Devin B. Strickland v. Arch Insurance Company

CourtCourt of Appeals for the Eleventh Circuit
DecidedJanuary 9, 2018
Docket17-10610
StatusUnpublished

This text of Devin B. Strickland v. Arch Insurance Company (Devin B. Strickland v. Arch Insurance Company) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eleventh Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Devin B. Strickland v. Arch Insurance Company, (11th Cir. 2018).

Opinion

Case: 17-10610 Date Filed: 01/09/2018 Page: 1 of 10

[DO NOT PUBLISH]

IN THE UNITED STATES COURT OF APPEALS

FOR THE ELEVENTH CIRCUIT ________________________

No. 17-10610 Non-Argument Calendar ________________________

D.C. Docket No. 5:14-cv-00070-LGW-RSB

DEVIN B. STRICKLAND,

Plaintiff-Appellant,

versus

ARCH INSURANCE COMPANY,

Defendant-Appellee. ________________________

Appeal from the United States District Court for the Southern District of Georgia ________________________

(January 9, 2018)

Before TJOFLAT, MARCUS and WILLIAM PRYOR, Circuit Judges.

PER CURIAM:

Devin Strickland appeals the district court’s grant of summary judgment in

favor of Arch Insurance Company (“Arch”) on Strickland’s action to recover on a

payment bond issued by Arch. Specifically, the district court concluded that Case: 17-10610 Date Filed: 01/09/2018 Page: 2 of 10

Strickland’s claims on the bond were time-barred. On appeal, Strickland argues

that the district court erred in granting summary judgment on this basis. After

careful review, we affirm.

The relevant, undisputed facts are these. Strickland provided sand to

Douglas Asphalt Paving Company (“Douglas”) for a Georgia Department of

Transportation (“GDOT”) road improvement project. The GDOT’s 2001 Standard

Specifications for the Construction of Transportation Systems were incorporated

into Douglas’s contract with GDOT. According to the Standard Specifications, the

contractor was obligated to provide any repairs until GDOT issued written final

acceptance. The contractor also had to furnish documentary proof of payment to

material suppliers. Arch issued a payment bond on behalf of Douglas for the

project in 2003. Arch agreed to pay all entities that supplied materials to Douglas.

In 2007, Douglas was no longer authorized to work on the project because GDOT

declared that the company was in default. In accordance with its performance

bond obligations, Arch took over Douglas’s work and arranged for completion of

the project by a third-party contractor. Strickland did not supply sand after

Douglas was removed from the project.

In August 2010, GDOT determined that the work on the project was

substantially complete and ready for final inspection. In September 2010, the

third-party contractor requested final inspection, and it was performed. The punch

2 Case: 17-10610 Date Filed: 01/09/2018 Page: 3 of 10

list generated from the inspection -- listing work not yet conforming to the contract

specifications -- was complete by September 2011. In early 2012, Arch and its

contractor requested that GDOT accept the road improvement project for

maintenance. In its request, Arch told GDOT that the project had been open to

unrestricted traffic, all pay items were complete, and all punch-list work was

complete. In February 2012, a GDOT area engineer requested maintenance

acceptance because the project had been satisfactorily completed. In March 2012,

GDOT accepted project maintenance responsibilities retroactive to September

2011. Arch received semi-final payment in July 2012, which was subject to a

review by an auditor. GDOT did not pay any additional money on the project.

In September 2012, Strickland sent a demand letter on Arch’s payment

bond. Arch acknowledged the claim and asked for additional documentation and a

proof of claim. Strickland did not respond to Arch’s requests. In 2014, Strickland

learned that GDOT was preparing to close out the project. A GDOT employee told

Strickland that he needed to file any claims he had immediately, as GDOT would

not close out a project if there was a pending lawsuit. Strickland filed the instant

action in August 2014. Later that month, a GDOT employee stated in an

e-mail that the road improvement project at issue had not yet received final

acceptance and approval. In September 2014, GDOT sent a letter of “final

acceptance,” which stated that the project had “been accepted” by GDOT as of

3 Case: 17-10610 Date Filed: 01/09/2018 Page: 4 of 10

April 17, 2012. According to a GDOT representative, the paperwork and close out

of the project took two years to complete; since September 2011, “final

acceptance” of the project had been pending the acquisition of a materials

certificate, which is GDOT paperwork stating that all materials used had been

certified and approved.

On this undisputed record, the district court granted summary judgment in

favor of Arch. It concluded that the one-year statute of limitations had run on

Strickland’s action because no genuine dispute of fact existed about the project

being completed and accepted in September 2011. This timely appeal follows.

We review a district court’s grant of summary judgment de novo, applying

the same legal standard as the district court and construing the facts and drawing

all reasonable inferences therefrom in the light most favorable to the non-moving

party. Josendis v. Wall to Wall Residence Repairs, Inc., 662 F.3d 1292, 1314

(11th Cir. 2011). We will affirm a grant of summary judgment if the movant has

shown, based on our review of the entire record, “that there is no genuine dispute

as to any material fact and the movant is entitled to judgment as a matter of law.”

Fed. R. Civ. P. 56(a). A district court’s interpretation and application of a statute

of limitations presents a legal question that we review de novo. Mississippi Valley

Title Ins. Co. v. Thompson, 802 F.3d 1248, 1252 (11th Cir. 2015).

4 Case: 17-10610 Date Filed: 01/09/2018 Page: 5 of 10

We are unpersuaded by Strickland’s argument that the district court erred in

granting summary judgment on statute of limitations grounds. In diversity actions,

we apply the relevant state’s statutes of limitations. Cambridge Mut. Fire Ins. Co.

v. City of Claxton, Ga., 720 F.2d 1230, 1232 (11th Cir. 1983). Under Georgia law,

“[n]o action can be instituted on the payment bonds or security deposits after one

year from the completion of the contract and the acceptance of the public works

construction by the proper public authorities.” O.C.G.A. § 13-10-65. State law

also determines when a diversity action commences for statute of limitations

purposes. See Walker v. Armco Steel Corp., 446 U.S. 740, 752-53 (1980). When

the Supreme Court of Georgia construed the former statute governing bonds for

public contractors (which did not vary in any material way from the current statute)

it held that the one-year statute of limitations period for filing suit on a payment

bond “commences at the completion of the actual construction work and

acceptance thereof by the public authority.” U.S.F. & G. Co. v. Rome Concrete

Pipe Co., 353 S.E.2d 15

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
Devin B. Strickland v. Arch Insurance Company, Counsel Stack Legal Research, https://law.counselstack.com/opinion/devin-b-strickland-v-arch-insurance-company-ca11-2018.