Dow Chemical Canada Inc. v. HRD Corp.

909 F. Supp. 2d 350, 2012 WL 6622685, 2012 U.S. Dist. LEXIS 179293
District Court, D. Delaware·Decided December 19, 2012·No. No. C.A. 05-023-RGA·Published·Cited by 1 cases

Opinion

MEMORANDUM OPINION

ANDREWS, District Judge:

Plaintiff Dow Chemical Canada, Inc. brings this supplemental motion for summary judgment (D.I. 481) in order to prove up damages on its contract claim against [352] Defendant HRD Corporation. A previous order of this Court (D.I. 444) granted Dow’s motion for summary judgment and established HRD’s breach of contract, but did not determine Dow’s damages. This opinion will determine Dow’s claims for damages.

BACKGROUND

On July 1, 2002, Dow and HRD entered into two contracts: the Joint Development Agreement (“JDA”) and the Supply Agreement. (D.I. 483, Exhs. 1, 2). The parties agreed to jointly develop polyethylene wax products. (D.I. 483, Exh. 1 at ¶ 1.3). After product development, Dow was to manufacture and supply HRD with the wax products. (D.I. 483, Exh. 2, ¶ (D)). They were to be produced from a Dow manufacturing plant (the “Sarnia Plant”) specifically customized for this purpose. (Id.). The JDA governed the collaboration to develop the wax products, and the Supply Agreement governed the subsequent commercial phase of the relationship. (D.I. 483, Exh. 1 at ¶¶ 1.3, 2.2, 10.18, 10.19). The parties’ rights to payment hinged on certain agreed upon developmental and commercial milestones. One of these milestones was known as the “Implementation Date,” or the date- that marked the beginning of the conversion process of Dow’s Sarnia Plant. (D.I. 483, Exh. 2 at ¶ 3.1) Another important milestone was known as “Beneficial Manufacture,” defined as Dow’s “first Delivery of Product to HRD.” (Id. at ¶ 1). “Delivery” occurred when “the Product is declared by [Dow] to be Prime Product or Off-Spec Product and (ii) when the Railcar is full or otherwise declared by [Dow] to be ready to be transported.”1 Thereafter, Dow would supply the wax products to HRD for four years, and HRD would purchase the output of the Sarnia Plant (up to 60 million pounds per year). (Id. at ¶¶ 2.1, 6.1, 6.2). Dow promised to sell the wax products only to HRD during these four years. (Id. at ¶ 31).

The parties reached the Implementation Date on February 28, 2003, triggering the Sarnia Plant’s conversion process. (D.I. 483, Exhs. 3 at pp. 2-3, 3B, 3D). The conversion was successful and Dow began actual wax production on May 2, 2004. (D.I. 483, Exh. 4). On May 11, 2004, Dow notified HRD that two railcars of Prime Product were available for transport. (D.I. 483, Exhs. 4, 5). Those two railcars were shipped, followed by two more on May 14, 2004 and a fifth railcar on June 4, 2004. (D.I. 483, Exh. 3H, 31). The deliveries constituted Beneficial Manufacture.2

On July 30, 2004, HRD requested that Dow halt production at the Sarnia Facility, alleging that the wax product did not meet its requirements and it was not marketable. (D.I. 483, Exh. 8). The parties entered discussions to find a solution to HRD’s issues with the wax product, with Dow conducting additional production research at HRD’s request. (D.I. 483, Exhs. 9, 10, 11, 12). These discussions failed and production never resumed. (D.I. 483, Exh. 12). On January 18, 2005, Dow informed HRD that the Supply Agreement was terminated due to HRD’s failure to pay the “Capacity Rights Payment” and the “Annual Operating Payment.” (D.I. 1, Exhs. G-L). That same day, Dow filed the breach of contract action initiating this case. (D.I. 1).

[353] This Court has held that HRD breached the Supply Agreement after the contract’s Beneficial Manufacture milestone. (D.I. 444, pp. 6-7, 29). As this is a motion to establish damages, the payment provisions of the Supply Agreement are key. The Supply Agreement details three different types of payments to Dow. They are the Capacity Rights Payment (“CRP”), the Annual Operating Payment (“AOP”) and the Variable Cost Payment (‘VCP”). The CRP was intended to compensate Dow for its costs of converting the Sarnia Plant. (D.I. 483, Exh. 2 at ¶ 8.1.1). The CRP had two components; the “Estimated CRP,” due within 15 days of the Implementation Date, and the Final CRP, intended to “true up” the difference between the Estimated CRP and Dow’s actual conversion costs.3 (Id. at ¶¶ 8.1.1, 8.2.1). The Final CRP was to be invoiced within 90 days of the Beneficial Manufacture. (Id. at ¶ 8.1.1). The second type of payment, the AOP, was an annual fee of $16,500,000 Canadian Dollars [CAN] to be invoiced in monthly installments. (Id. at ¶¶ 8.1.2, 8.2.2). It was intended to compensate Dow for the operational costs of the Sarnia Plant and to include a profit margin. (Id. at ¶ 8.1.2). The third type of payment, the VCP, compensated Dow for the market cost of the raw materials used to make the wax product. (Id. at ¶ 8.1.3). Dow admits that HRD met its obligations with respect to the Estimated CRP of $6,792,000, the first AOP monthly installment invoice, and the VCP for each railcar. (D.I. 482, p. 5).

Dow argues that this breach triggered various enforceable stipulated damages provisions of the Supply Agreement. One provision requires HRD to pay Dow the unpaid AOP for the rest of the year of contract termination. (D.I. 483, Exh. 2 at ¶ 21.5.1.1.2). Because Dow did not send notice of termination to HRD until January 18, 2005, Dow argues it is owed the AOP for the entire year of 2005 as well as the unpaid 2004 installments. Another provision requires HRD to pay Dow the Final CRP payment. (Id. at ¶ 21.5.1.1.1). A third provision requires HRD to pay Dow $.05 per pound, multiplied by three times the Sarnia Plant’s Annual Capacity of 60 million pounds. (Id. at ¶ 21.5.1.1.3). According to Dow, this provision is intended to compensate Dow for its “lost opportunity,” as another provision of the Supply Agreement prohibited Dow from selling wax products for three years after contract termination. Finally, Dow argues that it is owed monthly interest of 1.5% on these damages as well as costs and attorneys’ fees. (Id. at ¶ 8.2.5).

Dow now moves for summary judgment on all of these damages claims. .

DISCUSSION

Dow argues that it is owed the AOP for the entire year of 2005, as the Supply Agreement calls for HRD to pay Dow the AOP for the entire calendar year of its termination and Dow communicated contract termination on January 18, 2005. HRD disagrees for three reasons: (1) the contract was constructively terminated in 2004; (2) the 2005 AOP damages stipulation is invalid as a penalty; (3) and Dow’s request fails to reflect Dow’s mitigation of its damages by closing the Sarnia Plant in 2004.

(a) Constructive termination

Free access — add to your briefcase to read the full text and ask questions with AI

Dow Chemical Canada Inc. v. HRD Corp., 909 F. Supp. 2d 350, 2012 WL 6622685, 2012 U.S. Dist. LEXIS 179293 (D. Del. 2012).

909 F. Supp. 2d 350 (Dow Chemical Canada Inc. v. HRD Corp.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Smart Sand, Inc. v. US Well Services LLC
Superior Court of Delaware, 2021