Dodd v. Tucker

528 So. 2d 644, 1988 WL 43143
CourtLouisiana Court of Appeal
DecidedMay 4, 1988
Docket19587-CA
StatusPublished
Cited by8 cases

This text of 528 So. 2d 644 (Dodd v. Tucker) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dodd v. Tucker, 528 So. 2d 644, 1988 WL 43143 (La. Ct. App. 1988).

Opinion

528 So.2d 644 (1988)

Earle Newton DODD & Jacque Bradford Dodd, Plaintiffs-Appellants,
v.
William York TUCKER, Jr., Defendant-Appellant.

No. 19587-CA.

Court of Appeal of Louisiana, Second Circuit.

May 4, 1988.

*645 Blanchard, Walker, O'Quin & Roberts by M. Allyn Stroud, Shreveport, for defendant-appellant.

Bodenheimer, Jones, Klotz & Simmons by James P. Bodenheimer, Shreveport, for plaintiffs-appellants.

Before HALL, FRED W. JONES, JR. and LINDSAY, JJ.

LINDSAY, Judge.

This is a quanti minoris suit arising from the purchase of a house on Cross Lake in Shreveport, Louisiana, by Earle Newton Dodd and Jacque Bradford Dodd, the plaintiffs, from Dr. William York Tucker, Jr., the defendant. The trial court denied the plaintiffs' main demand. However, it overruled the defendant's plea of prescription and rendered judgment in the plaintiffs' favor on the demand asserted in their supplemental petition, which was filed three years after the original petition. Both the plaintiffs and the defendant appealed.

*646 We have reviewed and will discuss hereafter each of the issues raised by the parties in their respective appeals. Based upon that review, we conclude that, although the initial defect of which plaintiffs complain, i.e., the leaking roof and cracked slab in the den, were not apparent defects, nevertheless, recovery for the extensive repairs made to the home must be denied due to plaintiff's failure to prove, with any reasonable degree of accuracy, the cost of the necessary repairs, as opposed to discretionary remodeling costs. Further, we conclude that although the claim for the cost of repairing the slab in the master bedroom, which was made in plaintiff's supplemental petition filed over three years after the sale, had not prescribed, plaintiffs have also failed to prove that the slab was cracked and defective at the time of their purchase of the home.

Accordingly, we affirm in part, and reverse in part, the trial court judgment.

FACTS

In the early part of 1983, Mrs. Dodd learned that the Cross Lake home of Dr. Tucker was about to be put up for sale. Dr. Tucker was making plans to move to North Carolina. She contacted Dr. Tucker, who said he wanted her to wait until after certain work was done on the house before he showed it. Some repairs were made and the exterior of the house was painted before the Dodds viewed it in May, 1983. Their first brief visit was followed by a more extensive one a week later. The second visit lasted about an hour.

The house contained two bedrooms, two bathrooms, a living room, a dining room, a den, and a kitchen. There was also a two-car garage. The property included a pier and a boathouse on the lake. After viewing the home, an agreement was reached whereby the Dodds purchased the house for the sum of $110,000. The terms of the sale provided for payment of $19,201.21 in cash, plus the assumption of a first mortgage (the principal balance of which was $90,798.79 at the time of sale).

Mrs. Dodd testified that prior to the sale she and Dr. Tucker discussed a previous leak in the dining room ceiling. Dr. Tucker assured her that this leak had been repaired. She testified that she also asked Dr. Tucker if there was any drainage problem at the front of the house near the den, and he told her there was not. She stated that she observed an obvious crack in the front porch slab. Additionally, Mrs. Dodd testified that she noticed that the floor of the den slanted "a little" and in her deposition she admitted that Dr. Tucker also told her that the den floor slanted. Plaintiffs testified that they did not observe any defect in the den ceiling.

