Divis v. Clarklift of Nebraska, Inc.

590 N.W.2d 696, 256 Neb. 384, 1999 Neb. LEXIS 52
CourtNebraska Supreme Court
DecidedMarch 12, 1999
DocketS-97-905
StatusPublished
Cited by36 cases

This text of 590 N.W.2d 696 (Divis v. Clarklift of Nebraska, Inc.) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Divis v. Clarklift of Nebraska, Inc., 590 N.W.2d 696, 256 Neb. 384, 1999 Neb. LEXIS 52 (Neb. 1999).

Opinion

Hendry, C.J.

I. INTRODUCTION

This is a product liability action brought by appellant, Jay Arthur Divis, against appellees, Clarklift of Nebraska, Inc. (Clarklift), Clark Material Handling Company (Clark), Wahoo Concrete Products, Co. (Wahoo Concrete), and Right Line Equipment, Inc., for the injuries he sustained in a forklift accident.

The forklift in question can best be described as follows: The forklift contains two vertically parallel members (masts) that raise up and down inside the framework of the forklift. Two other horizontally parallel members (carriages) are welded to the masts. The forks, which are L-shaped, are bolted to the top carriage.

*386 [[Image here]]

The evidence indicates weld failure occurred at the point where the top carriage is welded to the masts.

II. BACKGROUND

In 1979, Clark designed and manufactured the forklift in question. On January 19, Clark shipped the forklift to Christy Equipment Company, Clarklift’s predecessor. In July, Clarklift sold the forklift to Georgia-Pacific Corporation (Georgia-Pacific). Approximately 12 years later, in 1992, Wahoo Concrete sought to purchase a used forklift from Clarklift. In July, Clarklift repurchased the forklift from Georgia-Pacific for resale to Wahoo Concrete.

Prior to delivering the forklift to Wahoo Concrete, Clarklift installed an attachment known as a side-shifter at the request of Wahoo Concrete. A side-shifter is an accessory that bolts onto the carriage of the forklift and allows the forks to move vertically and horizontally. In this respect, Clark’s procedures require that any installation of attachments to Clark forklifts be authorized and approved by Clark. Clarklift therefore requested authorization to install the side-shifter, which Clark provided.

Clarklift also refurbished the forklift. Clarklift contributed 3072 hours to refurbishing the forklift and spent $4,700 in parts and $1,825 in labor. The refurbishing consisted of such repairs *387 as removing the cab, sanding and painting, rebuilding the steering axle, installing the side-shifter, installing a new gas engine, adjusting the lift chains, replacing the upright bushings, replacing the side doors, repairing the shift linkage, installing new tires, repairing the sheet metal, and installing a new seat, as well as various other repairs which are indiscernible from the record.

At the time of sale, Clarklift issued a “Standard Industrial” warranty to Wahoo Concrete. Under the warranty, Clarklift warranted the drive train only. The drive train is defined in the warranty as the engine, transmission, and drive axle, excluding brakes. The warranty also excluded leaks, adjustments, and minor deficiencies.

Upon receipt of the forklift, Wahoo Concrete intended to use the forklift in the course of its business, manufacturing floorings for hog confinement facilities. The floorings are 10- by 10-foot concrete slabs weighing 1,800 pounds. The concrete slabs are manufactured by pouring concrete into metal forms. Once the concrete has set, the concrete must then be removed from the form. Wahoo Concrete accomplished this by operating the forklift with a steel extension (jib-boom) and chains.

The jib-boom in question is approximately 8 inches wide by 5V4 inches high by V4 inch thick, and 9 feet long. The jib-boom contains two 3/4-inch-diameter hooks welded to the bottom side of the attachment. One hook is positioned on the end of the jib-boom, and the other hook is positioned approximately 24 inches from the end. To use the jib-boom, the forks are moved to a position directly adjacent to one another. The jib-boom is attached to the forks, which are then positioned over the concrete slab and the form. A metal chain, which is attached to one of the hooks on the jib-boom, is then attached to the concrete slab, whereupon the forks are raised to lift the concrete slab out of the form.

