Donnes v. Four Beers

2022 MT 52N, 505 P.3d 391
Montana Supreme Court·Decided March 15, 2022·No. DA 21-0304·Unpublished

Opinion

03/15/2022

DA 21-0304 Case Number: DA 21-0304

IN THE SUPREME COURT OF THE STATE OF MONTANA 2022 MT 52N

DONNES, INC., a Montana Corporation,

Plaintiff and Appellant,

v.

FOUR BEERS, INC., a Montana Corporation, d/b/a STILLWATER EXCAVATING,

Defendant and Appellee.

APPEAL FROM: District Court of the Twenty-Second Judicial District, In and For the County of Stillwater, Cause No. DV 17-61 Honorable Matthew J. Wald, Presiding Judge

COUNSEL OF RECORD:

For Appellant:

W. Scott Green, Daniel L. Snedigar, Patten, Peterman, Bekkedahl & Green, PLLC, Billings, Montana

For Appellee:

Adam J. Tunning, Morgan Hoyt, Moulton Bellingham, PC, Billings, Montana

Submitted on Briefs: February 25, 2022

Decided: March 15, 2022

Filed:

c ir-641.—if __________________________________________ Clerk Justice Beth Baker delivered the Opinion of the Court.

¶1 Pursuant to Section I, Paragraph 3(c), Montana Supreme Court Internal Operating

Rules, this case is decided by memorandum opinion and shall not be cited and does not

serve as precedent. Its case title, cause number, and disposition shall be included in this

Court’s quarterly list of noncitable cases published in the Pacific Reporter and Montana

Reports.

¶2 Four Beers, Inc., (Stillwater Excavating) subcontracted with Donnes, Inc., to

perform work on a large earthmoving project for the Stillwater Mine in South Central

Montana (Mine). Donnes sued Stillwater Excavating for breach of contract and unjust

enrichment to recover for “extra work” it claims to have completed during the mitigation

of a highwall collapse in 2016. The District Court granted partial summary judgment to

Stillwater Excavating on Donnes’s breach of contract claim and, following a bench trial,

entered judgment for Stillwater Excavating on Donnes’s unjust enrichment claim. The

court also granted Stillwater Excavating statutory attorney fees and costs. Donnes appeals,

alleging that the District Court erred in its findings of fact and conclusions of law and

improperly awarded attorney fees to Stillwater Excavating. We affirm.

¶3 In 2015, Stillwater Excavating entered a contract with the Mine for the “Benbow

Project,” under which Stillwater Excavating agreed to excavate and move earth around a

mine entrance owned by the Mine. Stillwater Excavating entered a subcontract agreement

with Donnes to provide some earth-moving services for the Benbow Project. In June 2016,

the Benbow Project suffered the second of two “highwall collapses,” in which previously

excavated and placed material slid down a hill and needed to be replaced to satisfy safety

2 regulations. As a result of the collapse, the Mine hired Knight Piesold Consulting

(Knight Piesold) to recommend highwall mitigation measures. On June 27, 2016,

Knight Piesold submitted a plan to the Mine recommending construction of a buttress

adjacent to the highwall using materials excavated from an area around the mine entrance

referred to as the “Portal Pad.” The plan contained two measurements relevant to this

dispute. The first pertained to the buttress’s minimum elevation, which was necessary to

satisfy safety regulations; Knight Piesold’s plan stated that the Mine needed to construct

the buttress at 6,530 feet elevation. The second measurement pertained to the depth of the

Portal Pad excavation; Knight Piesold recommended that the Mine excavate the Portal Pad

thirteen feet below grade.

¶4 Stillwater Excavating and Donnes orally agreed to complete the necessary

excavation to construct the buttress and to split evenly the proceeds paid by the Mine. They

prepared a cost estimate for the project based on the volume of dirt they expected to move

in accordance with Knight Piesold’s plan. Consistent with that plan, Stillwater Excavating

and Donnes estimated that they would need to excavate, haul, and place a total of 67,500

cubic yards of dirt. On July 11, 2016, the Mine accepted the parties’ cost proposal and

entered into an agreement with Stillwater Excavating: “Field Change Notice No. 016”

(FCN 16). FCN 16 provided, in part, that Stillwater Excavating would construct the

buttress with material excavated from the Portal Pad and that Stillwater Excavating would

lower the Portal Pad’s elevation by thirteen feet.

