Dr. Humayun Akhtar and Yosaria Akhtar v. Jdn Properties At florham Park, L.L.C., Jdn Properties, L.L.C., Joseph Natale, Randy Deluca, Deltrus, L.L.C., and Casey & Keller, Inc.

New Jersey Superior Court Appellate Division·Decided February 24, 2015·No. A-2327-12·Published

Opinion

NOT FOR PUBLICATION WITHOUT THE APPROVAL OF THE APPELLATE DIVISION

SUPERIOR COURT OF NEW JERSEY APPELLATE DIVISION

DOCKET NO. A-2327-12T3

DR. HUMAYUN AKHTAR and APPROVED FOR PUBLICATION YOSARIA AKHTAR, February 24, 2015

Plaintiffs-Appellants, APPELLATE DIVISION

v.

JDN PROPERTIES AT FLORHAM PARK, L.L.C., JDN PROPERTIES, L.L.C., JOSEPH NATALE, RANDY DELUCA, DELTRUS, L.L.C., and CASEY & KELLER, INC.,

Defendants-Respondents.

Argued January 6, 2015 – Decided February 24, 2015 Before Judges Koblitz, Haas and Higbee.

On appeal from Superior Court of New Jersey, Law Division, Morris County, Docket No.

Docket No. L-1701-07.

Jay J. Rice argued the cause for appellants (Nagel Rice, L.L.P., attorneys; Mr. Rice, of counsel and on the brief; Randee M. Matloff, on the brief).

Andrew S. Cimino argued the cause for respondent Casey & Keller (Marshall Dennehey Warner Coleman & Goggin, attorneys; Mr.

Cimino, of counsel and on the brief).

The opinion of the court was delivered by KOBLITZ, J.A.D.

Plaintiffs, Dr. Humayun Akhtar and his wife, Yosaria, appeal from a jury verdict dismissing their malpractice claims against defendant,1 engineering firm Casey & Keller, Inc. A judge initially awarded plaintiffs summary judgment on liability, but a second judge reconsidered and vacated the grant of summary judgment. A third judge held a full trial, which yielded a no-cause jury verdict. Plaintiffs maintain that they were entitled to summary judgment as a matter of law, or at least a new trial, because their expert's opinion was unrebutted by defendant's expert. In light of plaintiffs' burden of proof and the conflicting evidence as to the factual predicates for their expert's opinion, we affirm.

I

As developer JDN Properties at Florham Park, L.L.C., (JDN FP), was planning a ten-lot project on a set of steep properties, its manager, Randy DeLuca, engaged engineer Michael Lanzafama's firm, Casey & Keller, Inc. Lanzafama's firm was to perform title, topographic, and utilities surveys, prepare designs for a road and other infrastructure for the project, and

1 "Defendant" refers only to Casey & Keller. The complaint against JDN FP, JDN Properties, and Joseph Natale, the principal of both entities, as well as on site-manager Randy DeLuca and his company Deltrus (collectively, the JDN defendants) is the subject of a separate consolidated appeal under docket numbers A-5907-11 and A-6064-11.

submit those documents for approval from the appropriate government agencies. In the course of that work, Lanzafama drafted an individual lot grading plan for what would become plaintiffs' property, depicting two semi-circular Allan Block retaining walls and incorporating the manufacturer's specifications. The grading plan was filed with the municipality in conjunction with the property's site plan and approved by borough engineer Robert Kirkpatrick in April 2005.

Plaintiffs contracted with JDN FP to purchase the lot and have a home constructed, with certain modifications, such as one to accommodate a full walk-out basement, which ultimately drove the price up to just over $1.56 million. Akhtar, who frequently visited the site during construction, testified at trial that shortly before the closing, he was surprised to find that the builder had deviated from Lanzafama's design by constructing a much longer, higher retaining wall along the eastern side of the property than originally designed. He acknowledged, however, that he had requested that the wall be raised by at least one foot to accommodate a backyard pool, and DeLuca introduced testimony suggesting that plaintiffs' requests for modifications required a more level backyard and consequently, expansion of the retaining wall. Lanzafama claimed at trial that his personnel had no knowledge of the modification until their site

visit for a final survey, but confirmed that his design provided sufficient information for building the wall ultimately constructed.

Nonetheless, the modification was undertaken without prior municipal approval, and JDN FP had apparently never obtained a permit for the wall in the first place. On one of his site visits, borough engineer Kirkpatrick noticed the change, along with other unauthorized work. Because the municipality had never inspected the retaining wall's construction, he requested a letter assuring that the wall had been built according to the manufacturer's specifications. Lanzafama wrote the letter at DeLuca's request.

