Dillard Construction, Inc. v. Haron Contracting Corp.

CourtCourt of Appeals of Tennessee
DecidedNovember 23, 2010
DocketE2010-00170-COA-R3-CV
StatusPublished

This text of Dillard Construction, Inc. v. Haron Contracting Corp. (Dillard Construction, Inc. v. Haron Contracting Corp.) is published on Counsel Stack Legal Research, covering Court of Appeals of Tennessee primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Dillard Construction, Inc. v. Haron Contracting Corp., (Tenn. Ct. App. 2010).

Opinion

IN THE COURT OF APPEALS OF TENNESSEE AT KNOXVILLE October 6, 2010 Session

DILLARD CONSTRUCTION, INC. v. HAVRON CONTRACTING CORP. ET AL.

Appeal from the Chancery Court for Hamilton County No. 08-0319 W. Frank Brown, III, Chancellor

No. E2010-00170-COA-R3-CV - FILED NOVEMBER 23, 2010

The only parties left litigating in what started out as a complex construction dispute are, on one side, Dillard Construction, Inc1 , and, on the other, Dillard’s demolition subcontractor, Havron Contracting Corp. After a bench trial and several post-trial motions, the court held that (1) Dillard, while not having a contract with Havron, was required by quantum meruit to pay Havron $91,100 for work performed by Havron’s subcontractors; (2) Dillard was not entitled to an offset against that judgment for damage done to electrical equipment by Havron’s subcontractor; (3) Havron was entitled to recover from Dillard, under a “pass- through” indemnity theory, the attorney’s fees awarded against Havron and in favor of its subcontractor; and (4) Havron was not entitled to recover the attorney’s fees that it, Havron, incurred in defending against the claims of its subcontractor. Dillard appeals challenging both the quantum meruit award and the denial of an offset. Havron challenges the trial court’s denial of indemnification for attorney’s fees Havron incurred in defending the claims of its subcontractor. We affirm.

Tenn. R. App. P. 3 Appeal as of Right; Judgment of the Chancery Court Affirmed; Case Remanded

C HARLES D. S USANO, J R., J., delivered the opinion of the Court, in which D. M ICHAEL S WINEY and JOHN W. M CC LARTY, JJ., joined.

1 The bonding company – International Fidelity Insurance Company – that posted a bond on behalf of Dillard to remove a lien on the property where the demolition work was being done is also a party. Fidelity’s interests are identical to Dillard and both are represented on this appeal by the same attorneys. For simplicity, we will refer to both parties as “Dillard.” Everett L. Hixson, Jr., and Adam U. Holland, Chattanooga, Tennessee, for the appellants, Dillard Construction, Inc., and International Fidelity Insurance Company.

C. George Caudle, Chattanooga, Tennessee, for the appellee, Havron Contracting Corp.

OPINION

I.

At an earlier time, there were a number of parties in this case and various cross- claims, counterclaims, and third-party claims. Many of these claims have been resolved and we are now focused only on the claims between Dillard and Havron.

The basic facts that give rise to this dispute are fairly simple. Dillard contracted with a property owner to relocate an industrial plant. Havron had bid on the same project, but the owner chose Dillard. Havron specialized in demolition rather than “building” and was therefore hired by Dillard to perform much of the demolition work on the project. The work specifically at issue here is the demolition of “Bay 8.” After demolition work began on Bay 8, Dillard and Havron exchanged documents concerning the work on Bay 8, but the trial court correctly found that the exchanges were only offers and counteroffers with no meeting of the minds. That finding is not at issue on appeal. What the “minds” of the two parties never met on was the demolition of the roof of Bay 8. Havron had priced demolition of “sandwich panels” and “structural steel” for the sum of $63,100. According to Havron, this price did not include the roof, but, according to Dillard, it did include the roof as part and parcel of the structural steel demolition. Significantly, the proof at trial was that the term “structural steel” has a specific meaning in the construction industry that does not include the roof of a structure.

