Dineen v. Ward

CourtSuperior Court of Maine
DecidedMarch 17, 2005
DocketLINcv-04-067
StatusUnpublished

This text of Dineen v. Ward (Dineen v. Ward) is published on Counsel Stack Legal Research, covering Superior Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dineen v. Ward, (Me. Super. Ct. 2005).

Opinion

STATE OF MAINE LINCOLN, ss. DAVID DINEEN, d/b/a MID-MAINE NURSERY & LANDSCAPE CONSTRUCTION,

Plaintiff

Vv.

NEIL WARD and NU-TEK HOME BUILDERS and DOUGLAS S. ROBERTS and ELISE C. ROBERTS,

Defendants

and

FIRST NATIONAL BANK OF DAMARISCOTTA,

Party-in-Interest

I. Introduction.

SUPERIOR COURT CIVIL ACTION DOCKET NO. CV-04-067 ror? Sy

DECISION AND ORDER

Pending before the court are four motions: plaintiff’s motion for attachment and

trustee process, defendant Neil Ward’s motion to dismiss and for Rule 11 sanctions,

plaintiff's motion to amend complaint, and defendant Ward’s motion for protective

order.

The motion for attachment was the subject of a testimonial hearing on February

9, 2005, which had been continued from the date set for same, February 8, 2005, because

of the unavailability of some of the defendants’ witnesses. Although argument had

been scheduled for February 8 on the motion to dismiss and the motion to amend, those

matters were also continued to the next day. Because of the press of time, the

defendants did not have the opportunity to present all of their witnesses on February 9, nor was oral argument heard on the other two motions. Nevertheless, the parties agreed that the court should decide the three motions without further testimony and without oral argument.

The motion for protective order has never been scheduled for oral argument but will nevertheless be addressed in this order as its disposition naturally follows the motions to dismiss and to amend.

The same attorney represents all defendants. The party-in-interest, First National Bank of Damariscotta, did not participate in the disputes concerning the pending motions.

Il. Motion for Attachment and Trustee Process.

At the outset of the discussion concerning this motion, it must be understood that the factual findings and conclusions concerning the applicable law expressed here are preliminary and only apply to this motion. That is, they are not binding on the parties or this court as “law of the case” because the hearing on this motion was abbreviated, especially as to any evidence the defendants may have presented. Moreover, the nature of a decision on a motion for attachment is predicative and not final. This is, the court’s task is to determine whether, based on the evidence presented, the plaintiff has established “by a preponderance of the evidence that the moving party will succeed on its claim and in an amount equal to or greater than the amount of the attachment sought.” (Emphasis supplied). Trans Coastal Corp. v. Curtis, 622 A.2d 1186, 1188 (Me. 1993); MLR. Civ. P. 4A(c), 4B(c).

In his motion, the plaintiff asks for attachment and trustee process on defendants Nu-Tek Home Builders and Douglas and Elise Roberts (collectively, “Robertses”) in the

sum of $64,829.50. Thus, it is incumbent upon him to establish by preponderance that he will succeed in his claim against these three defendants in that sum or a greater amount.

In the court’s view, the plaintiff has not succeeded in this mission because the court concludes that his version of the contractual relationship with the defendants is no more persuasive than theirs. The court also finds that the statute relied on by the plaintiff, 10 M.R.S.A. § 1115(1), does not yield the presumptive relief he requests.

The plaintiff’s view of the facts is that he had a time and materials contract with Nu-Tek and the Robertses. This was because the project was larger than those he had previously had with Nu-Tek and would entail contingencies and costs that were sufficiently unpredictable that a fixed price contract was not agreed to. In his post- hearing memorandum the plaintiff, through counsel, cites a number of facts which would support this conclusion. Thus, the plaintiff submitted three invoices which contained detailed entries for hours of work performed, cost of materials and costs for use of equipment. Accordingly, it may be said, the plaintiff understood that he would be paid on such a basis and billed accordingly. It is also true that, as to the first invoice, the plaintiff was paid approximately the sum cited which would suggest that the defendants had acquiesced in this approach.

Neil Ward (Ward), Nu-Tek’s principal, testified that this was a fixed price contract and that Dineen gave him a fixed bid of $50,000, “plus or minus a few bucks,” a representation that was corroborated by defendant Douglas Roberts. The fact that this figure was not precise does not, in the court’s view, suggest that it was not a fixed price contract as opposed to a time and materials contract. Just as with Nu-Tek’s agreement

with the Robertses, any fixed price contract is bound to have some margin for

correction. Ward also testified that he was concerned that he was not getting periodic progress payment bills from Dineen to pay him over time for the work contracted for. Obviously, also, if this was a time and materials contract, it would be likely that the subcontractor would bill frequently as he incurred expenses rather than submit three large detailed bills, the second of which followed the first by at least seven months.

Ward also said that his prior contracts with Dineen were fixed-price and that that circumstance suggests that this enterprise was the same as the parties’ past practice.

Ward’s and the Robertses’ payments to Dineen were also round figures, suggesting that this was a fixed-price contract as opposed to the acceptance of the more detailed billing and payments which a time and materials contract would suggest.

Finally, Dineen testified that when he got his final check from Ward on May 13, 2004, for $20,000, Ward was “in the ball park” of being up-to-date with what Nu-Tek owed him. Because this was the day before Ward discharged Dineen, it would appear that as of May 13, 2004, Dineen accepted that Nu-Tek’s “debt” to him was nearly paid. Therefore, because the amount Dineen had been paid as of that day was $47,000 and the alleged contract was for $50,000, it may be understood that the parties had, in fact, agreed to the fixed price and that Nu-Tek was “in the ball park” of satisfying its obligation of paying that sum. Even if this interpretation of these events is incorrect, certainly Nu-Tek would not have been “in the ball park” of satisfying Dineen’s bill if Nu-Tek still owed him $64,829.50 on May 13 - the amount Dineen claims Nu-Tek owes him as alleged in the pending motion.

Accordingly, the court does not find Dineen’s interpretation of the parties’ dealings more persuasive than the defendants’ and therefore cannot find that the

former has met his burden of proof on this motion. 5

The plaintiff also argues that by virtue of the provisions of 10 M.R.S.A. § 1115(1), the defendants have waived any objections to the plaintiffs’ invoices and therefore are liable to pay them in full.

The cited statute reads in pertinent part as follows:

§ 1115. Errors in documentation

1. Invoice errors. If an invoice is filled out incorrectly or incompletely

or if there is any defect or impropriety in an invoice submitted, the owner,

contractor or subcontractor must contact the person submitting the

invoice in writing within 10 working days of receiving the invoice. If the contractor or subcontractor does not notify the person submitting the invoice within 10 days, the documentary errors are deemed waived.

Regrettably, the court can find no Maine case law interpreting this provision, and the parties have cited none.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Jenkins, Inc. v. Walsh Bros., Inc.
2001 ME 98 (Supreme Judicial Court of Maine, 2001)
Trans Coastal Corp. v. Curtis
622 A.2d 1186 (Supreme Judicial Court of Maine, 1993)
State v. McKenna
1998 ME 49 (Supreme Judicial Court of Maine, 1998)
Johnson v. Exclusive Properties Unlimited
1998 ME 244 (Supreme Judicial Court of Maine, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
Dineen v. Ward, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dineen-v-ward-mesuperct-2005.