Dinwiddie Construction Co. v. Campbell

406 P.2d 294, 81 Nev. 469, 1965 Nev. LEXIS 257
CourtNevada Supreme Court
DecidedOctober 4, 1965
Docket4891
StatusPublished
Cited by5 cases

This text of 406 P.2d 294 (Dinwiddie Construction Co. v. Campbell) is published on Counsel Stack Legal Research, covering Nevada Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dinwiddie Construction Co. v. Campbell, 406 P.2d 294, 81 Nev. 469, 1965 Nev. LEXIS 257 (Neb. 1965).

Opinion

*470 OPINION

By the Court,

Badt, J.:

This appeal presents the question of the correct measure of damages for an innocent or non-willful taking of diatomaceous earth from a mineral claim of the rightful owner. It also involves a placing of the burden of proof as to the value of said ore and the deductible expenditures of defendant which may be considered in mitigation of damages.

Finally, we are concerned with two procedural questions: First, the admissibility for review of evidence first offered after judgment. Appellant introduced this evidence accompanying a request for an order vacating judgment. The order was denied and no appeal was taken. Nevertheless, appellant now seeks consideration of that accompanying evidence in his appeal here from the judgment.

Secondly, we consider the standing of a defendant to protest the alleged mis-naming of a co-defendant. This co-defendant is not appealing, nor is there any question as to the liability of either party. Appellant simply is concerned that the “mis-naming” will affect appellant’s rights under a “save harmless” clause in an asserted contract with such other party not named as a defendant. No cross-claim is involved.

*471 We proceed to the disposition of all of these questions in the inverse order in which they are named, irrespective of the fact the disposition of one or more of the questions may dispose of the entire appeal.

The points raised will be clearer from a brief recital of the facts and a reference to the pleadings.

Respondents sued Dinwiddie Construction Company, a corporation, and George E. Miller Construction Co., Inc., a corporation, thereafter and hereinafter referred to as Miller, alleging the removal by defendant Miller, which was alleged to be at the time a sub-contractor of defendant Dinwiddie, for the purpose of completing a contract of the said Dinwiddie, and with the knowledge and consent of said Dinwiddie, and under its orders and direction. Defendants filed a joint answer, with a general denial and the following affirmative defense: “Defendants (emphasis added) during the years 1959 and 1960 did remove certain diatomaceous earth for use on target Bravo 16, pursuant to a contract with the United States Navy.” Trial was had upon the issues thus raised and the court made findings of respondents’ ownership of their mining claims in the Wy2 of Section 11, T. 17 N., R. 27 E.; that certain lands in the Ey2 of Section 11 were thereafter withdrawn from entry, for use of the Navy as an aerial bombing range; that respondents’ claims in the W]/2 of Section 11 were never withdrawn from entry and their ownership was maintained through the performance of annual assessment work and continued possession and work upon said claims, including the drilling of two holes, one 75 feet deep and one 60 feet deep, and their marking of the boundaries of the claims. The Navy had in the past mined certain diatomaceous earth from respondents’ claim No. 1 and paid for the same at an agreed price. In 1963 respondents mapped their said claim and duly recorded the map in the office of the county recorder of Churchill County, being the county in which the said claims were located. Upon learning of the taking of the diatomaceous earth by the defendants, plaintiffs, respondents herein, promptly asserted their claims to the Navy and to the officers and agents of the defendants.

Plaintiffs’ complaint alleged that during 1959 and *472 1960 Dinwiddie was the primary contractor with the Department of Navy for the construction of the bombing ranges and that Miller was the sub-contractor of Dinwiddie to construct portions thereof, including the creation of targets by the use of diatomaceous earth, and that during the performance of said sub-contract Miller was at all times under the direct order and control of Dinwiddie, and the diatomaceous earth was taken with the knowledge and consent of Dinwiddie; also that the plans as prepared by the Navy for the use and direction of Dinwiddie erroneously outlined the bombing range as including the Wy2 of said Section 11; and that a Navy inspector designated to Miller the excavation theretofore made by the Navy as the place where the Navy had taken diatomaceous earth. The court further found that Miller or his employees could have observed the monuments establishing the corners and center posts of the claims in question, but that Miller relied upon its right to remove the diatomaceous earth on the mistaken premise that the site of removing the same was in the area withdrawn for Navy use; that Miller mined the earth solely from plaintiffs’ Wild Horse Claim No. 1 situate entirely in the Wy2 of said Section 11, and in such trespass the defendants converted to their own use 2,050 tons of diatomaceous earth of the value of $8.20 per ton in place, prior to the incurring of costs of mining the same, and that such trespass was not willful. Pursuant to such findings, judgment was entered against Dinwiddie (Dinwiddie Construction Co.) and Miller (George E. Miller Construction Co., Inc.) jointly and severally in the sum of $16,810.00, with interest and costs.

Dinwiddie and Miller moved for a new trial, which was denied. Thereupon the present substituted attorneys for appellant moved on behalf of Dinwiddie alone to vacate the judgment, which motion was likewise denied. As noted above, Dinwiddie alone appealed from the judgment. No appeal was taken from either the denial of the motion of Dinwiddie and Miller for a new trial or the denial of the motion of Dinwiddie to vacate the judgment.

*473 1. In support of the motion to vacate the judgment, which motion was made by Dinwiddie alone through its substituted attorneys, Dinwiddie submitted a copy of a sub-contract between it and George E. Miller personally. As noted, such motion, and the motion for new trial, were denied. Although no appeal was taken from such denial, said sub-contract was made a part of the record in Dinwiddie’s appeal from the judgment alone. No cross-claim had been filed against George E. Miller personally and no motion or affirmative defense was raised upon the ground of misjoinder or nonjoinder of parties and was at no time asserted prior to the entry of judgment. Patently the sub-contract was relevant only to the motion to modify the judgment. 1 Not only is this clear from the record, but in the affidavit of Richard O. Kwapil, Jr., in support of the motion to modify the judgment, we find the following:

“That the sub-contract agreement on the job in question was between DINWIDDIE CONSTRUCTION COMPANY and GEORGE E. MILLER personally; that thereafter GEORGE E. MILLER, personally, caused GEORGE E. MILLER CONSTRUCTION COMPANY to do the actual work on the job, but the sub-contract was still in full force and effect.” Dinwiddie predicates its appeal from the judgment on the contention that it had a sub-contract with George E. Miller, an individual, which contained a “hold harmless clause,” which he would be unable to pursue under the judgment as rendered against it and the asserted sub-contractor. This is without merit. In Gensler-Lee v. Geertson, 73 Nev. 328,

Related

Central Bit Supply, Inc. v. Waldrop Drilling & Pump, Inc.
717 P.2d 35 (Nevada Supreme Court, 1986)
Stearns' Properties v. Trans-World Holding Corp.
492 F. Supp. 238 (D. Nevada, 1980)
Barnes v. Lopez
544 P.2d 694 (Court of Appeals of Arizona, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
406 P.2d 294, 81 Nev. 469, 1965 Nev. LEXIS 257, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dinwiddie-construction-co-v-campbell-nev-1965.