Dillon v. Suburban Land Co.

80 S.E. 471, 73 W. Va. 363, 1913 W. Va. LEXIS 201
CourtWest Virginia Supreme Court
DecidedDecember 9, 1913
StatusPublished
Cited by4 cases

This text of 80 S.E. 471 (Dillon v. Suburban Land Co.) is published on Counsel Stack Legal Research, covering West Virginia Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillon v. Suburban Land Co., 80 S.E. 471, 73 W. Va. 363, 1913 W. Va. LEXIS 201 (W. Va. 1913).

Opinion

Miller, Judge:

From a judgment for plaintiffs for $863.50, on the verdict of the jury, defendant brings error.

The action was upon the common counts in assumpsit, with bill of particulars attached, for an alleged balance due on a contract to build two miles of road upon defendant’s suburban land.

The defense was non assumpsit, payments, and a notice of recoupment of damages for alleged breach of the contract. Accompanying the plea of payments was 'an account specifying the several payments made, aggregating $1,636.40.

By the original contract plaintiffs agreed, in substance, to grade and build the road, the grading, materials furnished, and work done thereunder to be strictly in accordance with the plans and specifications; and they were to be paid therefor by the defendant at the rate of $3,000.00 per mile, and estimates of the amount of work done and completed in a satisfactory manner to defendant’s engineers were to be made every two weeks; whereupon defendant, withholding 10% of the amount till completion, was to pay plaintiffs the remainder, or to such parties as might be entitled thereto on account of labor and materials furnished for said work, as the said engineers might direct.

Plaintiffs thereby also agreed to guarantee the workmanship and material for one year from completion of the con[365]*365tract, and in the event said road or any part thereof should not at the end of that period be in as good condition as when completed, except such injury as might be done to the limestone surface thereof by ordinary use, plaintiffs agreed to remove the unsatisfactory part of the road and replace the same with work and materials satisfactory to defendant.

Subject to inclemency of weather preventing it, plaintiffs agreed to complete the work on or before July 1, 1908, and faithful performance of the contract by them was to be secured by a bond in the penalty of $4,000.00, with satisfactory security. By a subsequent agreement the giving of the bond was waived, and in lieu thereof it was stipulated that defendant should retain $1,000.00, of the contract price, for one year after completion of the contract.

This contract, in writing, was signed by plaintiffs, and was executed on behalf of defendant by Blair P. Wilson, general manager, who is conceded to have had authority of his board of directors to make the contract.

It is proven that work under the contract had so far progressed by about July 1, 1908, that about a mile of the road had been completed, not in all respects finished and in perfect condition, but nearly so, but that on account of the intoxica: tion and neglect of one of the partners the work had been delayed, and it was then that Dillon, the other partner, appealed to the president and general manager of defendant for advice and direction, saying that he would not be able to complete the contract under existing conditions. He swears that they advised him to throw up the job, and that they would send the engineers to make a final estimate of the work done, and for which they would pay him in full; he to superintend the completion of the job under defendant’s direction at the rate of $3.00 per day. After the engineers reported he swears defendant’s general manager wanted to cut him down to some where over two hundred dollars, which he would not stand. It was then agreed, he says, that each of the parties should select an engineer to go on the ground and make an estimate, and that defendant was to pay him on the basis of that estimate. One of the estimates to which he refers, dated July 4, 1908, and which he introduced in evidence, is headed “Estimate No. 5 to Dillon & Harrison, Contractors”, and is as fol[366]*366lows: By 6500 cubic yards of excavation, at 21c, $1365.00. By 600 cubic yards of stone, at 1.25, $725.00. By 90 cubic yards of crushed limestone, at 1.75, $157.50. Total $2,247.50. Less 10% retained, $224.75. Balance $2,022.75. Less previous estimates, $1,359.00. Amount of this estimate, $663.75.

Another estimate, however, introduced by plaintiffs in connection with the testimony of Maupin, one of the engineers of the defendant company, dated July 13, 1908, addressed to the defendant company, and which Maupin swears was made for Dillon & Harrison because they wanted it, reads as follows: "Gentlemen: Complying with your directions for an accurate and complete estimate of the amount of work done to date on the road improvement for Westmoreland, we find as follows: 4010 cubic yards of excavation, 656.8 cubic yards of sand stone foundation, 92 cubic yards of limestone. Dillon and Harrison’s contract price is $3000.00 per mile for a completed roadway, 14 feet in width, with 3 inches sandstone bed, finished with 3 inches crushed limestone. Estimating one mile of completed work, we find that the excavation and necessary material will amount to the following: Excavation 5280 cubic yards, Sandstone foundation 684 cubic yards, Crushed limestone 684 cubic yards. Estimating this unfinished work on what we consider equitable prices for the different materials we have: 4010 cubic yards excavation at 21c, $842.10, 656.8 cubic yards sandstone at 1.35, $886.68, 92 cubic yards limestone at 1.56, $143.52. Full estimate on work done $1872.30. From tliis estimate we would advise that 10% be withheld for finishing and rolling.” Signed, "The Leete-Maupin Engineering Co., Per A. B. Maupin.”

The engineer selected by the plaintiffs was Howard Palmer. At the instance of the plaintiffs he made a subsequent estimate of the work of excavation done by plaintiffs, as of August 8, 1908, which purports to show 6,252.3 cubic yards of excavation, about 250 cubic yards short of the estimate of the Leete-Maupin Company, of July 4, and about 2240 cubic yards in excess of the estimate of the Leete-Maupin Company, of July 13. Palmer does not furnish any estimate of the stone furnished. It is fully proven that the estimate of July 4, was one of the bi-monthly estimates made under the contract, was not made from actual measurements, and was not, and not [367]*367intended to be very accurate. This is the main substance of the evidence offered by plaintiffs and upon which they rely.

In argument plaintiffs’ counsel endeavor to support the judgment upon the estimate of July 4, as follows: Work done, $2247.50; previous estimates, $1384.00; balance, $863.50, the exact amount of the verdict and judgment. But the previous estimates reported were $1359.00, not $1384.00. On the theory of plaintiffs’ counsel, therefore, the verdict and judgment should' have been $888.50, a difference of $25.00.

But defendant denies any contract modifying the original, binding it. It is conceded, however, by Wilson, general manager, and Bowman, secretary, both of whom were present, that a modification, substantially on the terms proven by plaintiffs was considered. According to Wilson’s evidence, Dillon went to his office about July 1, representing that he was having trouble with his partner and that it would be impossible for him to complete the work if he kept Harrison with him, and inquired if some new arrangement could not be made so that he could get fid of Harrison and go ahead with the work; that he called in Bowman, secretary, explained to him Dillon’s situation, and that he and Bowman agreed that if they could have a settlement agreeable to both parties they might settle with Dillon, so he might finish the job by the day, and in the same connection he says: “So we decided we would send an engineer down to make a final estimate, which we did, and afterwards Mr. Dillon refused to accept it.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

L.D.A., Inc. v. Cross
279 S.E.2d 409 (West Virginia Supreme Court, 1981)
W. Bateson & Co. v. Baldwin Forging & Tool Co.
84 S.E. 887 (West Virginia Supreme Court, 1915)
Bare v. Victoria Coal & Coke Co.
80 S.E. 941 (West Virginia Supreme Court, 1914)
Thomas v. Kanawha Valley Traction Co.
80 S.E. 476 (West Virginia Supreme Court, 1913)

Cite This Page — Counsel Stack

Bluebook (online)
80 S.E. 471, 73 W. Va. 363, 1913 W. Va. LEXIS 201, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillon-v-suburban-land-co-wva-1913.