Doberstein v. G-P Industries, Inc.

Court of Chancery of Delaware·Decided October 30, 2015·No. CA 9995-VCP·Published

Opinion

IN THE COURT OF CHANCERY OF THE STATE OF DELAWARE

ANNE L. DOBERSTEIN, )

)

Plaintiff, )

)

v. ) C.A. No. 9995-VCP )

G-P INDUSTRIES, INC., a Delaware corporation, ) DAVID GREENPLATE, SR., )

)

Defendants. )

MEMORANDUM OPINION

Date Submitted: July 10, 2015 Date Decided: October 30, 2015

Donald L. Logan, Esq., LOGAN & PETRONE, LLC, Wilmington, Delaware; Attorneys for Plaintiff.

Patrick McGrory, Esq., TIGHE & COTTRELL, P.A., Wilmington, Delaware; Attorneys for Defendants.

PARSONS, Vice Chancellor.

This is primarily a breach of contract action seeking damages for failure to perform under a residential renovation agreement. The plaintiff hired the defendants to substantially remodel her recently purchased residence, but the defendants suffered significant financial trouble and abandoned the project before completion. The plaintiff advances a number of theories of recovery, including fraud, intentional and negligent misrepresentation, breach of contract, and unjust enrichment. The defendants moved to dismiss three of the complaint‟s counts under Court of Chancery Rule 12(b)(6) for failure to state a claim and the remaining three counts along with the complaint entirely under Rule 12(b)(1) for lack of subject matter jurisdiction. For the reasons set forth below, I conclude that the plaintiff has not stated a claim upon which relief can be granted as to the first three counts and that this Court lacks subject matter jurisdiction over the remaining three counts. I therefore grant the defendants‟ motion and dismiss the complaint.

I. BACKGROUND1

A. Parties

Plaintiff, Anne L. Doberstein, is an individual who primarily works and resides in Switzerland. Doberstein also owns a residence located at 103 East Pembrey Drive in Wilmington, Delaware.

1 The facts recited herein are drawn from the allegations of the plaintiff‟s Verified Complaint (the “Complaint”). Those allegations and facts drawn from documents integral to the Complaint are presumed true for purposes of Defendants‟ motion to dismiss.

Defendant G-P Industries, Inc. (“G-P”) is a Delaware corporation that provides general contracting and altering and remodeling services in Wilmington, Delaware. Defendant David Greenplate, Sr. is the president and registered agent of G-P. G-P and Greenplate are referred to, collectively, as “Defendants.”

B. Facts

1. Doberstein hires G-P to renovate her house In October 2012, Doberstein entered into a contract with G-P (the “Agreement”), under which G-P agreed to serve as the general contractor on a significant home renovation project at Doberstein‟s Wilmington residence (the “Project”). On October 17, 2012, Greenplate, on behalf of G-P, prepared the Project‟s estimates and the Agreement. He estimated that the Project would cost Doberstein a total of $494,498.2 Under the terms of the Agreement, Doberstein was to provide advance deposits for subcontractors performing work on the basement as well as for the building permit. Otherwise, the Agreement did not contemplate Doberstein paying for any renovations before they were completed or paying subcontractors directly. Instead, G-P was to pay all subcontractors and to seek reimbursement through its invoices to Doberstein. In addition, G-P agreed to invoice Doberstein on the first of each month—with the exception of major material purchases, which were to be invoiced immediately—and to provide a three percent

2 Although they agree that the estimated $494,498 was the initial amount of the Agreement, the parties dispute the final amount covered by the Agreement. Based on the allegations in the Complaint and taking into account the additional $47,662 in supplemental estimates and change orders, I assume for purposes of this motion that the total amount of the Agreement was $542,159. See Compl. ¶ 6.

discount on labor charges when Doberstein paid in cash. G-P began work on the Project in November 2012. Defendants repeatedly assured Doberstein that the Project would be completed by the end of 2013.

Doberstein, who lives and works in Switzerland, began making monthly payments while abroad. On March 14, 2013, G-P sent Doberstein a $1,520 invoice for cabinet grade plywood. G-P had not yet begun construction on the portions of the Project that required the plywood, but purchased the plywood early because it was concerned that the cost would increase. Doberstein paid G-P to purchase the plywood in advance and store it until needed. Further, in that March 14 invoice and in an April 10, 2013 invoice, G-P offered Doberstein a three percent reduction on labor if she paid in cash directly to Greenplate. Doberstein paid a total amount of $33,950 in cash directly to Greenplate based on those two invoices.

