Dillard v. Shaughnessy, Fickel & Scott Architects, Inc.

943 S.W.2d 711, 1997 Mo. App. LEXIS 257, 1997 WL 81111
CourtMissouri Court of Appeals
DecidedFebruary 25, 1997
DocketWD 52665
StatusPublished
Cited by20 cases

This text of 943 S.W.2d 711 (Dillard v. Shaughnessy, Fickel & Scott Architects, Inc.) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillard v. Shaughnessy, Fickel & Scott Architects, Inc., 943 S.W.2d 711, 1997 Mo. App. LEXIS 257, 1997 WL 81111 (Mo. Ct. App. 1997).

Opinion

LAURA DENVIR STITH, Judge.

Appellant A.L. Huber & Son, Inc., a general contractor on a construction project, appeals the trial court’s ruling on motion for summary judgment that the indemnity provision of its subcontract with P&S Masonry, Inc. did not entitle it to indemnity for the *713 attorney’s fees it expended in defending a lawsuit brought against it by a worker injured on the construction project.

We affirm the trial court’s determination that Kansas law governs the interpretation of this subcontract and that under Kansas law Huber’s own attorney’s fees were not included in the provision requiring P&S to indemnify Huber for “any liability, loss, cost or expenses ... caused by either the General Contractor or the Sub-Contractor or by their work.”

We find, however, that the subcontract’s indemnity provision was broad enough to require P&S to indemnify Huber for the moneys Huber had paid to the project’s architect and engineer in settlement of their claims that the indemnity provision of Huber’s contract with the landowner explicitly required Huber to reimburse them for the attorney’s fees and expenses they incurred in defending the same personal injury suit. These sums constituted a liability of Huber to the architect and engineer, and hence came within the indemnity provision of the subcontract. Similarly, the subcontract required P&S to reimburse Huber for the moneys it was required to pay the landowner to reimburse it for the attorney’s fees it incurred in defending the personal injury claims against the landowner. Reversed and remanded for further proceedings in accordance with this opinion.

I. FACTUAL AND PROCEDURAL BACKGROUND

The Most Reverend Ignatius J. Strecker, Archbishop of the Roman Catholic Archdiocese of Kansas City, Kansas, hired A.L. Huber & Son, Inc. as general contractor for the •construction of a church and a school in Leawood, Kansas. He also hired Shaughnes-sy, Fiekel & Scott Architects, Inc. (“SFS”) to serve as architect for the construction project, and hired Structural Engineering Associates, Inc. (“SEA”) to serve as structural engineer for the project. The contract between Huber and the Archbishop contained a provision requiring Huber to indemnify the Archdiocese, SFS, and SEA for any claims and expenses, including attorney’s fees, caused in whole or in part by the negligence of Huber or its subcontractors.

Huber requested and received bids from several subcontractors, including P&S Masonry, Inc. It is unclear when Huber accepted P&S’s bid, but P&S began work on January 24, 1991. On January 28, 1991, Huber mailed P&S two subcontracts, one for masonry work on the church and one for masonry work on the school. On March 1,1991, John Pinnell, president of P&S, signed the subcontracts on behalf of P&S in its office in Le-nexa, Kansas. Mr. Pinnell then mailed the subcontracts back to Huber along with an attached list of exclusions and clarifications. Randy K. Huber, Vice-President of Huber, signed the subcontracts on behalf of Huber on March 4,1991, in Huber’s office in Kansas City, Missouri.

The subcontract signed by Huber and P&S contained an indemnity provision which stated in part that:

The Sub-Contractor will save the General Contractor harmless from any liability, loss, cost or expenses, resulting from injuries or damages to persons or property caused by either the General Contractor or the Sub-Contractor or by their work.

(emphasis added). This indemnification provision was contained in small gray print as part of a “boilerplate” series of pre-printed provisions on the back of the contract form.

On March 20, 1991, Lee Dillard, an employee of P&S, was injured when a masonry wall on the construction site collapsed. Mr. Dillard subsequently filed suit against the Archbishop, SFS, SEA, Huber, and two other corporations he alleged were responsible for the placement and maintenance of scaffolding involved in the fall. Archbishop Strecker demanded that Huber provide him with a defense pursuant to the indemnity provision of his contract with Huber. Huber’s insurer provided a defense to the Archbishop, and Mr. Dillard subsequently dismissed his claim against the Archbishop.