On June 1, 1994, Divis was employed at Wahoo Concrete as a concrete finisher. One of Divis’ responsibilities was to assist in manufacturing the concrete slabs, which included removing the slabs from the forms once the concrete was set. On the day of the accident, several Wahoo Concrete employees, including Divis, were in the process of removing a slab from a form when the slab became somewhat unbalanced. Attempting to act as a *388 counterbalance, Divis sat on the concrete slab while the slab was being raised out of the form. Divis’ position, when sitting on the concrete slab, placed him under the masts and carriages of the forklift. While the slab was being raised out of the form, the welds on the top carriage and the masts failed. The carriage unit snapped, falling down on top of Divis, striking him on the head, pinching him between the slab and the jib-boom, and ultimately causing severe injuries.

On August 24, 1995, Divis filed a second amended petition against appellees based on negligence, strict liability, and breach of warranty. On January 16, 1997, Clark and Clarklift filed motions for summary judgment, alleging that Divis’ claims were barred by the product liability statute of repose, Neb. Rev. Stat. § 25-224(2) (Reissue 1995). On March 6, 1997, a summary judgment hearing was held where evidence was adduced which included, inter alia, the opinions of several experts regarding the cause of the accident. The experts agreed that the accident was caused by a weld failure that occurred between the top carriage and the masts, that the weld failure was caused by a lack of fusion between the carriage and the masts, and that the lack of fusion occurred at the time of manufacture in 1979. Based on this evidence, the district court ruled in favor of Clark and Clarklift, finding, “The evidence presented is uncontroverted that this failure resulted from the original manufacture and not from acts of ‘Clarklift.’ ”

III. ASSIGNMENTS OF ERROR

Rephrased and reordered, Divis claims that the district court erroneously granted summary judgment because (1) the statute of repose began anew when Clarklift reconditioned and refurbished the forklift, which Clark approved and authorized; (2) the statute of repose does not apply to the allegations of negligence Divis asserted against Clarklift; and (3) a factual issue exists regarding whether the “Standard Industrial” warranty issued by Clarklift falls with the exception in § 25-224(2).

IV. STANDARD OF REVIEW

In reviewing an order granting a motion for summary judgment, an appellate court views the evidence in a light most favorable to the party opposing the motion and gives that party *389 the benefit of all reasonable inferences deducible from the evidence. Zimmerman v. FirsTier Bank, 255 Neb. 410, 585 N.W.2d 445 (1998).

When reviewing a question of law, an appellate court reaches a conclusion independent of the lower court’s ruling. Hoiengs v. County of Adams, 254 Neb.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Everhart v. Merrick Mfg. II, L.L.C.
2022 Ohio 4626 (Ohio Court of Appeals, 2022)
Ag Valley Co-op v. Servinsky Engr.
974 N.W.2d 324 (Nebraska Supreme Court, 2022)
Jeffery Oppedahl v. Mobile Drill International Inc
899 F.3d 505 (Eighth Circuit, 2018)
In re Conagra Foods, Inc.
90 F. Supp. 3d 919 (C.D. California, 2015)
Malen v. MTD Products, Inc.
628 F.3d 296 (Seventh Circuit, 2010)
Detmer v. Bixler
642 N.W.2d 170 (Nebraska Court of Appeals, 2002)
Gerlach v. State
623 N.W.2d 1 (Nebraska Court of Appeals, 2000)
Fidler v. Koster
603 N.W.2d 165 (Nebraska Court of Appeals, 1999)
State v. White
601 N.W.2d 731 (Nebraska Supreme Court, 1999)
Fackler v. Genetzky
595 N.W.2d 884 (Nebraska Supreme Court, 1999)
Holste v. Burlington Northern Railroad
592 N.W.2d 894 (Nebraska Supreme Court, 1999)

Cite This Page — Counsel Stack

Bluebook (online)
590 N.W.2d 696, 256 Neb. 384, 1999 Neb. LEXIS 52, Counsel Stack Legal Research, https://law.counselstack.com/opinion/divis-v-clarklift-of-nebraska-inc-neb-1999.