The plaintiffs moved into the house in July, 1983. The first hard rain occurred in August, 1983, at which time the den roof leaked water into the house. The plaintiffs engaged Paul Tilton, the operator of New Day Construction Company and a close friend of more than twenty years, to look at the house and make repairs to the roof. He agreed to perform the work on a "cost, plus ten percent" basis. In the course of repairing the den roof, Mr. Tilton discovered that the slab of the den floor was cracked and the walls were improperly constructed. He also discovered other extensive defects in the house which, in his view, "necessitated" repairs. He testified that the den roof was the initial cause of the repairs, and then "one thing led to another."

Mr. Tilton placed a new gabled roof over the entire house. He also installed a cathedral ceiling in the den. Other "defects" discovered by Mr. Tilton included: (1) a rotted kitchen floor attributable to the rusted and leaking dishwasher and hot water tank; (2) sagging piers underneath the house which made it difficult to raise and lower the windows in the guest bedroom; (3) old termite damage under the dining room windows; and (4) rotted porch beams and ceiling joists.

In the course of his work, which consisted of practically rebuilding the house and making the "necessary" repairs referred to above, Mr. Tilton also rebuilt the lower kitchen cabinets, and then painted and refinished all of the kitchen doors and top cabinets. New hardware was installed. *647 He also painted the living room, the den, the guest bedroom and the hallway. He installed new carpeting in several areas, and constructed new steps leading from the entrance to the den. The arrangement of the walls between the den and the dining area was modified. The front door of the home was placed in a new location. Mr. Tilton said that the sagging of the building prevented the windows in the guest bedroom from closing normally. When he took the windows out, he also repositioned them to a level more pleasing to Mrs. Dodd. On the extensive, Mr. Tilton placed stone siding on the front, back, and one side of the house. He also poured a new concrete slab for the front porch, and set new posts for the front porch. A concrete patio was built at the rear of the home. The chimney was reflashed and covered with stone.

The plaintiffs filed suit on June 7, 1984, seeking $46,267.25, the amount spent on repairs, plus costs and reasonable attorney fees. The defendant answered, alleging that any defects in the house were apparent, or, alternatively, the defects did not exist on the day of the sale and did not appear within three days of the sale. The defendant also pled alternatively that the defects did not exist on the day of the sale and were caused later by the plaintiff's lack of care. The defendant further claimed that the plaintiffs purchased the house "as is" and the sales price was reduced to reflect the condition of the house.

On July 16, 1987, the date of trial, the plaintiffs filed a supplemental petition alleging that in December, 1986, they discovered a crack in the slab of the master bedroom. They claimed additional damages of $4,054, the amount required to repair the slab and stabilize the soil. To this claim the defendant pled the prescription of one year.

Following the trial, the trial court rejected the plaintiffs' principal demand, but granted judgment in their favor on the demand contained in their supplemental petition. The trial judge did not assign written reasons for judgment. However, in an oral colloquy with counsel at the conclusion of the trial, he indicated that the defect in the roof was apparent, and, even if it was not apparent, the testimony concerning the necessity for the extensive repairs and the cost thereof was not sufficient for him to exercise his discretion in awarding damages.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bailey v. DeLaCruz
143 So. 3d 1220 (Louisiana Court of Appeal, 2014)
Fisher v. Batista
968 So. 2d 337 (Louisiana Court of Appeal, 2007)
Kent v. Cobb
811 So. 2d 1206 (Louisiana Court of Appeal, 2002)
Industrial Roofing v. Jc Dellinger Mem.
751 So. 2d 928 (Louisiana Court of Appeal, 1999)
Long v. Bruns
727 So. 2d 664 (Louisiana Court of Appeal, 1999)
Dixie Roofing v. Allen Parish Sch. Bd.
690 So. 2d 49 (Louisiana Court of Appeal, 1996)
Sydnes v. Harwell
651 So. 2d 419 (Louisiana Court of Appeal, 1995)
Creger v. Robertson
542 So. 2d 1090 (Louisiana Court of Appeal, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
528 So. 2d 644, 1988 WL 43143, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dodd-v-tucker-lactapp-1988.