On May 19, 1992, Huber’s attorney sent a letter to P&S stating that Mr. Dillard’s injury was attributable to P&S’s work, and that P&S had “a contractual obligation to A.L. Huber with respect to plaintiffs’ claims in the *714 Dillard lawsuit as well as any related claims that may be made against A.L. Huber by the codefendants in that lawsuit or by others.” Huber demanded that P&S or its insurer defend and indemnify Huber against Mr. Dillard’s suit and all future claims.

SFS and SEA were granted summary judgment on all of Mr. Dillard’s claims against them. They then filed cross-claims against Huber seeking indemnification for their expenses and attorney’s fees incurred in defending Mr. Dillard’s claims. The circuit court found they were not entitled to indemnity. On appeal, this Court reversed and remanded. We noted that, in addition to suing SFS and SEA, Mr. Dillard had claimed that his injuries were caused in whole or in part by Huber and P&S. If this were proved, it would trigger the indemnity provision of the contract between Huber and the Archbishop, which specifically required:

the General Contractor to indemnify Architects and Architects’ consultant (Engineers) from claims and expenses, including attorney fees attributable to injury caused in whole or in part by the negligence of the General Contractor [Huber] or its subcontractors.

Dillard v. Shaughnessy, Fickel and Scott Architects, Inc., 884 S.W.2d 722, 723 (Mo.App.1994) (emphasis added).

On remand, Huber settled SFS and SEA’s indemnity claims against it by paying them $34,210.11 and $48,084.49, respectively. He then filed a third-party petition against P&S, Count II of which sought indemnity from P&S for the moneys Huber had paid in settlement of SFS and SEA’s claims against Huber for indemnity. Count I sought indemnity from P&S for the attorney’s fees and expenses Huber itself incurred in defending against Mr. Dillard’s suit. Count III sought indemnity for the attorney’s fees and other expenses it had paid in defending Mr. Dillard’s claims against Archbishop Strecker.

P&S and Huber filed cross-motions for summary judgment. Both motions were based on the language of the indemnity provision of their subcontract, which, as earlier noted, required P&S to indemnify Huber for “any liability, loss, cost or expenses” resulting to Huber from injuries to persons such as Mr. Dillard which arose in whole or in part out of Huber’s or P&S’s negligence.

The trial court ruled that the phrase “any liability, loss, cost or expenses” as used in the indemnity provision of the subcontract did not include Huber’s attorney’s fees incurred in defending Mr.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Prather v. Organon USA, Inc.
957 F. Supp. 2d 1110 (E.D. Missouri, 2013)
Sturgeon v. Allied Professionals Insurance Co.
344 S.W.3d 205 (Missouri Court of Appeals, 2011)
Crater Corp. v. Lucent Technologies, Inc.
625 F. Supp. 2d 790 (E.D. Missouri, 2007)
Ameristar Jet Charter, Inc. v. Dodson International Parts, Inc.
155 S.W.3d 50 (Supreme Court of Missouri, 2005)
Goede v. Aerojet General Corp.
143 S.W.3d 14 (Missouri Court of Appeals, 2004)
Byers v. Auto-Owners Insurance Co.
119 S.W.3d 659 (Missouri Court of Appeals, 2003)
Nusbaum v. City of Kansas City
100 S.W.3d 101 (Supreme Court of Missouri, 2003)
Armstrong Business Services, Inc. v. H & R Block
96 S.W.3d 867 (Missouri Court of Appeals, 2002)
Chesapeake Operating, Inc. v. Nabors Drilling USA, Inc.
94 S.W.3d 163 (Court of Appeals of Texas, 2002)
Sachs Electric Co. v. HS Construction Co.
86 S.W.3d 445 (Missouri Court of Appeals, 2002)
PVI, Inc. v. Ratiopharm GmbH
Eighth Circuit, 2001
Amtech Lighting Services Co. v. Payless Cashways, Inc.
203 F.3d 1081 (Eighth Circuit, 2000)
CMT Partners v. Alaiwat
969 S.W.2d 885 (Missouri Court of Appeals, 1998)
Emerson Electric Co. v. Crawford & Co.
963 S.W.2d 268 (Missouri Court of Appeals, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
943 S.W.2d 711, 1997 Mo. App. LEXIS 257, 1997 WL 81111, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillard-v-shaughnessy-fickel-scott-architects-inc-moctapp-1997.