Command Construction Industries, L.L.C. v. City of New Orleans

126 So. 3d 716, 2013 WL 5757865
CourtLouisiana Court of Appeal
DecidedOctober 23, 2013
DocketNos. 2013-CA-0524, 2013-CA-0525
StatusPublished
Cited by6 cases

This text of 126 So. 3d 716 (Command Construction Industries, L.L.C. v. City of New Orleans) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Command Construction Industries, L.L.C. v. City of New Orleans, 126 So. 3d 716, 2013 WL 5757865 (La. Ct. App. 2013).

Opinion

DANIEL L. DYSART, Judge.

Lin this case involving the award of a public construction contract, appellant, Command Construction Industries, L.L.C. (“Command”), seeks reversal of the trial court’s denial of its request for injunctive relief (or mandamus). For the reasons that follow, we find that the trial court improperly denied Command’s request for injunctive relief (or mandamus). At this stage, with the near completion of the contract at issue, a reversal of the trial court’s rulings is no longer possible. As Command reserved its right to seek damages at a later date “should the contract be improperly awarded,” we remand this matter for a determination of whether Command is entitled to damages.1

Intervenor, Durr Heavy Construction, L.L.C. (“Durr”), to whom the contract was awarded, appeals the trial court’s denial of attorney’s fees and costs. Because of our finding that the contract was improperly awarded to it, we do not reach the issues raised in its appeal as those issues are moot.

_|2F ACTUAL AND PROCEDURAL BACKGROUND

This matter involves the bidding on, and awarding of, a public works construction project by the City of New Orleans (“City”), known as the Harrison Avenue Streetscape Project (“the Project”). The contract for the work was ultimately awarded to Durr. Two unsuccessful bidders on' the project, Command and FHP Tectonics Corp. (“FHP”) filed separate actions seeking injunctive relief (or mandamus). Those cases were consolidated; however, FHP voluntarily dismissed its action on October 8, 2012. Accordingly, the only matter before this Court concerns Command.

Command initiated this action by filing a Petition for Temporary Restraining Order, Preliminary Injunction and Writ of Mandamus (“Petition”) on August 17, 2012, which sought to compel the City to award it the construction project for which it was allegedly the lowest bidder. The Petition also sought to enjoin the City from receiving bids and awarding or executing any [718]*718contract until the request for preliminary injunction was heard.

According to the Petition, the City opened bidding on the Project on July 10, 2012. Bids were submitted by FHP, Durr and Command. FHP was the lowest bidder; however, because of irregularities in its submission, FHP’s bid was not considered. The next lowest bid was from Command, whose base bid totaled $2,793,046.00. Durr submitted a base bid in the amount of $2,974,275.00. By letter dated July 11, 2012 (the day after Durr submitted its bid), Durr sought to Ramend its bid because of a “clerical error,” and it substituted a revised base bid (“Revised Bid”) of $2,444,850.80.

On July 27, 2012, Command issued a letter of formal protest to Durr’s bid, which maintained that Durr’s bidding procedures violated the Louisiana Public Bid Law, La. R.S. 38:2212 et seq. At that time, the contract had not been awarded. However, the City reportedly advised Command that it intended to award the contract to Durr, leading Command to file this lawsuit on August 17, 2012.

By order dated August 20, 2012, the trial court denied Command’s request for a temporary restraining order and a writ of mandamus. The court set the application for injunctive relief for an August 30, 2012 hearing, with the matter to be heard upon the verified pleadings and supporting affidavits.

Durr intervened in the action on September 5, 2012, on the basis that the contract was properly awarded to it on August 17, 2012, as it was the lowest bidder on the project. As concerns Durr’s amended bid submission, Durr’s position was that a clerical error had been made, which was obvious from the bid submission form. In addition to a declaration that the contract had been properly awarded to it, Durr sought attorney’s fee and costs under La. R.S. 38:2220.4 B(l). Durr filed a Motion for Attorney’s Fees and Costs which was heard on November 30, 2012, and denied by judgment dated January 8, 2013.

The trial court then rendered judgment on February 19, 2013, denying Command’s request for a preliminary and permanent injunction. It further denied the request for a writ of mandamus as moot. Appeals were taken by Command as |4to the denial of injunctive relief and mandamus, and by Durr as to the trial court’s denial of its request for attorney’s fees and costs. DISCUSSION

The main issue in this appeal turns on whether Durr’s Revised Bid submission complied with the provisions of the Public Bid Law found at La. R.S. 38:2212 et seq. According to the documents in the record, the City solicited bids for the Project, which contained certain instructions, including the warning that “[bjids containing any conditions, omissions, unexplained alterations, or irregularities of any kind may be rejected as informal.” The City’s bid documents further indicated that “[t]he prices should be expressed in words and figures ... [and][i]n case of discrepancy between the prices written in the bid and those given in the figures, the price in writing will be considered as the bid.” Modifications to bids were permitted before bidding was opened, as the bid documents expressly stated that:

Prior to the time set for bid opening, written and online bids may be modified and withdrawn. Modified bids must be on official forms. Changes and erasures to written bids must be explained or noted over the initials of the bidder and signed by a person legally empowered to bind the bidder.
(Emphasis added).

Implicit within these guidelines is that, once bidding was opened, modifications [719]*719were no longer permitted. Furthermore, any “changes and erasures” (i.e.“modifications”) had to be “explained or noted.” Again, though, changes and erasures to written bids were allowed only “prior to the time set for bid opening.”

|5The form used by the bidders, a Louisiana Uniform Public Work Bid Form,2 requires a declaration of each bidder that it is familiar with the project work site and a certification that it will provide “all labor, materials, tools, appliances and facilities as required to perform, in a workmanlike manner, all work and services for the construction and completion of [the Project], all in strict accordance with the Bidding Documents.” The bid form then sought a “TOTAL BASE BID” sum, which specifically stated that it was for “all work required by the Bidding Documents (including any and all unit prices designated as ‘Base Bid’ but not alternates).” (Emphasis added). Immediately after the total base bid, each bidder was to supply three alternates, each in a lump sum; one for “[cjross walk,” another for “planting in median area,” and a third for “PVC sleeves and pull boxes.”

There is no dispute that Durr’s original total base bid was mistakenly comprised of the base bid (an addition of all the unit prices) plus all three alternates. That is, Durr erroneously added the three alternates to the base bid unitRprices to arrive at its initial bid of $2,974,975.00. This sum is obviously higher than Command’s base bid of $2,793,046.00. When the three alternates are subtracted from the total base bid, however, Durr’s base bid is $2,444,850.90, as stated in its July 11, 2012 letter, which is lower than Command’s bid.

The question before this Court, therefore, is whether the City was required to consider only Durr’s initial bid of $2,974,975.00 or whether it could consider Durr’s entire bid packet (of seven pages) to determine the correct amount of its total base bid.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
126 So. 3d 716, 2013 WL 5757865, Counsel Stack Legal Research, https://law.counselstack.com/opinion/command-construction-industries-llc-v-city-of-new-orleans-lactapp-2013.