Donovan v. A.A. Beiro Construction Co.

746 F.2d 894, 241 U.S. App. D.C. 161, 12 OSHC (BNA) 1017, 1984 U.S. App. LEXIS 17347
CourtCourt of Appeals for the D.C. Circuit
DecidedOctober 26, 1984
DocketNos. 83-2008, 83-2053
StatusPublished
Cited by6 cases

This text of 746 F.2d 894 (Donovan v. A.A. Beiro Construction Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the D.C. Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Donovan v. A.A. Beiro Construction Co., 746 F.2d 894, 241 U.S. App. D.C. 161, 12 OSHC (BNA) 1017, 1984 U.S. App. LEXIS 17347 (D.C. Cir. 1984).

Opinion

Opinion for the Court filed by Circuit Judge WALD.

WALD, Circuit Judge:

A.A. Beiro Construction Company, Inc. (“Beiro”) was one of a number of prime contractors engaged in the construction of the District of Columbia Convention Center. Beiro was cited for both serious and nonserious violations of section 5(a)(2) of the Occupational Safety and Health Act, 29 U.S.C. §§ 651-78 (“the Act”) following an Occupational Safety and Health Administration (“OSHA”) inspection of the construction site.1 Beiro contested all of the citations, alleging that OSHA lacked proper authority to conduct a warrantless inspection and that Beiro was a victim of vindictive and selective prosecution. Following an evidentiary hearing, the administrative law judge (“AU”) found that OSHA had obtained proper consent for the inspection and had not vindictively prosecuted Beiro, but vacated three serious and three nonserious citations on substantive grounds. Both the Secretary of Labor (“Secretary”) and Beiro timely petitioned the Occupational Safety and Health Review Commission (“the Commission”) for discretionary review. The AU decision became a final order when no Commissioner directed review. 29 U.S.C. § 661(i). The case is be[164]*164fore this court on cross-petitions of Beiro and the Secretary pursuant to section 11(a) of the Act, 29 U.S.C. § 660(a). Beiro claims the AIJ erred in finding that the inspection did not violate the fourth amendment or OSHA regulations and that Beiro was not vindictively and selectively prosecuted. The Secretary claims the AU erred in vacating serious citation item 8 and non-serious citation item 2. We affirm the decision of the AU on all counts.

I. Background

Contrary to standard practice, there was no one prime contractor for the District of Columbia Convention Center construction project. Instead the D.C. Government entered into contracts with a number of “prime contractors,” with one, the Fuller-Griffin Company, also being retained as the construction superintendent for the project. Hence, the Fuller-Griffin Company along with Mr. Gordon, the Project Manager for the D.C. Government, represented the District at the worksite.

The Convention Center construction site came up on OSHA’s “general inspection” list in early 1981. The inspection was assigned to Mr. Tupper, an OSHA compliance officer. Before Mr. Tupper got around to making the general inspection, OSHA received a complaint about safety conditions at the site from an employee of one of the construction companies at the site, Midwest Steel Erectors. Mr. Tupper was then assigned to service the employee complaint as well as conduct the general inspection.

On March 2, 1981, Mr. Tupper arrived at the construction site to carry out his assigned tasks. He was directed to the office of Mr. Pope, Project Manager for the Fuller-Griffin Company. Mr. Tupper showed his credentials, advised Mr. Pope of the nature of his inspection, and asked Mr. Pope to assemble the representatives of all the contractors at the site. All of the representatives arrived and agreed to cooperate with the inspection, including Midwest Steel Erectors. All except Beiro.

Beiro was one of the prime contractors at the site engaged in erecting basic concrete structures. Beiro’s General Superintendent, Mr. Martin, was the last to arrive at the meeting. He asked Mr. Tupper to wait until Beiro’s Safety Director, Mr. Braswell, arrived. When Mr. Braswell arrived, he informed Mr. Tupper that he was not going to allow any part of Beiro’s work area to be inspected without a warrant. Mr. Tupper responded that his first concern was to investigate the Midwest Steel employee complaint. Mr. Braswell, however, continued to object because Mr. Tupper would be able to view Beiro’s work in progress once he was on the site. Mr. Martin and Mr. Braswell then positioned themselves in the doorway so as to physically block Mr. Tupper from exiting the office to perform his inspection. Mr. Tupper called his supervisor, Mr. Holmes, who advised Mr. Tupper to consider Beiro’s actions a denial of entry and to leave the worksite.

The following day, March 3, 1981, Mr. Holmes informed Mr. Tupper that all the legal problems had been resolved and that the D.C. Government, owner of the work-site, had consented to the inspection. Mr. Tupper returned to the worksite with two other compliance officers. Mr. Gordon met them at the site and confirmed that the D.C. Government would fully cooperate with the inspection. The OSHA team then proceeded to conduct its inspection beginning with Beiro. Mr. Braswell and Beiro’s legal counsel, Mr. Rubenstein, accompanied the compliance officers during the inspection of Beiro.

As a result of this inspection, Beiro was issued serious and nonserious citations, carrying a total proposed penalty of $6900. Beiro contested the citations claiming that OSHA had conducted an illegal inspection. Specifically, Beiro argued that the inspection violated Beiro’s fourth amendment rights, the Act, and OSHA regulations. In addition, Beiro claimed to be a victim of vindictive and selective prosecution. The AU found that the OSHA inspection was conducted pursuant to valid consent obtained from the D.C. Government and that Beiro’s other claims lacked merit. The [165]*165ALJ decision also vacated a number of the citations on substantive grounds.

On this appeal Beiro continues to argue that OSHA conducted an illegal inspection and that it was a victim of vindictive and selective prosecution. The Secretary argues that the ALJ erred in vacating two of the citations.

II. The OSHA Inspection

The Act authorizes two types of inspections: an inspection pursuant to a general administrative plan, 29 U.S.C. § 657(a); and an inspection pursuant to an employee complaint, 29 U.S.C. § 657(f). Neither section of the Act mentions the need for a search warrant or other process.2 The Supreme Court, however, held in Marshall v. Barlow’s, Inc., 436 U.S. 307, 98 S.Ct. 1816, 56 L.Ed.2d 305 (1978), that an administrative search warrant is required for nonconsensual OSHA inspections. The Court, nonetheless, noted that “the great majority of businessmen can be expected in normal course to consent to inspection without warrant....” Id. at 316, 98 S.Ct. at 1822. Since OSHA conducted a warrantless inspection of Beiro, the questions to be addressed by the court are whether OSHA had obtained valid consent to inspect and, if so, whether the inspection exceeded the scope of that consent. The AU concluded that “the reliable and creditable evidence” of the record established that “the OSHA inspection of the D.C. Convention Center worksite, and Beiro’s construction activities thereon, on March 3 and 4, 1981, was made pursuant to consent properly, sought and obtained from appropriate and authorized representatives of the D.C. Government, the owner of the worksite.” See AU Decision at 43.

A. Consent to Inspection

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
746 F.2d 894, 241 U.S. App. D.C. 161, 12 OSHC (BNA) 1017, 1984 U.S. App. LEXIS 17347, Counsel Stack Legal Research, https://law.counselstack.com/opinion/donovan-v-aa-beiro-construction-co-cadc-1984.