Douglas Environmental Associates, Inc. v. Massachusetts Department of Environmental Protection

7 Mass. L. Rptr. 524
CourtMassachusetts Superior Court
DecidedJuly 24, 1997
DocketNo. 932753B
StatusPublished

This text of 7 Mass. L. Rptr. 524 (Douglas Environmental Associates, Inc. v. Massachusetts Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Douglas Environmental Associates, Inc. v. Massachusetts Department of Environmental Protection, 7 Mass. L. Rptr. 524 (Mass. Ct. App. 1997).

Opinion

Botsford, J.

Introduction

The plaintiffs Douglas Environmental Associates, Inc. and Vincent Barletta (collectively referred to as DEA) bring this action to challenge the repeated denials by the Department of Environmental Protection (the department) of a permit to construct an integrated landfill facility in Douglas, Massachusetts. DEA began its efforts to secure the necessary agency approvals for the landfill project in 1987; the department’s latest decision denying the necessary construction permit is dated September 22, 1995.

One count of DEA’s amended complaint seeks review of the department’s decision denying the operating permit pursuant to G.L.c. 30A, §14, and presently before the court is DEA’s motion for partial summary judgment on this count. The department has filed the voluminous administrative record with its answer. DEA argues that the 1995 permit denial must be reversed because, inter alia, it is unsupported by substantial evidence, arbitrary and capricious, and based on error of law. The department and the intervenor-defendants, the Town of Webster and eighteen citizens who represent themselves and Citizens for a Clean Environment, an unincorporated association (collectively referred to as the intervenors), argue that the department’s decision should be affirmed. For the reasons discussed below, DEA’s motion for partial summary judgment is allowed.

Background3

What DEA proposes to build is an integrated solid waste management facility that would include landfilling, recycling and composting operations. The facility would be built on 982 acres of industrially zoned, wholly undeveloped land which DEA owns in Douglas, abutting the Douglas state forest. The proposal further calls for the facility to -be developed in four phases, with each phase allowing approximately five years of operating capacity. The permit at issue here relates to phase one of the facility’s landfill operation, and if granted, would authorize the construction of a 35 acre landfill with seven cells and related structures.4

The siting of and approval of permits for waste disposal facilities is governed by G.L.c. 111, §150A. As indicated, DEA initiated the multi-phase administrative process to obtain permission to build the landfill facility in 1987, beginning with site assignment proceedings before the Douglas board of health.5 Since 1992, DEA has been before the department seeking the necessary permit to construct the landfill facility. The history of the department’s dealings with DEA since September 1992 has been quite extraordinary in many respects, but one of its significant attributes is its length.

1. The September 1992 draft permit and the April 1993 final permit denial.

In September 1992, the department granted DEA a draft landfill construction permit for phase one of the [525]*525project. This draft proposed to allow DEA to accept 1500 tons per day of solid waste, of which 600 tons per day could be municipal solid waste (residential, commercial and institutional waste). The issuance of the draft permit was followed by two public hearings and the submission of many comments and much information to the department in connection with DEA’s construction permit application. The record reveals that there has been substantial and often intense local opposition to the proposed facility, as well as opposition from other quarters, including the department.

In April 1993, the department issued a final decision denying the permit. Its denial was based on two issues: (1) the hydrogeological aspects of the project, and in particular, the claimed failure of DEA to determine accurately the site characteristics and to demonstrate that the environmental monitoring system was adequate; and (2) the claimed failure of DEA to show that the project would not constitute a threat to certain identified endangered species and species of special concern under the Massachusetts Endangered Species Act (MESA), G.L.c. 131A.6 On both points, the department concluded that more studies would need to be completed and submitted by DEA, and without them, no permit could be issued.

In a memorandum of decision dated December 9, 1993, I allowed DEA’s motion for partial summary judgment seeking reversal of the department’s 1993 permit denial under G.L.c. 30A, §14. The basis of the decision was that the department had violated DEA’s due process rights by basing its decision on reports and information that either were never made available to DEA for comment before the permit denial was issued, or were submitted too late for DEA to comment on. The case was remanded to the department for further proceedings, and specifically to allow DEA (and other interested parties) a full opportunity to respond to the hydrogeological reports and the letter from the Division of Fisheries and Wildlife (DFW)7 which had played a significant role in the department’s decision. (Administrative Record [A.R.], ex. S41.)