At trial Lanzafama testified that, before doing so, he discussed with DeLuca the methods that had been used to construct the wall and inspected the wall himself, albeit after its completion. He explained that while investigating, he observed geogrid fabric protruding from the wall at various points, confirming that the three appropriately spaced layers of geogrid had been placed. He also observed drainage pipes extending from the wall, suggesting that the required toe drain had been installed at the crushed stone's base to evacuate any water that might build up within or alongside the wall. His field crew took measurements of the wall to confirm its location

and elevation, and he himself examined soil immediately behind the wall to confirm its stability. He further reviewed photographs his crew had taken on site visits, which he believed showed that the blocks, gravel, and geogrid were appropriately placed and that the correct compaction tools had been used. Moreover, he recalled his own prior site visits at various stages of the wall's construction, albeit undertaken for other reasons, where he nonetheless saw the wall being built with appropriate materials and equipment. He concluded from those observations that the wall had been appropriately built and felt comfortable writing the letter.

Borough building inspector Stephen Jones testified at deposition that the letter had not specifically been requested in connection with the review of any application for a certificate of occupancy. It was, in any event, submitted in connection with such an application. The borough issued a temporary certificate of occupancy for the property on June 1, 2006. Pursuant to the contract, JDN FP then remitted a "time of the essence letter" to plaintiffs and set a closing date for June 9. Akhtar performed a walk-through of the property prior to closing and requested repair of certain defects. Plaintiffs first became aware of serious problems with the property when

they learned from a plumber not long after closing that the house was "sliding." They have never moved in.

Subsequent investigations by engineering firm LAN, hired by JDN FP, revealed cracking in the foundation under a substantial portion of the eastern side of the house due to improperly compacted soil. Plaintiffs, meanwhile, retained Henry Naughton, an engineering consultant, who concluded that the cracks in the foundation were attributable to the soil's poor bearing capacity. He further concluded that the eastern retaining wall, which Lanzafama had vouched for, had questionable long term stability that, because of transport of soil through the wall, would undermine structures supported on the soil. He testified that failure of the retaining wall was one of the causes of the movement of the house. LAN recommended installing helical piles to bolster the foundation and arrest its settlement, but plaintiffs and JDN FP were never able to agree on an appropriate remedy.

Free access — add to your briefcase to read the full text and ask questions with AI

Dr. Humayun Akhtar and Yosaria Akhtar v. Jdn Properties At florham Park, L.L.C., Jdn Properties, L.L.C., Joseph Natale, Randy Deluca, Deltrus, L.L.C., and Casey & Keller, Inc., (N.J. Ct. App. 2015).

Dr. Humayun Akhtar and Yosaria Akhtar v. Jdn Properties At florham Park, L.L.C., Jdn Properties, L.L.C., Joseph Natale, Randy Deluca, Deltrus, L.L.C., and Casey & Keller, Inc. (Dr. Humayun Akhtar and Yosaria Akhtar v. Jdn Properties At florham Park, L.L.C., Jdn Properties, L.L.C., Joseph Natale, Randy Deluca, Deltrus, L.L.C., and Casey & Keller, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Johnson v. Salem Corp.
477 A.2d 1246 (Supreme Court of New Jersey, 1984)
Frugis v. Bracigliano
827 A.2d 1040 (Supreme Court of New Jersey, 2003)
Gilhooley v. County of Union
753 A.2d 1137 (Supreme Court of New Jersey, 2000)
Cameco, Inc. v. Gedicke
724 A.2d 783 (Supreme Court of New Jersey, 1999)
Conrad v. Michelle & John, Inc.
925 A.2d 54 (New Jersey Superior Court App Division, 2007)
State v. Odom
560 A.2d 1198 (Supreme Court of New Jersey, 1989)
Estate of Roach v. Trw, Inc.
754 A.2d 544 (Supreme Court of New Jersey, 2000)
Sons of Thunder, Inc. v. Borden, Inc.
690 A.2d 575 (Supreme Court of New Jersey, 1997)
Dolson v. Anastasia
258 A.2d 706 (Supreme Court of New Jersey, 1969)
Johnson v. Cyklop Strapping Corp.
531 A.2d 1078 (New Jersey Superior Court App Division, 1987)
Ferdinand v. Agricultural Ins. Co. of Watertown, NY
126 A.2d 323 (Supreme Court of New Jersey, 1956)
Saldana v. DiMedio
646 A.2d 522 (New Jersey Superior Court App Division, 1994)
Cineas v. Mammone
636 A.2d 1071 (New Jersey Superior Court App Division, 1994)
Lewis v. American Cyanamid Co.
715 A.2d 967 (Supreme Court of New Jersey, 1998)
CPC Intern., Inc. v. HARTFORD ACC.
720 A.2d 408 (New Jersey Superior Court App Division, 1998)
Southport Dev. Group, Inc. v. TP. OF WALL
685 A.2d 84 (New Jersey Superior Court App Division, 1996)
Lombardi v. Masso
25 A.3d 1080 (Supreme Court of New Jersey, 2011)
Pomerantz Paper Corp. v. New Community Corp.
25 A.3d 221 (Supreme Court of New Jersey, 2011)
State v. Reldan
495 A.2d 76 (Supreme Court of New Jersey, 1985)
Sisler v. Gannett Co., Inc.
536 A.2d 299 (New Jersey Superior Court App Division, 1987)