Developers Surety and Indemnity v. Renaissance/Valley Farms, LLC

614 F. App'x 805
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 2, 2015
Docket14-6400
StatusUnpublished
Cited by1 cases

This text of 614 F. App'x 805 (Developers Surety and Indemnity v. Renaissance/Valley Farms, LLC) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Developers Surety and Indemnity v. Renaissance/Valley Farms, LLC, 614 F. App'x 805 (6th Cir. 2015).

Opinion

*807 OPINION

MATTICE, District Judge.

Renaissance/Valley Farms, LLC, DKCD, Inc., and Donald J. Cook (hereinafter, “Appellants” or “the' Renaissance parties”) raised claims under Kentucky law for breach of contract, negligence, and contractual and common law indemnity against T & C Contracting, Inc., (hereinafter, “T & C” or “Appellee”) arising out of T & C’s subcontract with DKCD to perform certain roadway construction work. On cross motions for summary judgment, the district court denied the motion of the Renaissance parties and granted T & C’s motion as to all claims against T & C. The Renaissance parties timely appealed, and we now affirm the district court’s decision.

I. Background

Although the procedural history of this action is complex, this matter comes before this Court solely for a review of the district court’s judgment as to Appellants’ claims against Appellee for breach of contract, negligence, and indemnification. The parties did not below, and do not now, dispute the vast majority of the basic facts underlying this action.

In 2004, Renaissance/Valley Farms, LLC (hereinafter, “R/V”) commenced construction of a subdivision on the north side of Valley Station Road in Louisville, Kentucky. The project required certain road construction to be completed in order to accommodate the increase in traffic that would stem from the new subdivision, including the widening of a curved stretch of Valley Station Road and the construction of additional lanes of traffic. R/V — the “owner” of the project — contracted with DKCD, Inc., doing business as Renais-sanee Development, to serve as construction manager of the project (hereinafter, the “original contract”). 1 DKCD retained Heritage Engineering, LLC to prepare engineering plans for the roadway construction project.

Because Valley Station Road is a state-owned right of way that is under the. control of the Kentucky Transportation Cabinet (hereinafter, “KYTC”), R/V was required to apply for an encroachment permit in order to perform construction on the roadway. R/V submitted its application for such a permit, including the initial engineering site design plan prepared by Heritage (hereinafter, the “original plan”). In February 2005, the KYTC issued an encroachment permit to R/V to complete the construction as requested. The permit states:

THE PERMITTEE AGREES THAT ALL WORK WITHIN THE EXISTING RIGHT-OF-WAY SHALL BE DONE IN ACCORDANCE WITH THE PLANS AS APPROVED AND PERMITTED BY AN ENCROACHMENT PERMIT. ANY CHANGES OR VARIANCES MADE AT THE TIME OF CONSTRUCTION WITHOUT WRITTEN APPROVAL FROM THE DEPARTMENT OF HIGHWAYS SHALL BE REMOVED BY THE PERMITTEE AT NO EXPENSE TO THE DEPARTMENT OF HIGHWAYS AND SHALL BE REDONE TO CONFORM WITH THE APPROVED PLANS.

The permit incorporates by reference the May 26, 2004 design plan prepared by Heritage, and states that “[t]he permittee agrees as a condition to the issuance of the permit to construct and maintain such facilities in accordance with said plan....”

*808 Steven Tucker, the engineer with KYTC who approved of R/V’s encroachment permit, confirmed that KYTC would have to review any revisions to plans upon which a permit had been issued before such revised plans could be used to construct or complete a project. Tucker confirmed that such revisions are done by the engineer or the permittee, not by the construction company. 2

In August 2005, DKCD entered into a subcontract with T & C to perform the construction work on Valley Station Road. 3 The relevant portions of the subcontract are as follows:

SECTION FOUR PERFORMANCE OF WORK
A. Subcontractor shall :.. perform all labor required for the completion of the above-described work in accordance with all provision of the original contract [between R/V and DKCD] and of the specifications, plans, and addenda referred to in the original contract, all of which are hereby made a part of this agreement, and to the satisfaction of owner and contractor.
SECTION FOURTEEN CHANGES, EXTRA WORK, AND DISPUTES
A. Changes in Original Contract. Construction Manager is not an insurer or guarantor of the work or any part of the work; of the performance by owner of the original contract; or of plans and specifications furnished by owner. Subcontractor shall be bound by any changes or alterations made by owner to the original contract specifications or plans, or in the amount or character of the work or any part of the work, to the same extent that contractor is bound by any such change or alteration.
B. Notice of Change Order. Subcontractor will be notified of any change order requested by or of owner with respect to subcontract work and will be consulted with respect to the proposed terms of any such change order, but subcontractor shall be bound by the terms of any change order negotiated in good faith by Construction Manager with owner....
SECTION TWENTY-FOUR SPECIAL PROVISIONS
Subcontractors shall comply with all federal, state, territorial, and local codes and statutes of the area involved and shall indemnify Construction Manager against any and all claims or liens as a result of acts or omissions on part of subcontractor with respect to any noncompliance with such codes and statutes.

It is undisputed that, at some point in 2005, Heritage prepared a revised site design plan for the Valley Station Road construction (hereinafter, “the revised plan”). 4 *809 Both the original and existing plans included a “typical section” providing for the road to be constructed with a cross slope of “2% minimum or continue existing grade” of the roadway. The revised plans also contained “spot elevations” that were to be used to grade the slope of the roadway construction because the drainage ditch would not allow for a continuous matching slope of the existing grade. It is undisputed that no one involved in the project — that is, the Renaissance parties, Heritage, or T & C — submitted the revised plans to the KYTC.

According to T & C’s president, Donald Thornberry, Les Gatrost — the project superintendent appointed by the Renaissance parties — brought T & C a copy of the revised plans. 5 It is undisputed that T & C used the revised engineering plans, rather than the original plans, to complete the construction work on Valley Road Station. Gatrost was -present on the site for thé duration of the construction work “almost on a daily basis” as the construction representative for the Renaissance parties.

T & C completed the construction as detailed in the revised plans prepared by Heritage.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
614 F. App'x 805, Counsel Stack Legal Research, https://law.counselstack.com/opinion/developers-surety-and-indemnity-v-renaissancevalley-farms-llc-ca6-2015.