On December 4, 2009, Dillard’s project manager, Kemp, instructed Havron to start the demolition of Bay 8, beginning at the northeast corner. Kemp stated that the work needed to start “yesterday.” This was after a brief walk through that did not include all of Bay 8 and, as we have stated, before an agreement could be finalized.

Havron is a supervising contractor that does not have its own work crews. Havron hired Sitton Construction, LLC to begin the demolition of Bay 8. Sitton began its demolition work on a “lean-to” structure in which electrical components, including switchgear, were located. In the course of the demolition of the lean-to, Sitton damaged the switchgear. This did not sit well with the owner because the owner had planned to reuse the switchgear. Dillard informed the owner that it would do whatever it took to make the owner whole. Dillard instructed Havron to terminate Sitton. Havron did as instructed and almost

-2- immediately contracted with Paul Hutcherson dba H&S Construction, which will be referred to herein as “H&S,” to perform the work started by Sitton.

As work progressed, a disagreement between Dillard and Havron as to the scope of the work came to light. Dillard insisted that the structural steel component of demolition included the roof. Havron insisted that roof removal was an extra that was not included in the price of $63,100. H&S concurred with Havron that roof removal was extra work H&S had not agreed to perform. Dillard insisted that the roof be removed. Havron gave H&S a change order adding a payment of $21,100 for removal of the roof, which, coincidentally, brought H&S’s total contract amount with Havron to Havron’s initial price to Dillard of $63,100. Havron added approximately $7,000 profit and billed Dillard $28,000 for roof removal and $63,100 for sandwich panel and structural steel demolition for a total of $91,100.

The property owner secured replacement switchgear at a total cost of $72,688. Dillard agreed with the owner that the cost of the replacement switchgear should be deducted from Dillard’s contract price. Dillard then tried to pass the cost of the new switchgear on to Havron. Dillard took the position that Havron was responsible for the full cost of the replacement switchgear; it refused to pay Havron for the demolition work. Dillard also stood by its claim that the roof was included in the structural steel demolition and that Havron was not entitled to extra pay for the roof, beyond the original $63,100 price. Havron filed a lien against the property in the amount of $91,100. Havron refused to pay H&S until Dillard paid Havron. Havron relied on a “pay when paid” clause in its contract with H&S. H&S then filed a lien against the property in the amount of $63,100. Dillard secured a bond from International Fidelity Insurance Company to discharge the liens.

Almost every person or entity in the chain between the property owner and H&S, including the bonding company, sued every other person or entity in the chain on a variety of theories. Included was a claim under the Tennessee Prompt Pay Act, Tenn. Code Ann. § 66-34-101 et seq. (2004 & Supp. 2009), by H&S against Havron and Dillard. The bench trial lasted two days and was successful in resolving much of the case. After the trial, but before the court decided the case, Havron moved to amend its claim against Dillard to include a claim for indemnity in the event Havron were held liable to H&S. The trial court allowed the amendment to conform to the evidence. Four aspects of the trial court’s final judgment are implicated in this appeal.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bogan v. Bogan
60 S.W.3d 721 (Tennessee Supreme Court, 2001)
MacHinery Sales Co. v. Diamondcut Forestry Products, LLC
102 S.W.3d 638 (Court of Appeals of Tennessee, 2002)
Castelli v. Lien
910 S.W.2d 420 (Court of Appeals of Tennessee, 1995)
Paschall's, Inc. v. Dozier
407 S.W.2d 150 (Tennessee Supreme Court, 1966)
Pullman Standard, Inc. v. Abex Corp.
693 S.W.2d 336 (Tennessee Supreme Court, 1985)
Estate of Wilson v. Arlington Auto Sales, Inc.
743 S.W.2d 923 (Court of Appeals of Tennessee, 1987)
Cohen v. Noel
56 S.W.2d 744 (Tennessee Supreme Court, 1933)
Bauman v. Smith
499 S.W.2d 935 (Court of Appeals of Tennessee, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
Dillard Construction, Inc. v. Haron Contracting Corp., Counsel Stack Legal Research, https://law.counselstack.com/opinion/dillard-construction-inc-v-haron-contracting-corp-tennctapp-2010.