Divan Builders v. Planning Bd. Tp. of Wayne

334 A.2d 30, 66 N.J. 582, 1975 N.J. LEXIS 240
CourtSupreme Court of New Jersey
DecidedMarch 13, 1975
StatusPublished
Cited by38 cases

This text of 334 A.2d 30 (Divan Builders v. Planning Bd. Tp. of Wayne) is published on Counsel Stack Legal Research, covering Supreme Court of New Jersey primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Divan Builders v. Planning Bd. Tp. of Wayne, 334 A.2d 30, 66 N.J. 582, 1975 N.J. LEXIS 240 (N.J. 1975).

Opinion

The opinion of the Court was delivered by

Pashman, J.

The principal question posed by this appeal is whether the Municipal Planning Act, N. J. 8. A. 40:55-1.1 et seq. authorizes a municipality to enact an ordinance *587 which empowers the governing body or the Planning Board, if it has been authorized by ordinance to act on applications for subdivision approval “in lieu of the governing body,” N. J. S. A. 40:55~1.14 to condition subdivision approval upon a developer’s installation of ofE-site improvements. The trial court granted summary judgment for plaintiff, Divan Builders, Inc. v. Wayne Planning Board, 122 N. J. Super. 508 (Law Div. 1973), and the Appellate Division affirmed, Divan Builders, Inc. v. Wayne Planning Board, 127 N. J. Super. 368 (App. Div. 1974). 1 We granted defendants’ petition for certification, 65 N. J. 283 (1974).

The facts were largely stipulated by the parties. Plaintiff Divan Builders, Inc. initially applied to the Wayne Township Planning Board for subdivision approval in late 1969'. Divan’s proposal contemplated the construction of 31 single family dwellings in a residential zone of the Township. Because a substantial portion of the building site was covered by a pond, the developer’s plan called for its draining and the construction of a conduit which would pipe the water from its upstream source through the development and into an existing drainage facility on the downstream border of the site.

Despite some preliminary concern over the drainage problem associated with the proposed subdivision, the Township governing body granted preliminary subdivision approval on October 7, 1970 on the recommendation of the Planning Board. In January 1972 final subdivision approval was granted for five of the lots, and in May 1972, plaintiff applied for final approval of the remaining 26 lots.

On June 21, 1972, the Wayne governing body amended its subdivision ordinance by adopting Ordinance No. 69-1972. The ordinance establishes procedures to be followed when off- *588 site improvements are deemed necessary to service a subdivision. The ordinance provides in part that:

Prior to the granting of final approval of all subdivisions hereafter submitted to the Planning Board, and prior to the issuance of any building permits for any land use, including land uses which require site plan approval . . . and any residence or other use of property on an unimproved street or where any off-site improvements have not then been installed, the subdivider or other named type of applicant . . . shall have installed, posted a performance bond, or made cash payments, in the manner provided in Section 5 below, with respect to the immediate or ultimate installation of any required off-site improvements. [Ordinance No. 69-1972, § 14-26(a)].

Off-site improvements include the installation of new, or the extension or modification of existing improvements made necessary in whole or in part by the subdivision which will be benefited by the improvement. 2 The ordinanee also provides that the cost of off-site improvements shall be allocated between the applicant, other property owners, or any one or more of them. The cost allocation is based upon such factors as the benefit conferred upon the subdivision, the cost of the improvement, and the extent to which the improvement is necessary to protect neighboring property under the proposed plan.

*589 On June 26, 1972, the Planning Board recommended final approval of plaintiff’s remaining 26 lots subject to certain conditions, including the following:

[T]hat the applicant contribute to the Township of Wayne a sum of $20,000 as their share of improving the downstream conditions of the stream which carries the drainage from the subdivision.

In July 1972 plaintiff received final approval for the remaining portion of its subdivision on the condition that it pay the Township $20,000. This' sum represented approximately 8% of the estimated $250,000 cost of the off-site improvement deemed necessary to serve the entire drainage basin. Only one other developer, however, was required to contribute a similar sum pursuant to the ordinance. 3

The parties stipulated that: (1) the drainage system would accommodate the increased runoff from plaintiff’s property as well as from neighboring properties and tracts located downstream in the drainage basin 4 ; (2) the system would protect previously developed properties from floods which would otherwise result from the development of plaintiff’s subdivision and other unimproved property as well 5 ; (3) it *590 was the established policy of the municipality to impose a required contribution from the owner of each of the undeveloped tracts in the drainage basin pursuant to Ordinance No. 69 for his fair share of the improvement when the owners apply for subdivision approval, site plan approval, or a building permit.

