Douglas Environmental Associates, Inc. v. Massachusetts Department of Environmental Protection

1 Mass. L. Rptr. 407
CourtMassachusetts Superior Court
DecidedDecember 9, 1993
DocketNo. 93-2753-B
StatusPublished

This text of 1 Mass. L. Rptr. 407 (Douglas Environmental Associates, Inc. v. Massachusetts Department of Environmental Protection) is published on Counsel Stack Legal Research, covering Massachusetts Superior Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Douglas Environmental Associates, Inc. v. Massachusetts Department of Environmental Protection, 1 Mass. L. Rptr. 407 (Mass. Ct. App. 1993).

Opinion

Botsford, J.

In a final decision dated April 16, 1993, the Department of Environmental Protection (the Department) denied the application for a landfill construction permit filed by the plaintiff Douglas Environmental Associates, Inc. (DEA).3 DEA brings this action to challenge that decision on a number of grounds; also raised are claims against the Commissioner of the Department and certain others related to actions taken by them in connection with the permit application proceedings.

By agreement of the parties, DEA is first pursuing its claim against the Department brought under G.L.c. Ill, §150Aand c. 30A, §14, which is setforthin Count IV of the verified complaint. To that end, the Department has filed the record of its administrative proceeding leading to the decision denying the permit. DEA has now filed a motion for partial summary judgment on the c. 30A claim; the Department opposes the motion. For the reasons discussed below, DEA’s motion for partial summary judgment is ALLOWED.

BACKGROUND

The record filed by the Department and submissions of the parties reveal the following undisputed facts. In 1987, DEA began the multi-step administrative process to obtain a permit to construct a solid waste landfill facility in Douglas, Massachusetts. The proposed landfill would include landfilling, recycling and composting operations, to be developed in four phases, with each phase allowing approximately five years of operating capacity. The landfill construction permit at issue here relates to phase one of the proposed landfill, and seeks approval for the construction of a 35-acre landfill with seven cells and related structures.4 The proposed landfill would receive up to 1500 tons per day of municipal trash.

Before seeking the landfill construction permit, DEA was required to obtain a site assignment from the Douglas board of health.5 The site assignment was granted on April 1, 1987; opponents to the landfill project then appealed the board of health’s decision to the Department. The Department’s review of the site assignment decision was stayed, however, to permit DEA to file with the Secretary of Environmental Affairs an environmental impact report concerning the proposed project in compliance with the Massachusetts Environmental Policy Act (MEPA), G.L.c. 30, §§62A-62H. On February 20, 1990, the secretary certified that DEA had met the requirements of MEPA by filing a complete report.

The Department then undertook its review of the board of health’s site assignment determination. On March 6, 1991, after a public hearing and a review of the public comments filed, the Department upheld the determination. Judicial review of the Department’s decision was sought by the Town of Webster and an unincorporated association called Citizens for a Clean Environment. In a decision dated August 21, 1992, a judge of this court (McDaniel, J.) affirmed the Department’s site assignment decision.

In contemplation of DEA’s application for the facility construction permit, DEA and the Department entered into a “Multiple Permit Alternative Schedule Project Fee and Schedule Agreement” (fee and schedule agreement) pursuant to the Department’s regulations. See 310 Code Mass. Regs. §4.00 et seq. Pursuant to the fee and schedule agreement, DEA paid the Department a permit application fee of $52,065; the Department in turn agreed to process and review the landfill construction permit within prescribed time frames and in accordance with 310 Code Mass. Regs. §4.00.

On February 27, 1992, the Department determined that DEA’s permit application was administratively complete. The Department then undertook a technical review of the application for the next six months. It determined during this process that additional information about, among other things, the hydrogeologic characteristics of the landfill site was needed, and DEA responded by providing more information and conducting more studies. On September 25, 1992, the Department determined that the application was technically complete; it also issued a decision granting DEA a draft landfill construction permit on the same date. After public notice, a public hearing on the draft permit was held on November 18,1992. Thereafter, on December 29, 1992, a public meeting was held in Douglas at the request of certain legislators. The public comment period on the draft permit was extended to January 15, 1993.

During the public comment period, the Department received many submissions, including a hydrogeology [408]*408report of Patrick Barosh & Associates (the Barosh report) and various letters concerning the existence of rare animal species on the proposed landfill site. On January 15, 1993, the DEP ceased receiving public comments and began reviewing the full permit application record.6

As part of its review, and following the close of the public comment period, the Department set up two “peer review” processes, one to deal with hydrogeological issues and one to deal with rare or endangered species questions. With respect to hydrogeology, the Department retained the services of seven hydrogeologists who were not otherwise employed by the Department or the Commonwealth — most worked for private companies — to conduct a review of the Department’s own technical file relating to the permit application as well as the information submitted dialing the public comment period.7 This hydrogeological peer review committee met in February 1993 with several officials and staff of the Department to conduct the review and answer ten questions about hydrogeological concerns. A written report of the peer review committee’s responses was prepared by an employee of the Department and approved by all the committee members.8 The report states that in the committee’s judgment, DEA had not submitted sufficient documentation of the proposed site’s bedrock fracture or lineament features to permit an informed decision that the site was monitorable. It also sets forth a detailed recommendation for a multi-phase study of the bedrock fracture system that should be undertaken. The report, dated March 19, 1993, was submitted to the Commissioner for his consideration in making a final decision on the permit application. That report was not provided to DEA or any other interested party before the Department's decision was issued.

The second peer review involved seeking the advice and recommendations of the Division of Fisheries and Wildlife (DFW) with respect to rare species issues raised by the permit application. Again, the Department set up this “review” after January 15, 1993. The commissioner of DFW submitted a letter to the Department on March 5, 1993, responding to questions posed by the Department. The DFW letter sets forth information about observations of certain rare species in the area of the proposed landfill site which appears to come from the agency’s own records as well as records of a program entitled the Natural Heritage and Endangered Species Program. It does not appear that all of the factual information discussed in the DFW letter was presented to the Department during the public comment period. The DFW letter was not provided to DEA or any other interested party before the close of the public comment period.

On April 16, 1993, the Department issued its final decision on DEA’s permit application. The decision denies the application, and specifies that the denial is based on two issues: the hydrogeology of the site and protection of endangered and rare species.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Norway Cafe, Inc. v. Alcoholic Beverages Control Commission
386 N.E.2d 32 (Massachusetts Appeals Court, 1979)
Vitale v. Planning Board of Newburyport
409 N.E.2d 237 (Massachusetts Appeals Court, 1980)
National Wildlife Federation v. Marsh
568 F. Supp. 985 (District of Columbia, 1983)
Massachusetts General Hospital v. Commissioner of Public Welfare
216 N.E.2d 434 (Massachusetts Supreme Judicial Court, 1966)
Bottomley v. Division of Administrative Law Appeals
22 Mass. App. Ct. 652 (Massachusetts Appeals Court, 1986)
Marathon Oil Co. v. Environmental Protection Agency
564 F.2d 1253 (Ninth Circuit, 1977)
Seacoast Anti-Pollution League v. Costle
572 F.2d 872 (First Circuit, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
1 Mass. L. Rptr. 407, Counsel Stack Legal Research, https://law.counselstack.com/opinion/douglas-environmental-associates-inc-v-massachusetts-department-of-masssuperct-1993.