Dovetail Construction Co. v. Baumgartel, Unpublished Decision (9-25-2001)

CourtOhio Court of Appeals
DecidedSeptember 25, 2001
DocketCase No. 00CA2.
StatusUnpublished

This text of Dovetail Construction Co. v. Baumgartel, Unpublished Decision (9-25-2001) (Dovetail Construction Co. v. Baumgartel, Unpublished Decision (9-25-2001)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dovetail Construction Co. v. Baumgartel, Unpublished Decision (9-25-2001), (Ohio Ct. App. 2001).

Opinion

DECISION AND JUDGMENT ENTRY
This is an appeal from the judgment of the Washington County Court of Common Pleas. Plaintiff-Appellant Dovetail Construction Co., Inc., an Ohio corporation, sought damages from Defendants-Appellees Rolf E. and Megan Baumgartel for the balance allegedly due under certain agreements to construct a log home for appellees. Following a bench trial, the trial court found in favor of appellees and awarded them damages based on their counter-claim. Appellant appeals that judgment, as well as the trial court's denial of its motion for findings of fact and conclusions of law.

We find appellant's assignments of error to be without merit and affirm the judgment of the trial court.

The Contract and Construction
In October 1996, appellant and appellees entered into a written contract, which provided that appellant was to construct a log home for appellees. Appellant was to build the home using a log home kit procured from an independent supplier and paid for by appellees. The contract price for this construction was $84,710. The contract price did not include any necessary work for utility installation or driveway construction. Apparently, the parties orally agreed that the charges for work performed on utility installation and driveway construction were to be billed and paid for apart from the written contract. The parties also orally agreed to the amounts of those charges.

In November 1996, after appellees acquired the requisite financing and the log home kit to be used by appellant, construction of the log home commenced.

The Disagreements and Legal Action
While there were a number of disagreements during construction, none were of such magnitude that appellant or appellees took any formal action. In August 1997, appellees took possession of the log home and began living there. Ongoing negotiations between the parties to settle their differences were fruitless, and appellees notified appellant, by means of certified mail, that any entry upon appellees' property by appellant without appellees' express permission would be treated as a trespass.

In December 1997, appellant filed a complaint against appellees seeking both a judgment against them and foreclosure of a mechanic's lien on the log home and the property upon which it was situated. Appellees timely answered and filed a counter-claim against appellant.

In May 1998, appellees filed a motion for summary judgment. Appellant opposed appellees' motion. The trial court heard arguments on the motion in July 1998. The scope of this motion was limited to the foreclosure of appellant's purported mechanic's lien on appellees' property and whether appellant had properly perfected the lien. The trial court granted appellees' motion for summary judgment regarding the mechanic's lien in August 1998. This order is not a part of this appeal.

A number of motions, none of which are pertinent to this appeal, were filed and disposed of prior to trial. Commencing in late October 1999, a four-day bench trial was held.

The trial court filed its initial decision granting judgment to appellees on December 8, 1999. This entry was immediately followed by the trial court's "First Amended Decision" on December 9, 1999. The trial court entered a judgment in favor of appellees on their counter-claim in the amount of $20,935 plus interest and costs. The trial court found no fraud on the part of appellant and disallowed appellees' claim for treble damages.

On December 15, 1999, appellant filed a request for specific findings of fact and conclusions of law. The trial court denied the motion on the grounds that its amended decision complied with the requirements of Civ.R. 52. Appellant also filed a motion for a new trial, which was denied without a hearing.

The Appeal
Appellant timely appealed certain decisions of the trial court, raising eleven assignments of error for our consideration.

I. THE TRIAL COURT'S DETERMINATION OF THE AMOUNT THAT APPELLEES PAID APPELLANT UNDER THE CONTRACT IS IN ERROR.

II. THE TRIAL COURT ERRED AS A MATTER OF LAW IN ITS INTERPRETATION OF THE BUILDING CONTRACT ENTERED INTO BETWEEN THE PARTIES.

III. THE TRIAL COURT'S DETERMINATION THAT VARIATIONS WHICH THE APPELLANT MADE FROM THE MANUFACTURER'S RECOMMENDED FASTENING PATTERN IN THE INSTALLATION OF THE ROOF ON APPELLEES' RESIDENCE REQUIRED REPLACEMENT OF THE ROOF IS UNSUPPORTED BY EVIDENCE.

IV. THE TRIAL COURT ERRED IN NOT APPLYING THE TERMS OF THE VERBAL AGREEMENT BETWEEN APPELLANT AND APPELLEES TO DISPUTES BETWEEN THE PARTIES OVER THE DRIVEWAY.

V. THE TRIAL COURT'S DETERMINATION TO GRANT APPELLEES AN AMOUNT ESTIMATED TO BE $1,900 FOR REMOVING RAFTER SUPPORT AND REPLACING IS NOT SUPPORTED BY THE EVIDENCE.