On September 6, 1972, the Wayne governing body passed Ordinance No. 108-1972, a bond ordinance authorizing the construction of the drainage basin improvement project as a general improvement — no part of the cost of which “has been or shall be specially assessed on property specially benefited thereby” — and appropriating $250,000 for that purpose. To meet that appropriation, bonds totaling $238,050 were to be issued, the ordinance reciting that the remaining $11,950 (“down payment”) was available from contributed funds and that it was estimated that a total of $40,000 of contributed funds would be received.

Shortly after the enactment of the bond ordinance, plaintiff instituted the present action to recover the $20,000 paid to the Township. On cross motions for summary judgment, the trial court upheld the right of municipalities to require protective drainage improvements to be constructed either on-site or off-site as a condition precedent to subdivision approval when the development will be fully integrated into the community at large. Divan, supra, 122 N. J. Super, at 515. The court nonetheless entered judgment for plaintiff because in its view, while the Township could compel the developer to pay for improvements made necessary to serve the subdivided plots, the developer could not be required to pay for improvements made necessary to accommodate adjoining areas. 122 N. J. Super, at 517-18. The court also *591 considered the effect of the bond ordinance on the dispute and concluded that the adoption of the improvement ordinance enhanced plaintiff’s right to recover since the balance of the general drainage improvement was to be paid from ad valorem

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Blackridge Realty, Inc. v. the City of Long Branch
New Jersey Superior Court App Division, 2025
Henry v. New Jersey Department of Human Services
9 A.3d 882 (Supreme Court of New Jersey, 2010)
Toll Bros., Inc. v. BD. OF CHOSEN FREEHOLDERS, CTY. OF BURLINGTON
944 A.2d 1 (Supreme Court of New Jersey, 2008)
D.L. Real Estate Holdings, L.L.C. v. Point Pleasant Beach Planning Board
820 A.2d 1220 (Supreme Court of New Jersey, 2003)
DL Real Estate Holdings, LLC v. Planning Board
820 A.2d 1220 (Supreme Court of New Jersey, 2003)
Builders League of South Jersey, Inc. v. BURLINGTON CTY. PLANNING BD.
801 A.2d 380 (New Jersey Superior Court App Division, 2002)
City of Annapolis v. Waterman
745 A.2d 1000 (Court of Appeals of Maryland, 2000)
F & W ASSOCIATES v. County of Somerset
648 A.2d 482 (New Jersey Superior Court App Division, 1994)
Dolan v. City of Tigard
512 U.S. 374 (Supreme Court, 1994)
Goldstein v. Planning Board
639 A.2d 1161 (New Jersey Superior Court App Division, 1993)
Tennis Club Assoc. v. Planning Bd.
621 A.2d 79 (New Jersey Superior Court App Division, 1993)
Vrabel v. Mayor and Council
601 A.2d 229 (New Jersey Superior Court App Division, 1992)
Cameron & Cameron, Inc. v. PLANNING BD. OF TOWNSHIP OF WARREN
593 A.2d 1250 (New Jersey Superior Court App Division, 1991)
Squires Gate, Inc. v. County of Monmouth
588 A.2d 824 (New Jersey Superior Court App Division, 1991)
NJ Shore Builders Ass'n v. MARLBORO TP.
591 A.2d 950 (New Jersey Superior Court App Division, 1991)
Holmdel Builders Ass'n v. Township of Holmdel
583 A.2d 277 (Supreme Court of New Jersey, 1990)
Holmdel Builders v. Holmdel Tp.
556 A.2d 1236 (New Jersey Superior Court App Division, 1989)
Kode Harbor Dev. Assoc. v. Atlantic
553 A.2d 858 (New Jersey Superior Court App Division, 1989)

Cite This Page — Counsel Stack

Bluebook (online)
334 A.2d 30, 66 N.J. 582, 1975 N.J. LEXIS 240, Counsel Stack Legal Research, https://law.counselstack.com/opinion/divan-builders-v-planning-bd-tp-of-wayne-nj-1975.