DiBiase v. Universal Design & Builders, Inc.

473 A.2d 875, 1984 Me. LEXIS 662
CourtSupreme Judicial Court of Maine
DecidedApril 4, 1984
StatusPublished
Cited by12 cases

This text of 473 A.2d 875 (DiBiase v. Universal Design & Builders, Inc.) is published on Counsel Stack Legal Research, covering Supreme Judicial Court of Maine primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
DiBiase v. Universal Design & Builders, Inc., 473 A.2d 875, 1984 Me. LEXIS 662 (Me. 1984).

Opinion

NICHOLS, Justice.

The Defendant, Universal Design & Builders, Inc., appeals from an order of the Superior Court, Cumberland County, awarding the Plaintiff, William DiBiase, the return of his deposit money and denying the Defendant’s counterclaim seeking damages for breach of contract. That court found that the contract was not enforceable due to mutual mistake. The Plaintiff cross-appeals and seeks review of the court’s finding that time was not of the essence of the contract.

We affirm the judgment.

The Plaintiff, as buyer, and the Defendant, as seller, purported to enter into a contract (dated April 20, 1979) for the sale of real estate. The real estate consisted of a subdivision known as “Sunrise Terrace” “being sold as approved by Town of Cape Elizabeth for 23 single family residential house lots.” The purchase price was $88,-000, $4,000 of which the Plaintiff paid as an earnest money deposit. The Town demanded that a sum of money be put in escrow, in lieu of posting a bond, to cover the costs of road work and utility work on the subdivision project. The Plaintiff’s undertaking of the subdivision project was contingent on his entrance into the performance escrow agreement, which was to be financed by the Sun Savings and Loan Association. .

The contract provided that it was “subject to purchaser being able to confirm that the property is approved for subdivision as per the attached plans, and if the property is not approved as per plans, then the earnest money deposit will be promptly returned to the purchaser.” On the day the contract was signed, the Defendant informed the Plaintiff that the Town of Cape Elizabeth Planning Board had given final approval for the subdivision of all 23 lots and that completion of the subdivision plans would be automatic.

The contract further provided that the Plaintiff would have fifteen days after title was cleared to purchase the property; at that time a deed showing merchantable title would be delivered to the Plaintiff. In addition the contract expressly stated that “time is an essential part of this agreement.” On November 29,1979, the Defendant informed the Plaintiff that title had been cleared. The closing was to be held fifteen days later. When they met for closing, however, the Defendant was unable to present signed releases for five of the encumbrances on the property, although these releases had been signed the same morning and delivered to the Plaintiff’s attorney’s law firm. The Plaintiff refused to conclude the purchase on the grounds (iterated in his complaint) that he was not being presented with marketable title and that the subdivi *877 sion was not approved for subdivision per plans.

The Plaintiff sued to recover his deposit, and the Defendant counterclaimed for breach of contract. At the jury-waived trial, on February 1, 1983, evidence of the following additional facts was adduced: The Defendant’s principal officer, George King, and its real estate broker, Ted Scon-tras, informed the Plaintiff, that based on their understanding, the Town of Cape Elizabeth would approve the Plaintiff as the subdivision developer and would give him the same terms as it had the Defendant, including the amount of the required performance escrow agreement. Testimony varied as to the sum the Plaintiff would need to put into escrow under the original understanding between the Town and the Defendant. It may have been $76,000 or $100,000; at most, it was $140,000. It later developed that by November 8-9, 1979, the Town had not given final subdivision approval for all the lots and that it would require the Plaintiff to put at least $175,000 into escrow. The Sun Savings and Loan Association refused to finance more than $129,000 of the escrow agreement. The Town placed on the Plaintiff additional conditions which he had not been led to anticipate.

The Superior Court concluded, in an order dated March 10,1983, that the contract was unenforceable, because the parties had made a mutual mistake with respect to a material element of the contract — although this issue was not raised in the pleadings. The court entered judgment for the Plaintiff.

The Defendant’s first objection to this final order is that the issue of mutual mistake was not properly before the court. The issue was mentioned neither in the initial pleadings, in the pretrial memoranda, nor in the trial court’s pre-trial order. As a general rule, the issue would be treated as waived. M.R.Civ.P. 16(a)(3)(H); Ocean National Bank of Kennebunk v. Odell, 444 A.2d 422, 424 (Me.1982). However, M.R. Civ.P. 15(b) provides that “[wjhen issues not raised by the pleadings are tried by . . . implied consent of the parties, they shall be treated in all respects as if they had been raised in the pleadings.” This rule generally obtains even where the issue is omitted from a pre-trial order. See Mains v. United States, 508 F.2d 1251' (6th Cir.1975); 3 Moore’s Federal Practice ¶ 15.13[1] (1983).

There is authority for the proposition that an issue is tried by implied consent when one party generates it during the trial and the opposing party does not object to it at the time. Doane v. Pine State Volkswagen, Inc., 377 A.2d 481, 484 n. 2 (Me.1977); Gallegos v. Stokes, 593 F.2d 372, 375 (10th Cir.1979). But cf. Cushman v. Perkins, 245 A.2d 846 (Me.1968). When both parties acknowledge an unpleaded issue during trial, implied consent is indisputable. 1 Field, McKusick & Wroth, Maine Civil Practice § 15.5 at 304 (1970). Midway in this trial, the presiding justice put the parties on notice that he considered the fundamental issue in the case to be the Plaintiff’s understanding at the time of contract as to the preconditions for completing the subdivision. During the remainder of the trial, both sides focused principally on both the Plaintiff’s and the Defendant’s understanding of these preconditions. 1 Both par *878 ties thereby acknowledged the issue that the understanding of these preconditions may have been mistaken and that the mistake may have been mutual. Hence, the issue of mutual mistake was tried by implied consent.

The Defendant next contends that the trial court erred in finding mutual mistake as to a material element of the contract. It protests that there was no mistake on its part, for it “knew what the terms of the contract were, and knew what the various conditions and escrow requirements relating to the subdivision were.” The trial court, however, found that the Defendant was mistaken in believing that once the Plaintiff entered into the contract, he would be automatically approved by the Town for the subdivision project and would receive the same escrow terms. This finding may not be disturbed unless it was clearly erroneous. Blackmer v. Williams,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lindsay E. Verite v. Eric J. Verite
2016 ME 164 (Supreme Judicial Court of Maine, 2016)
Peter M. Beckerman v. Bruce Pooler
2015 ME 80 (Supreme Judicial Court of Maine, 2015)
Guardianship of Kean R. IV.
2010 ME 84 (Supreme Judicial Court of Maine, 2010)
Yim K. Cheung v. Wing Ki Wu
2007 ME 22 (Supreme Judicial Court of Maine, 2007)
Railan v. Katyal
766 A.2d 998 (District of Columbia Court of Appeals, 2001)
Ahlgren v. Fabian
1999 ME 6 (Supreme Judicial Court of Maine, 1999)
Poling v. Northup
652 A.2d 1114 (Supreme Judicial Court of Maine, 1995)
Bouchard v. Blunt
579 A.2d 261 (Supreme Judicial Court of Maine, 1990)
Clarke v. DiPietro
525 A.2d 623 (Supreme Judicial Court of Maine, 1987)
Miller v. Lentine
495 A.2d 1229 (Supreme Judicial Court of Maine, 1985)
Shore Builders, Inc. v. Dogwood, Inc.
616 F. Supp. 1004 (D. Delaware, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
473 A.2d 875, 1984 Me. LEXIS 662, Counsel Stack Legal Research, https://law.counselstack.com/opinion/dibiase-v-universal-design-builders-inc-me-1984.