2d 103 (Second Circuit, 1930)

Cite This Page — Counsel Stack

Bluebook (online)
15 F.2d 41, 1926 U.S. App. LEXIS 2811, Counsel Stack Legal Research, https://law.counselstack.com/opinion/drainage-dist-no-7-of-poinsett-county-v-sternberg-ca8-1926.