2. Doberstein discovers issues with the Project’s progress In May 2013, Doberstein traveled from Switzerland to visit the Project site. Upon arrival, she discovered that little work had been completed, despite the fact that she had paid Defendants $127,820.10. After Doberstein returned to Switzerland, her interior designer, Matthew Pearson, spoke with Greenplate about the lack of progress. Greenplate explained that the Project had been delayed due to a lack of manpower, delays on other projects, and shuffling employees. He assured Pearson, however, that the Project still would be completed by the end of 2013.

On or about July 25 and 27, 2013, a neighbor, who also served as the president of the neighborhood homeowners‟ association, contacted Doberstein regarding the unkempt

state of her property. The neighbor informed Doberstein that little progress had been made on the Project in the past several months, even after the meetings Doberstein and Pearson had with Greenplate. Doberstein contacted Greenplate, demanding action. On August 9, 2013, Greenplate sent a letter to Doberstein‟s neighbors, explaining that the Project had been delayed due to weather and manpower issues and stating that “we did stop working there in early May . . . .”3 Despite halting work on the Project, G-P had sent Doberstein invoices from May through August for a total amount of $49,500.

Later in August 2013, Pearson began meeting weekly at the Project site with Greenplate and insisted that G-P prepare a schedule of the work to be done. During those weekly meetings, Pearson observed three to six workers on the Project at any given time. Doberstein and Pearson later discovered that the Project was unmanned most of the week and that the number of workers was increased on days when Greenplate would meet with one of them.

3. The Project’s completion date gets delayed In September 2013, Doberstein learned that, contrary to her explicit instructions, Pearson had not been copied on the invoices sent to her by G-P and Greenplate. Doberstein reiterated her request for Pearson to be copied on all invoices. Later that month, during one of their weekly meetings, Greenplate revealed to Pearson that the Project would not be completed until the end of January 2014. Doberstein did not respond well to this news. To ameliorate her displeasure, Greenplate told Doberstein that

3 Compl. ¶ 12.

the Project would be substantially complete by the end of 2013, such that Doberstein could move in her things. Throughout the rest of 2013, G-P‟s invoicing accelerated in amount and frequency. By the end of December 2013, Doberstein had paid a total of $314,434.68 to G-P and Greenplate since the Project‟s inception, representing fifty-eight percent of the total $542,159 due under the Agreement, though the Project was nowhere near complete.

Free access — add to your briefcase to read the full text and ask questions with AI

Doberstein v. G-P Industries, Inc., (Del. Ct. App. 2015).

Doberstein v. G-P Industries, Inc. (Doberstein v. G-P Industries, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Candlewood Timber Group, LLC v. Pan American Energy, LLC
859 A.2d 989 (Supreme Court of Delaware, 2004)
Airborne Health, Inc. v. Squid Soap, LP
984 A.2d 126 (Court of Chancery of Delaware, 2009)
Getty Refining & Marketing Co. v. Park Oil, Inc.
385 A.2d 147 (Court of Chancery of Delaware, 1978)
Clinton v. Enterprise Rent-A-Car Co.
977 A.2d 892 (Supreme Court of Delaware, 2009)
NAMA Holdings, LLC v. Related World Market Center, LLC
922 A.2d 417 (Court of Chancery of Delaware, 2007)
Wood v. Coastal States Gas Corp.
401 A.2d 932 (Supreme Court of Delaware, 1979)
International Business MacHines Corp. v. Comdisco, Inc.
602 A.2d 74 (Court of Chancery of Delaware, 1991)
Crescent/Mach I Partners, L.P. v. Turner
846 A.2d 963 (Court of Chancery of Delaware, 2000)
Savor, Inc. v. FMR Corp.
812 A.2d 894 (Supreme Court of Delaware, 2002)
Kuroda v. SPJS Holdings, L.L.C.
971 A.2d 872 (Court of Chancery of Delaware, 2009)
Maloney-Refaie v. Bridge at School, Inc.
958 A.2d 871 (Court of Chancery of Delaware, 2008)
Diebold Computer Leasing, Inc. v. Commercial Credit Corp.
267 A.2d 586 (Supreme Court of Delaware, 1970)
Crosse v. BCBSD, INC.
836 A.2d 492 (Supreme Court of Delaware, 2003)
Price v. E.I. DuPont De Nemours & Co.
26 A.3d 162 (Supreme Court of Delaware, 2011)
AFSCME Locals 1102 & 320 v. City of Wilmington
858 A.2d 962 (Court of Chancery of Delaware, 2004)
Allen v. Encore Energy Partners, L.P.
72 A.3d 93 (Supreme Court of Delaware, 2013)