District of Columbia v. Metropolitan Railroad

8 App. D.C. 322, 1896 U.S. App. LEXIS 3174
CourtDistrict of Columbia Court of Appeals
DecidedMarch 24, 1896
DocketNo. 442
StatusPublished
Cited by1 cases

This text of 8 App. D.C. 322 (District of Columbia v. Metropolitan Railroad) is published on Counsel Stack Legal Research, covering District of Columbia Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
District of Columbia v. Metropolitan Railroad, 8 App. D.C. 322, 1896 U.S. App. LEXIS 3174 (D.C. 1896).

Opinions

Mr. Justice Morkis

delivered the opinion of the Court:

1. By concession of counsel for the District of Columbia in open court in the hearing before us, it now appears that the claim of the District to the items in schedule D, for work in Georgetown amounting to $15,292.63, is without foundation; and that this sum in any event must be deducted •• from the demand of the District, which is thus reduced to the sum of $132,214.42. The work done on the streets of Georgetown specified, in this schedule had been done before, the railroad company had begun to occupy these streets in any manner; and when it did occupy them, it repaired the streets at its own expense, and continued to keep them thereafter in good order and .condition. The claim of the District in this instance'was wholly erroneous and is so shown by the record; and the attorney for the District could ■ scarcely do otherwise than abandon these items.

2. On the other hand, the item of $1,914.52, in schedule.. Ba, for work done on Boundary street, is scarcely open to [344]*344discussion. That work was done in the summer of 1875, after the railroad company bad fully occupied the street and was running its 'cars thereon ; and the material used for paving, which was Belgian block, was well suited for the purposes of the company, and a durable pavement. And this sum of $1,914.52 must, therefore, be adjudged in favor of the District of Columbia in any event.

3. With reference to the items contained in schedules B and C, both of which stand upon the same basis, it appears that while the railroad company under its charter had the right of constructing its branch lines of road upon the streets therein mentioned, it had not in any manner exercised that right when the Board of Public Works entered upon those streets and undertook to lay the pavements with part of the cost of which it is now sought to charge the railroad company. The company had still about two years in one case and nearly three years in the other within which to construct these lines ; and it ^alleged, and it may be assumed to have been the fact, that its resources at the time were unequal to the expenditure that would be entailed by the work of construction. In this condition of things the president of the railroad company addressed, on October 26, 1871, the following communication to the Board of Public Works :

“ Washington, October 26, 1871.
“ To the Hon. Board of Public Works of the District of Columbia.
“ Gentlemen : Your board having recently ordered the paving of certain streets through which Congress had given this company permission to lay rails whereon to run street cars, we would respectfully ask the privilege to lay down the sleepers and crossties as the paving progresses, thereby preserving the streets and avenues from being cut up at a future day in the execution of this work. It is the intention of this company to extend the Metropolitan Railroad westward from its present terminus to Georgetown and eastward to Uniontown, and also to lay tracks on Ninth street [345]*345to Pennsylvania avenne, to the Boundary, and on 4^ street from the city, hall to the arsenal gate as soon as the property holders along these lines subscribe to additional stock, which, it is hoped, will be done shortly. The company are willing, with the permission of the board, to go on at once and lay the timbers for these lines, fully preparing them for the rails to be put in at some future time. To keep a well-laid pavement in good order it is desirable to avoid all excavation, particularly in the center of the street. This consideration doubtless influenced your board in its wise precaution of ordering all water, gas, and service pipes to be laid prior to the paving. ■ The, necessity is more apparent, where railroad privileges have been granted, to have the timbers laid as the paving progresses, which will not only be a benefit to the city, but add to the comfort of those residing upon or passing over the street. We are willing to anticipate the putting down of the sleepers and crossties of our contemplated extensions, provided the paving be done by your own contractor without charge • against us-, and should be pleased if the suggestion herein submitted should meet the favor of your board.
“ Very respectfully, your obedient servant,
“ J. W. Thompson, President

The answer of the Board of Public Works to this communication would seem to have been the passage by it on the same day (October 26, 1871,) of the following resolution :

“ Resolved, That when this board shall have authorized the paving of a roadway of any street or avenue along which any horse railroad company is empowered to lay railroad tracks, such company shall have the privilege of laying, at its own expense, the sleepers, crossties, and other woodwork of such tracks in advance of paving, so as to prepare the track for the rails and thus prevent the necessity of disturbing the pavement for this purpose at a future time; said work to be done under the direction of the board.”

[346]*346In pursuance of this resolution, and of the understanding created thereby, the railroad company at its own expense laid the'sleepers and crossties on Ninth street and East. Capitol street, while the pavements were being laid by the Board of Public Works ; but it did not lay its rails or begin the running of its cars until some time after the laying of the pavements had been completed. How long this was does not appear from the record before us.

Substantially the same conditions prevailed and the same action was taken with regard to Seventeenth street, between H and I streets, and Connecticut avenue, which are the subject of schedule C.

The liability, therefore, of the railroad company to the District of Columbia, in regard to the items contained in these two schedules B and C, depends upon the determination of the question, whether by laying down its sleepers and crossties under this resolution adopted by the Board of Public Works, the railroad company immediately thereupon so occupied the streets and avenues upon which it had been authorized to construct its road, as to become liable to the District of Columbia for the cost of paving then done by the board on the portion of the streets and avenues thereafter used by the railroad company. This question we musL answer in the negative.

Evidently it was not the understanding or intention of the Board of Public Works at that time to order the paving of any portion of these streets or avenues to be done by the railroad company. Nor was it the intention to charge the railroad company with any portion of the cost; for no charge. therefor was ever made by the board against the company. And so far as the understanding of all the parties at the time can avail in the consideration of the question, it is beyond all doubt that the railroad company was not supposed to have incurred, by the action which it took, any liability whatever on account of the paving.

The arrangement suggested by the letter of the. president of the railroad company, to which evidently the resolution [347]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
8 App. D.C. 322, 1896 U.S. App. LEXIS 3174, Counsel Stack Legal Research, https://law.counselstack.com/opinion/district-of-columbia-v-metropolitan-railroad-dc-1896.