Diamond B-Y Ranches v. Tooele County

2004 UT App 135, 91 P.3d 841, 498 Utah Adv. Rep. 32, 2004 Utah App. LEXIS 42, 2004 WL 905956
CourtCourt of Appeals of Utah
DecidedApril 29, 2004
DocketCase No. 20030578-CA
StatusPublished
Cited by3 cases

This text of 2004 UT App 135 (Diamond B-Y Ranches v. Tooele County) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diamond B-Y Ranches v. Tooele County, 2004 UT App 135, 91 P.3d 841, 498 Utah Adv. Rep. 32, 2004 Utah App. LEXIS 42, 2004 WL 905956 (Utah Ct. App. 2004).

Opinion

OPINION

ORME, Judge:

¶ 1 Diamond B-Y Ranches asserts that it is entitled to compensation under federal and state “taking” jurisprudence because Tooele County’s denial of Diamond’s request for a conditional use permit to operate a gravel pit rendered its property valueless. The trial court granted summary judgment in favor of the County based on its determination that Diamond had no protected property interest in the permit and did not provide sufficient evidence to allow approval of the permit. We reverse and remand.

BACKGROUND

¶ 2 Diamond owns over 190 acres of land in Tooele County, approximately one.third of which is within the northern boundary of the town of Stockton. The property has historically been used to operate a gravel pit, and Diamond purchased it either to conduct its own gravel pit operation or to sell it to a gravel extraction company. The nearest residential subdivision is a quarter mile from the southern boundary of the property. Within the property is a substantial portion of a unique geologic formation known as the Stockton Bar, which is a sediment deposit that is approximately 100 feet high and runs for several miles through the property.

¶ 3 In May 2000, Diamond contracted to sell the property to Geneva Rock Products, Inc. for six million dollars. At that time, the property was zoned such that mining and related activities, including the operation of a gravel pit, were among the activities designated as conditional uses for the property. The offer was therefore conditioned on Geneva obtaining a permit to operate a gravel pit, concrete batch plant, and asphalt hot plant on the property. On July 12, 2000, Geneva submitted its application to the County for a permit to conduct such activities on the property.

¶ 4 The application for a conditional use permit was reviewed by the Tooele County Planning Commission at a public hearing on July 19, one week after it was submitted. The Planning Commission expressed concerns about (1) negative impacts to residents, given the property’s close proximity to Stockton and (2) the destructive impact that an extraction operation would have on the Stockton Bar itself. Several citizens, including the mayor of Stockton, voiced their opinions at the meeting, primarily raising concerns about pollution and health problems that would result from a gravel pit operating next to a residential area. With regard to the Stockton Bar, the University of Utah had presented information describing the bar as *843 an important “geoantiquity,” 1 graduate students had “identified a potentially endangered species of plant that grows there,” and the County Engineer was concerned that “mining through the bar could disrupt the bar’s function as an ah’ dam between Tooele and Rush valleys.” The Planning Commission decided to “table the application until the County receives an Environmental Impact Statement (EIS) that fully explores every potential impact of this operation [and that t]he EIS shall be conducted at. [Diamond]’s expense by an independent firm of the County’s choosing.” A representative of Geneva indicated that Geneva “will be willing to get and pay for the study”; that “he was not aware of the concerns of the public”; that “they have encountered some other complications besides this”; and that “they will review what has been presented and could walk away from the project.” In light of the extensive opposition to the proposal, a member of the Commission “stated that she wants to let Geneva Rock know that they will have an uphill battle if the applicant proceeds.”

¶ 5 Geneva’s uphill battle became even more rigorous — or was at least temporarily delayed — the very next day. In order to reevaluate its overall policy regarding extraction operations, the County instituted a six-month moratorium on July 20, 2000, postponing consideration regarding any request for a conditional use permit to operate a gravel pit. Geneva did not further pursue the permit, and assigned its application to Diamond one week before the moratorium expired. When the moratorium expired on January 23, 2001, the County enacted an ordinance, which created a new “mining, quarry, sand and gravel excavation zone” and removed all mining activities from the list of uses conditionally permitted in the previous multiple use zoning district. Diamond’s property was not included among the areas eventually designated for extraction activities under the new zoning ordinance, but because the original application predated the zoning change, Diamond was allowed to continue to pursue the application under the previous ordinance. On January 24, 2001, Diamond “wrote the County Engineer[,] requesting that: (1) it continue to consider the pending Application on a grandfathered basis under the old zoning ordinance, because it was submitted before the ordinance was modified, and in the alternative, (2) that the County consider re-zoning Plaintiffs property to the new ... zoning classification.”

V 6 The Planning Commission next met on February 7, 2001, to discuss Diamond’s pending application under the prior ordinance. Once again, members of the Planning Commission and the public registered their concerns with the application. Diamond’s attorney, who attended the meeting, responded to those concerns by asserting that “it is their right to mine their property”; “[t]hey are willing to work with the community and be good neighbors”; and “[t]hey are willing to meet any reasonable request by the commission.” The Planning Commission, once again faced with several members of the community speaking in opposition to the proposal, “decided to table this item until an EIS is obtained by a company agreeable [to] both the county and the land owners.”

¶ 7 On March 21, 2001, the Planning Commission reconvened to consider the alternative request made by Diamond, namely “that the County consider re-zoning Plaintiffs property to the new ... zoning classification.” The Planning Commission evidently determined that Diamond’s property was not an appropriate location for extraction operations and recommended that the Tooele County Board of Commissioners deny the request to rezone. Among other things — all of which relate to concerns for the health and welfare of the citizens of Stockton and preservation of the Stockton Bar — this recommendation was based on the following: the Stockton Bar’s status as a “geoantiquity”; the possibility that “mining through the bar could disrupt the bar’s function as an air *844 dam”; the mayor’s suggestion “that there would be many [e]nvironmental impacts on the community”; the close proximity to an “existing residential development”; and “the odors of the asphalt operation and fugitive dust.” Over the next two months, the County Commission held three hearings in which the same concerns regarding negative impacts to the Stockton Bar and the surrounding community were echoed. On May 22, 2001, the County Commission denied Diamond’s request to have its property included in the new zone that permitted mining and extraction activities.

¶ 8 Diamond continued to pursue the application under the prior ordinance and requested bids from seven engineering firms that had been approved by the Planning Commission to provide an EIS. Only two of those firms responded, and neither offered to perform all' of the services that had been requested by the Planning Commission.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Town of Gurley v. M & N Materials, Inc.
143 So. 3d 1 (Supreme Court of Alabama, 2012)
Stevens v. LaVerkin City
2008 UT App 129 (Court of Appeals of Utah, 2008)
Arnell v. Salt Lake County Board of Adjustment
2005 UT App 165 (Court of Appeals of Utah, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2004 UT App 135, 91 P.3d 841, 498 Utah Adv. Rep. 32, 2004 Utah App. LEXIS 42, 2004 WL 905956, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diamond-b-y-ranches-v-tooele-county-utahctapp-2004.