2. The January 13, 1995 partial decision.

Although the remand decision was issued in December 1993, the department did not reopen the public record for public comment until March 1994. The public comment period in fact ran from March 30, 1994 to June 1994, and was reopened by the department to run again from July to August 16, 1994. The department then reviewed all the public comments it received, including further hydrogeological reports submitted by DEA and reports on rare species surveys conducted on DEA’s behalf, for the next five months.

The administrative record reveals that in December 1994, Thomas Powers, then the Acting Commissioner of the department, wrote a memorandum to Trudy Coxe, the Secretary of Environmental Affairs, in which he stated that (1) the department’s staff were now “reasonably convinced” the site was adequately monitorable from a hydrogeological point of view, and (2) DEA had established, to the satisfaction of DFW as the concerned agency, that the rare species on which the department had based its April 1993 permit denial were not present on the site, although DEA had discovered the presence of marbled salamanders, a threatened but not endangered species, and spotted turtles, a species of special concern. The memorandum went on to state:

DFW has submitted a letter adopting the [DEA] consultant’s conclusions on species identification and their suggestion that the species and the landfill can co-exist provided buffer zones are established and physical barriers constructed between the breeding grounds and landfill footprint. Given DFW’s position, the realization there are no endangered species, the availability of surrounding suitable habitat and the general difficulty in justifying permit decisions on species issues, I don’t believe a permit denial should rest solely on salamander or turtle habitat considerations . . .

(A. R. ex. 1 .)8

The memorandum then turned to the issue of disposal capacity need. The Acting Commissioner stated a belief that the department could reopen the issue despite the fact that the 1993 permit denial did not touch upon it, and outlined an “alternative approach” to capacity need based on a “permitting hierarchy” where land fill “mining and expansion projects would require consideration over a proposal [like DEA’s] that would despoil open space.” (Id.) The memorandum offered two options with respect to the upcoming DEA permit decision:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Chase v. Pevear
419 N.E.2d 1358 (Massachusetts Supreme Judicial Court, 1981)
Boston Gas Co. v. Department of Public Utilities
324 N.E.2d 372 (Massachusetts Supreme Judicial Court, 1975)
Simon v. State Examiners of Electricians
479 N.E.2d 649 (Massachusetts Supreme Judicial Court, 1985)
Cohen v. Board of Registration in Pharmacy
214 N.E.2d 63 (Massachusetts Supreme Judicial Court, 1966)
Johnson v. Kennedy
214 N.E.2d 276 (Massachusetts Supreme Judicial Court, 1966)
MacGibbon v. Board of Appeals of Duxbury
340 N.E.2d 487 (Massachusetts Supreme Judicial Court, 1976)
D'AMOUR v. Board of Registration in Dentistry
567 N.E.2d 1226 (Massachusetts Supreme Judicial Court, 1991)
Salisbury Water Supply Co. v. Department of Public Utilities
184 N.E.2d 44 (Massachusetts Supreme Judicial Court, 1962)
Town of Hamilton v. Department of Public Utilities
190 N.E.2d 545 (Massachusetts Supreme Judicial Court, 1963)
Langlitz v. Board of Registration of Chiropractors
486 N.E.2d 48 (Massachusetts Supreme Judicial Court, 1985)
Flint v. Commissioner of Public Welfare
589 N.E.2d 1224 (Massachusetts Supreme Judicial Court, 1992)
Bays' Legal Fund v. Browner
828 F. Supp. 102 (D. Massachusetts, 1993)
School Committee v. Massachusetts Commission Against Discrimination
280 N.E.2d 404 (Massachusetts Supreme Judicial Court, 1972)
New Boston Garden Corp. v. Board of Assessors
420 N.E.2d 298 (Massachusetts Supreme Judicial Court, 1981)
Quincy v. Planning Board
652 N.E.2d 901 (Massachusetts Appeals Court, 1995)

Cite This Page — Counsel Stack

Bluebook (online)
7 Mass. L. Rptr. 524, Counsel Stack Legal Research, https://law.counselstack.com/opinion/douglas-environmental-associates-inc-v-massachusetts-department-of-masssuperct-1997.