Diamond Asphalt Corp. v. Sander

171 Misc. 2d 879
CourtNew York Supreme Court
DecidedAugust 1, 1996
StatusPublished
Cited by2 cases

This text of 171 Misc. 2d 879 (Diamond Asphalt Corp. v. Sander) is published on Counsel Stack Legal Research, covering New York Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Diamond Asphalt Corp. v. Sander, 171 Misc. 2d 879 (N.Y. Super. Ct. 1996).

Opinion

OPINION OF THE COURT

Helen E. Freedman, J.

These two CPLR article 78 proceedings, which raise identical issues of law, are consolidated for joint determination.1

Petitioners are unsuccessful bidders for street repair and reconstruction contracts with the City of New York Department of Transportation (DOT). They seek an order annulling the award by the municipal respondents2 (collectively, the City respondents) of the contracts to other businesses, and directing [882]*882the City to award the contracts to petitioners, on the ground that the City’s bid selection procedure violates General Municipal Law § 103 (1), which governs the award of public works contracts.3 Consolidated Edison Co. of New York, New York Telephone Company and Empire City Subway Co. (collectively, the Utilities) move to intervene in these proceedings.

Facts

Under the bidding procedure for the contracts at issue, the City respondents required that joint bids be submitted for (1) the project work for the City (the City Work) and (2) ancillary work for the Utilities, whose underground pipes, cables, wires and other privately owned facilities lie in the path of the City’s proposed construction (the Utility Work). The Utility Work involves protecting or relocating the Utilities’ facilities when necessary to perform the City Work. Both the City Work and the Utility Work for each project are governed by a single contract between the contractor and the City; under the contract, the City pays the contractor for both the City Work and the Utility Work. In a public works bid package distributed to prospective bidders, including petitioners, the City included a "Special Notice to Bidders”, which advised bidders that the Utility Work was included in the contract, that the contractor would be paid by the City for the Utility Work, and that "the Utilities] shall fund the cost of the Utility Work under an agreement between them and the City.”4

The agreement referred to above (the Joint Bidding Agreement or JBA), dated April 23, 1992, sets forth the joint bidding arrangement at issue here. The JBA applies to DOT and Department of Environmental Protection (DEP) projects for the construction, improvement and repair of roads and other [883]*883thoroughfares and sewers, culverts, water mains, etc. Its salient provisions are as follows:

The Joint Bidding Agreement provides that Utility Work to be performed by the City Work contractor will be included in the City’s project contract (the project contract). The city will require bidders for a project contract to submit joint bids for the Utility Work and the City Work. The JBA further provides that: "The City shall, consistent with its policy for letting construction contracts, award its construction contract to the lowest responsible bidder, based upon the total of each bid made for all work, including the Utility Work, to be performed under the [project] contract. The City and the [Utilities] agree that the priced [sic] bid by the City contractor should reflect an equitable distribution of costs for work to be performed on behalf of the parties and that excessive and unbalanced bids are to be avoided. The City agrees to consult with the [Utilities] as to what constitutes an excessive or unbalanced bid and as to what action the City, in its discretion, should take in the event of the submission of an excessive or unbalanced bid.” (Art 3, B.) The City is to administer the project contract on behalf of itself and the Utilities. The project contractors will look solely to the City for payment for the Utility Work. The Utilities agree to reimburse the City for the cost of the Utility Work, plus the cost of any extra Utility Work required during the course of the project and a pro rata share of certain incidental costs, and also to pay the City a 5% surcharge as an administrative fee.

As required by the City, each petitioner submitted a sealed bid which apportioned the contract price between the City Work and the Utility Work. The petitioners submitted the lowest bids for the City Work portion of each project contract, but their aggregate contract bids for the City Work and the Utility Work exceeded other companies’ aggregate bids for the contracts.

After reviewing the submitted bids, the City awarded the contracts to each of the lowest aggregate bidders for the contracts.5 City Chief Procurement Officer Richard M. Bonamarte sent petitioners letters dated June 14, 1996 with respect to each contract, stating that, under Mayor Giuliani’s authority and pursuant to New York City Charter § 313 (b) (2) and [884]*884Procurement Policy Board rules, he had determined that it was "in the best interest of the City” to award the contract to "the overall lowest responsive and responsible bidder for the combined City and Utility [Work]”. Bonamarte acknowledged to each petitioner that "the price allocated by [the successful bidder] to the [City Work] is greater than that incorporated into your firm’s bid.” Bonamarte wrote that his determination to award the contract to the lowest joint bidder was based on commitment letters executed by the City and the Utilities, under which the City would award the contract to the over-all lowest bidder, but would "pay as its share only the lowest price for City [W]ork that was contained in any responsive and responsible bid.” Under the commitment letters, the Utilities would pay the City the difference between the price of the lowest bidder for the City Work, i.e., the petitioners, and the City Work portion of the lowest joint bid (the Differential).6 Accordingly, Bonamarte concluded, the City "receives all the benefits incident to joint bidding as well as the lowest price for its work obtained through competitive sealed bidding.”

Contentions

Petitioners contend that they were the lowest responsible bidders for the City Work portion of the contracts, and accordingly the contracts should have been awarded to them under General Municipal Law § 103 (1), which states in relevant part: "Except as otherwise expressly provided by an act of the legislature or by a local law adopted prior to September first, nineteen hundred fifty-three, all contracts for public work involving an expenditure of more than twenty thousand dollars * * * shall be awarded by the appropriate officer, board or agency of a political subdivision or of any district therein * * * to the lowest responsible bidder furnishing the required security after advertisement for sealed bids in the manner provided by this section * * * Such officer, board or agency may, in his [885]*885or its discretion, reject all bids and readvertise for new bids in the manner provided by this section.” Petitioners acknowledge that General Municipal Law § 103 (1) provides that a municipality may "bypass” a lowest responsible bidder in accordance with laws adopted prior to September 1, 1953. But they deny that the City respondents had authority to bypass under New York City Charter § 313 (b) (2), which Bonamarte cited in his letters to petitioners, and which respondents now invoke as grounds for the bypass.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

General Contractors Ass'n of New York, Inc. v. Tormenta
180 Misc. 2d 384 (New York Supreme Court, 1999)
Diamond Asphalt Corp. v. Sander
238 A.D.2d 197 (Appellate Division of the Supreme Court of New York, 1997)

Cite This Page — Counsel Stack

Bluebook (online)
171 Misc. 2d 879, Counsel Stack Legal Research, https://law.counselstack.com/opinion/diamond-asphalt-corp-v-sander-nysupct-1996.