VI. THE TRIAL COURT'S DETERMINATION TO GRANT APPELLEES AN AMOUNT ESTIMATED TO BE $875 FOR REWORKING COLLAR RAFTERS IS NOT SUPPORTED BY EVIDENCE.

VII. THE TRIAL COURT'S DETERMINATION TO GRANT APPELLEES AN AMOUNT ESTIMATED TO BE $562.50 FOR CAULKING AT THE CEILING AND PAINTING BOLTS IS NOT SUPPORTED BY THE EVIDENCE.

VIII. THE TRIAL COURT'S DETERMINATION TO GRANT APPELLEES AN AMOUNT ESTIMATED TO BE $2,765.25 FOR REMOVING BASEBOARD AND REPLACING IT WAS AGAINST THE WEIGHT OF THE EVIDENCE.

IX. THE COURT RECOGNIZED THAT APPELLEES VERBALLY AGREED TO SOME CHANGE ORDERS, BUT IT FAILED TO CREDIT APPELLANT FOR SOME CHANGE ORDERS WHICH WERE CONCEDED BY THE APPELLEES.

X. THE COURT ERRED IN FAILING TO CONSIDER ALTERNATIVE THEORIES OF RECOVERY ADVANCED BY APPELLANT ON ITEMS THAT APPELLANT INITIALLY BILLED AS CHANGE ORDERS.

XI. THE TRIAL COURT ERRED IN FAILING TO RESPOND AFFIRMATIVELY TO APPELLANT'S REQUEST FOR SEPARATE FINDINGS OF FACT AND CONCLUSIONS OF LAW.

For purposes of our analysis, we will address Assignment of Error One and Assignments of Error Three through Nine conjointly. The remaining assignments of error will be addressed in turn.

I. Factual Findings of the Trial Court
Our analysis begins with those assignments of error that challenge the factual findings of the trial court, namely Assignment of Error One and Assignments of Error Three through Nine.

In reviewing factual findings of a trial court, the appropriate standard of review that an appellate court must apply is manifest weight of the evidence. The judgment of a trial court should not be overturned as being against the manifest weight of the evidence if some competent and credible evidence supports that judgment. See C.E. Morris Co. v. Foley Construction Co. (1978), 54 Ohio St.2d 279, 376 N.E.2d 578. Factual findings of the trial court are to be given great deference on review because the trial court is in a better position "to view the witnesses and observe their demeanor, gestures and voice inflections, and use these observations in weighing the credibility of the proffered testimony." Seasons Coal Co. v. Cleveland (1984), 10 Ohio St.3d 77, 80,461 N.E.2d 1273, 1276; see, also, Myers v. Garson (1993),66 Ohio St.3d 610, 615, 614 N.E.2d 742, 745.

A.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reineck v. Randall
484 N.E.2d 1061 (Ohio Court of Appeals, 1984)
In Re Fetzer
692 N.E.2d 219 (Ohio Court of Appeals, 1997)
Abney v. Western Reserve Mutual Casualty Co.
602 N.E.2d 348 (Ohio Court of Appeals, 1991)
Drake Center, Inc. v. Ohio Department of Human Services
709 N.E.2d 532 (Ohio Court of Appeals, 1998)
Barton v. Ellis
518 N.E.2d 18 (Ohio Court of Appeals, 1986)
Ottery v. Bland
536 N.E.2d 651 (Ohio Court of Appeals, 1987)
Ford Motor Co. v. John L. Frazier & Sons Co.
196 N.E.2d 335 (Ohio Court of Appeals, 1964)
McCray v. Clinton County Home Improvement
708 N.E.2d 1075 (Ohio Court of Appeals, 1998)
Sammarco v. Anthem Insurance Companies, Inc.
723 N.E.2d 128 (Ohio Court of Appeals, 1998)
Sites v. Moore
607 N.E.2d 1114 (Ohio Court of Appeals, 1992)
McKay Machine Co. v. Rodman
228 N.E.2d 304 (Ohio Supreme Court, 1967)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
Ohio Bell Telephone Co. v. Public Utilities Commission
593 N.E.2d 286 (Ohio Supreme Court, 1992)
Myers v. Garson
614 N.E.2d 742 (Ohio Supreme Court, 1993)
Nationwide Mutual Fire Insurance v. Guman Bros. Farm
652 N.E.2d 684 (Ohio Supreme Court, 1995)
Sammarco v. Anthem Insurance Companies, Inc.
719 N.E.2d 963 (Ohio Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
Dovetail Construction Co. v. Baumgartel, Unpublished Decision (9-25-2001), Counsel Stack Legal Research, https://law.counselstack.com/opinion/dovetail-construction-co-v-baumgartel-unpublished-decision-9-25-2001-ohioctapp-2001.