Don M. Barron Contractor, Inc. v. City of Natchitoches

879 So. 2d 414, 4 La.App. 3 Cir. 173, 2004 La. App. LEXIS 1773, 2004 WL 1496890
CourtLouisiana Court of Appeal
DecidedJuly 7, 2004
DocketNo. 2004-173
StatusPublished
Cited by1 cases

This text of 879 So. 2d 414 (Don M. Barron Contractor, Inc. v. City of Natchitoches) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Don M. Barron Contractor, Inc. v. City of Natchitoches, 879 So. 2d 414, 4 La.App. 3 Cir. 173, 2004 La. App. LEXIS 1773, 2004 WL 1496890 (La. Ct. App. 2004).

Opinions

hTHIBODEAUX, Chief Judge.

In this public bid law case, plaintiff-appellant, Don M. Barron Contractor, Inc. (Barron), the second lowest bidder on a city construction project, appeals the judgment of the trial court in favor of the City of Natchitoches, Louisiana (the City). The judgment dismissed Barron’s petition for injunctive relief recalling the temporary restraining order it obtained on December 12, 2003. Barron sought injunctive relief against the City to prevent it from contracting with CBC Services, Inc. (CBC), the apparent low bidder for the construction of an alternate water supply for the City. For the following reasons, we affirm the judgment of the trial court.

I.

ISSUE

The issue in this case is whether the trial court properly applied La.R.S. 38:2212(A)(l)(a), also called the “Public Bid Law,” where the lowest bidder did not properly fill in the blanks of the bid form supplied by the City to potential construction bidders.

II.

FACTS

The facts of this case are not disputed. Sibley Lake provides water for the City. To supply an alternate water source for the city in times of drought, the City decided to connect Sibley Lake with Bayou Pierre. Thereafter, the City advertised for bids on the construction project that would link the two water bodies. Public bids were opened in November 2003. CBC and Barron were two of the seven companies that bid on the project. The City determined that CBC provided the lowest bid at $1,449,180.00, and Barron provided the second lowest bid at $1,502,633.50, a ^difference of $53,453.50. After a meeting of the City’s evaluation committee, the City chose to award the contract to CBC.

Barron objected to the City’s action awarding the contract to CBC. However, its objection was to no avail as the City Council voted unanimously to award the project contract to CBC because it was the lowest responsible bidder. Thereafter, Barron filed a petition for injunctive relief seeking a temporary restraining order and preliminary injunction against the City to enjoin it from executing the contract with CBC for the construction of the alternate water supply project. CBC intervened supporting the City’s position in this matter. Barron alleged that it, not CBC, was actually the lowest responsible bidder because CBC failed to complete the City’s bid form correctly.

The portion of the bid form regarding the price of the top soil required to complete the project is at issue. Portions of the City’s bid form required that the bidders provide prices based on the per unit cost of a listed item. In one column, the amount per unit of material is to be written in both words and numerals. The form provided that “[i]n case of discrepancy, the amount in words will govern.” The bid form stated that the project would require 250 cubic yards of top soil. Thus, [416]*416in the unit price column, the bidders were required to write the price of one cubic yard of soil. In the last column, the bidder is required to provide the total cost by multiplying the cost per cubic yard of topsoil by 250 cubic yards. In the present case, CBC correctly noted the topsoil at $20.00 per cubic yard in the blank provided for placing the cost in numeric terms. However, in the blank provided for writing out the monetary term in words, CBC wrote out the total cost of providing topsoil for the project instead of writing the unit price of “twenty dollars and no/100.” Thus, from the words written in that blank, it appears that CBC quoted a $5,000.00 unit price for |3the topsoil, which, when calculated, results in a total cost, for just the project’s topsoil needs, of $1,250,000.00, which would make CBC’s bid clearly higher than Barron’s bid when the cost of the remainder of the project’s needs are taken into account. CBC did correctly write the total cost of $5,000.00 based on the $20.00 per unit of topsoil in the total column.

In response to Barron’s petition, the trial court entered a temporary restraining order. On December 18, 2003, after a hearing, the trial court recalled the temporary restraining order and dismissed Barron’s petition for injunctive relief. It is from this action by the trial court that Barron appeals.

III.

LAW AND DISCUSSION

Barron argues that the trial court committed legal error in finding that the public bid law does not prohibit the acceptance of bids that are not completed in conformity with the bid form provided by the public agency requesting bids. Barron asserts that the trial court erred in finding that CBC submitted the lowest bid where the unit price of the topsoil quoted by CBC would make CBC the highest bidder on the City’s water project.

Public contracts are governed by Title 38 of the Louisiana Revised Statutes, Public Contracts, Works & Improvements. Specifically, La.R.S. 38:2212 A(l) regulates the awarding of public works contracts and provides:

(a) All public work exceeding the contract limit as defined in this Section, including labor, materials, to be done by a public entity shall be advertised and let by contract to the lowest responsible bidder who had bid according to the contract, plans, and specifications as advertised, and no such public work shall be done except as provided in this part.
(b) The provisions and requirements of this Section, [¿those stated in the advertisement for bids, and those required on the bid form shall not be considered as informalities and shall not be waived by any public entity.

Further, La.R.S. 38:2212, which requires that public contracts be advertised and competitive bids be obtained prior to a public entity contracting for public works, “is a prohibitory law founded on public policy. It was enacted in the interest of tax paying citizens of this state, and its purpose is to protect these citizens against contracts of public officials awarded through favoritism and possibly involving exorbitant and extortionate prices.” Mickey O’Connor Gen. Contractor, Inc. v. City of Westwego, 01-825, p. 4 (La.App. 4 Cir. 11/27/01), 804 So.2d 128, 130, writ denied, 01-3391 (La.3/15/02), 811 So.2d 908 (citations omitted). In Haughton Elevator Div. v. State, 367 So.2d 1161 (La.1979), the supreme court instructed that when awarding a public works contract, the public agency is vested with the power and discretion to determine the responsibility of the bidder and to reject all bids if none [417]*417is satisfactory. The public agency cannot arbitrarily select a bid that is higher and reject bids that are lower. Mickey O’Connor Gen. Contractor, Inc., 804 So.2d 128. All that is required of the awarding public agency, after careful consideration of the bid document, is that it act in a manner that is not arbitrary. Williams v. Board of Sup’rs, 388 So.2d 438 (La.App. 2 Cir.1980).

In the present case, the City interpreted the CBC bid on the 250 cubic square yards of topsoil at $20.00 per unit for a total of $5,000.00. It chose to rely on the amount in the bid form written in numerals, which corresponded to CBC’s total cost for providing all of the topsoil, instead of the amount written in words. The primary issue presented for our review is whether this interpretation by the City is arbitrary or is an abuse of discretion.

There is no question that the CBC bid, with respect to the unit price of |Rthe topsoil, contained a discrepancy between the amount written in words and the amount written in numerals.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Command Construction Industries, L.L.C. v. City of New Orleans
126 So. 3d 716 (Louisiana Court of Appeal, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
879 So. 2d 414, 4 La.App. 3 Cir. 173, 2004 La. App. LEXIS 1773, 2004 WL 1496890, Counsel Stack Legal Research, https://law.counselstack.com/opinion/don-m-barron-contractor-inc-v-city-of-natchitoches-lactapp-2004.