¶5 In August 2016, while the project was still underway, the buttress reached a height

of 6,530 feet. The parties had at that point moved 60,000 cubic yards of dirt, and the

3 Portal Pad had not yet been excavated thirteen feet below its original elevation. After a

short pause caused by confusion about the two measurements, the Parties agreed to

continue excavating into the Portal Pad and adding the excavated material onto the buttress

until they lowered the Portal Pad by thirteen feet. Donnes claims that it was to be

compensated for work that exceeded the 6,530-foot elevation mark; Stillwater Excavating

denies discussing such additional terms. On August 10, 2016, Knight Piesold drafted a

letter to the Mine revising the final height of the buttress, but the parties did not receive or

rely on this letter.

¶6 Stillwater Excavating and Donnes completed the Portal Pad buttress project at the

end of August 2016. As agreed, the Mine paid Stillwater Excavating $1,159,091.64, and

Stillwater Excavating paid Donnes fifty percent of the proceeds ($579,545.82). When they

completed the project, the parties had moved roughly 69,000 cubic yards of dirt onto the

buttress. Of that volume, approximately 9,938 cubic yards of dirt were added above the

6,530-foot elevation point. Several months later, Donnes sent Stillwater Excavating a

request for payment for the 9,938 cubic yards it moved above 6,530 feet, claiming that it

was “extra” work. When Stillwater Excavating did not agree, Donnes sued for breach of

contract, alleging unjust enrichment as an alternative claim. The District Court granted

summary judgment to Stillwater Excavating on its breach of contract claim because, even

if Donnes could establish that it had a separate contract with Stillwater Excavating to

construct the buttress above 6,530 feet elevation, the contract would be void for lack of

4 certainty as there was no evidence the parties discussed any payment terms for work that

went beyond what was included in the lump sum set forth in FCN 16.1

¶7 The District Court held a bench trial on Donnes’s remaining claim for unjust

enrichment. Greg Russell, Stillwater Excavating’s project manager, testified that the

6,530-foot mark represented the minimum elevation at which the buttress needed to be

constructed for safety purposes. He said that the elevation of the buttress did not factor

into the cost estimates, which were prepared by Stillwater Excavating and Donnes and

submitted to the Mine, nor did the elevation of the buttress serve as the basis for

Stillwater Excavating and Donnes’s agreement. Rather, Russell testified that the cost

proposal was based on the volume of dirt moved. He also explained that the 69,000 cubic

yards of dirt moved amounted to only two percent more than the agreed upon 67,500 cubic

yards. Donnes’s expert, Richard Stryker, admitted that excavation contractors generally

do not receive additional compensation for quantities that exceed estimates by less than

ten percent. Donnes’s president, Frank Donnes, testified that Stillwater Excavating and

Free access — add to your briefcase to read the full text and ask questions with AI

Donnes v. Four Beers, 2022 MT 52N, 505 P.3d 391 (Mo. 2022).

2022 MT 52N (Donnes v. Four Beers) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Cameron v. Mercer
1998 MT 134 (Montana Supreme Court, 1998)
In Re the Estate of Lande
1999 MT 179 (Montana Supreme Court, 1999)
Schmieding v. Schmieding
2000 MT 237 (Montana Supreme Court, 2000)
Mountain West Farm Bureau Mutual Insurance v. Brewer
2003 MT 98 (Montana Supreme Court, 2003)
Blue Ridge Homes, Inc. v. Thein
2008 MT 264 (Montana Supreme Court, 2008)
State v. Sage
2010 MT 156 (Montana Supreme Court, 2010)
Northern Cheyenne Tribe v. Roman Catholic Church
2013 MT 24 (Montana Supreme Court, 2013)
Boyne USA, Inc. v. Spanish Peaks Development, LLC
2013 MT 1 (Montana Supreme Court, 2013)
Moore v. Goran, LLC
2017 MT 208 (Montana Supreme Court, 2017)
Montana Digital v. Trinity Church
2020 MT 250 (Montana Supreme Court, 2020)
Associated Mgmt. Servs., Inc. v. Ruff
2018 MT 182 (Montana Supreme Court, 2018)