Domar Ocean Transportation, Ltd. v. M/V Andrew Martin

754 F.2d 616
Court of Appeals for the Fifth Circuit·Decided March 8, 1985·No. No. 83-3348·Published·Cited by 11 cases

Opinion

PATRICK E. HIGGINBOTHAM, Circuit Judge:

After settling the question of liability arising from a collision between two barges under tow, the litigants tried damages to a magistrate. Both sides appeal. We conclude that the plaintiff’s tug and tow were so operated as an integrated unit that the physical damage to the barge was sufficient to allow recovery for the loss of use of both under the test of State of Louisiana v. M/V TESTBANK, 752 F.2d 1019 (5th Cir.1985) (en banc): that recovery for economic injury requires physical damage to a proprietary interest. We also review the calculation of detention damages and the award of prejudgment interest, affirming in part and reversing in part.

I

Domar Ocean Transportation, Ltd., the maritime freight transportation division of Lee-Vac, Ltd., owns the tank barge DO-MAR 7001. Domar, under a long-term, open-ended “evergreen” charter beginning in 1976, had chartered Cenac Towing Co.’s tug CINDY CENAC to tow the DOMAR 7001. Domar, at its own expense, had in[618] stalled a raised pilothouse on the CINDY CENAC so that it could be used with the DOMAR 7001 to perform lightering and bunkering services.

On September 12, 1980, the DOMAR 7001 and CINDY CENAC were in the Port Arthur Canal near Mesquite Point, Texas, on their way to Tampa, Florida with a load of No. 6 oil, when the DOMAR 7001 was struck by the BELCHER 101, a barge in the tow of the ANDREW MARTIN, a tug owned by defendant Andrew Martin Marine Corporation. The DOMAR 7001 sustained damage to two of her port cargo tanks. Domar immediately dispatched another barge/tug unit, the barge DOMAR 6501 and the tug RENE J. CHERAMIE, which took on the DOMAR 7001’s cargo of oil and completed the voyage.

At the same time, Domar began contacting nearby shipyards in an attempt to locate a yard with gas-freeing facilities that were both available and large enough to handle the DOMAR 7001. After finding none in the immediate vicinity, Domar decided to have the CINDY CENAC tow the DOMAR 7001 to Avondale Shipyards in New Orleans. The DOMAR 7001 arrived at Avondale on September 15. Because another vessel was still in Avondale’s gas-freeing facility, gas-freeing on the DOMAR 7001 did not begin until September 19.

After gas-freeing was completed and the DOMAR 7001 was surveyed, Domar requested bids from area repair yards for structural repairs to the barge. On September 30, it accepted Avondale’s low bid, and Avondale performed repair operations between October 2 and October 27. On the 27th, Avondale released the DOMAR 7001 from its repair facilities back to its gas-freeing facilities. On October 31, the CINDY CENAC arrived and took the DOMAR 7001 back into service. While the DOMAR 7001 had been under repair, Domar had subchartered the CINDY CENAC, as well as using it to tow other barges.

Domar filed this admiralty action in rem against the ANDREW MARTIN. The parties stipulated that the ANDREW MARTIN would be liable for 80 per cent of Domar’s provable damages, but could not agree on the proper amount of damages. They then tried the damages issue before a magistrate, who entered written findings of fact and conclusions of law. With one modification, not relevant here, the district court approved the magistrate’s findings and entered judgment for Domar. Andrew Martin challenges one item of damages on appeal; Domar, on cross-appeal, complains that four items were too low.

II

-1-

The DOMAR 7001 was at Avondale Shipyards for 1103 hours between September 15 and October 31. The magistrate, after disallowing one 98-hour and one 96-hour block of this time (see subpart 2, infra), awarded Domar detention damages of $373 per hour, the average rate charged for the DOMAR 7001/CINDY CENAC combination. The magistrate multiplied that figure by 85.6 per cent, Domar’s average utilization rate for Class III barges, and further reduced the award by $107,977.17, the sum earned by the CINDY CENAC while the DOMAR 7001 was out of service. The resulting award for detention damages was $182,216.83.

Andrew Martin complains that much of this award represents Domar’s loss of the optimal use of the CINDY CENAC, which, deprived of its partner the DOMAR 7001, earned less than it would have otherwise. Andrew Martin argues that because the CINDY CENAC itself suffered no physical damage, Domar cannot recover for the loss of its use under Robins Dry Dock & Repair Co. v. Flint, 275 U.S. 303, 48 S.Ct. 134, 72 L.Ed.2d 290 (1927) and State of Louisiana v. M/V TESTBANK, 752 F.2d 1019 (5th Cir.1985) (en banc). Andrew Martin cites Domar’s accounting records, which attribute 35 per cent of the profits from the DOMAR 7001/CINDY CENAC combination to the barge, and 65 per cent to the tug, and asks that we allow only 35 per cent of the sum awarded below for detention damages.

[619] TESTBANK is not so restrictive. TESTBANK reaffirms this circuit’s rule, developed from Robins, that maritime tort damages for economic loss can be awarded only when the plaintiff has suffered physical damage to a proprietary interest. Do-mar, though, had a proprietary interest in the DOMAR 7001 and the CINDY CENAC as a unit. Domar was in the business of freight transportation, not of vessel rental. Accordingly, it offered its customers the use of the DOMAR 7001 and the CINDY CENAC as a unit, and not as individual vessels. Moreover, Domar had spent $350,000 to install a raised pilothouse aboard the CINDY CENAC specifically to enable the CINDY CENAC and DOMAR 7001 to be used together for lightering and bunkering. Even if the two vessels were not so uniquely designed to work with each other as to exclude other use, they were indisputably so operated that they functioned as an integrated unit.

We are persuaded that Domar had the requisite proprietary interest in the combination. The DOMAR 7001/CINDY CE-NAC unit was physically damaged through Andrew Martin’s stipulated negligence. Thus, TESTBANK is no bar to Domar’s recovery for the loss of use of the unit.

Andrew Martin also contends that in any event, as a matter of law, Domar’s damages for the loss of use of the undamaged CINDY CENAC were too tenuous and remote to be reasonably foreseeable. TESTBANK’s requirement of physical injury is a pragmatic limitation on the recovery of foreseeable economic losses. On these facts, that Domar’s damages were foreseeable is implicit in the conclusion that the test of TESTBANK is met.

-2-

Free access — add to your briefcase to read the full text and ask questions with AI

Domar Ocean Transportation, Ltd. v. M/V Andrew Martin, 754 F.2d 616 (5th Cir. 1985).

754 F.2d 616 (Domar Ocean Transportation, Ltd. v. M/V Andrew Martin) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Dow Chemical Co. v. Texaco Refining & Marketing, Inc.
887 F. Supp. 853 (E.D. Virginia, 1995)
Pillsbury Co. v. Midland Enterprises, Inc.
715 F. Supp. 738 (E.D. Louisiana, 1989)
Bosnor, S.A. de C.V. v. Tug L.A. Barrios
796 F.2d 776 (Fifth Circuit, 1986)
Elevating Boats, Inc. v. Gulf Coast Marine, Inc.
766 F.2d 195 (Fifth Circuit, 1985)
Holt Hauling & Warehousing Systems, Inc. v. M/V Ming Joy
614 F. Supp. 890 (E.D. Pennsylvania, 1985)