Detroit & I. R. Co. v. A. Guthrie & Co.

72 F.2d 126, 1934 U.S. App. LEXIS 4468
CourtCourt of Appeals for the Sixth Circuit
DecidedJune 5, 1934
DocketNo. 6455
StatusPublished
Cited by2 cases

This text of 72 F.2d 126 (Detroit & I. R. Co. v. A. Guthrie & Co.) is published on Counsel Stack Legal Research, covering Court of Appeals for the Sixth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Detroit & I. R. Co. v. A. Guthrie & Co., 72 F.2d 126, 1934 U.S. App. LEXIS 4468 (6th Cir. 1934).

Opinion

MOORMAN, Circuit Judge.

In 1927 the appellant determined to construct a line of railroad in Ohio about four miles in length, extending from the north abutments of. a bridge crossing .the Maumee river north to milepost 80, a point near a track of the Wabash Railroad. It also determined to erect a substructure for the IVlaumeo River Bridge. The proposed route oE the road crossed Turkey foot creek three times, necessitating the erection of three bridges. On June 15, 1927, appellant contracted with the M. E. White Company for the erection of the substructure of the Maumee River Bridge, the work to be completed in one year from that date; and on September 28, 19:17, it contracted with Green & Sawyer for the construction of the three Turkeyfoot Creek bridges, to be completed May 1, 1928. Part of the grading for the roadway could be done by teams and scrapers; part of it required the hauling in of earth for fills. In order to obtain the earth the appellant acquired a tract of land of about 45 ax;réa for a borrow pit west of a point midway between the termini of the proposed line. On January 16, 1928, the appellee entered into a contract with appellant to do the grading, work from; the Maumee river to milepost SO according to specifications furnished by the appellant. Appelle'e entered upon the performance of the work about the middle of May, and, after finishing it, brought this suit against the appellant to recover the additional costs it was put to in performing the work, resulting, as it claimed, from misrepresentations made by the appellant in the specifications as to the conditions under which the work could be performed. The appellant filed answer denying the averments of misrepresentation, ‘and by counterclaim sought judgment for an overpayment made to the appellee. The jury found in favor of appellant on the counterclaim, and for the appellee as follows: $39,825.48 for loss or damage sustained by reason of the delay in completing the masonry or bridge structures; $14,589.55 loss on account of misrepresentations as to the borrow pit; and $3,388.02 additional expense incurred as a result of the difference between the number of cubic yards of dirt for long-haul excavation indicated by appellant and the actual amount thereof. The appellee filed a remittitur as to the latter itero, and the court entered judgment oil the other awards. No appeal has been taken from the finding and judgment on the counterclaim.

The elaim of loss on account of delay in completing the bridge structures consisted of increased expense or costs of moving equipment to the borrow pit and doing the excava^tion and filling work. The appellee contended, and introduced evidence to show, that had the bridges been completed by May 1, it could have laid a track along the right of way and over the bridges so tha.1 its equipment could have been placed on small cars at the Wabash siding and transported to the borrow pit, whereas, the bridges not being completed by that date, it was compelled to unload the equipment at Liberty Center and haul it from that point to the borrow pit at an increased expense; and, further, that it contemplated using camp cars on the siding- of the Wabash for its men and transporting them to and from their work over the tracks which it proposed to lay, but being unable to lay the tracks because of the delay in finishing the [128]*128bridges, the men left the work, and it was compelled to obtain other men at additional expense. It also contended that had the bridges been constructed, it could have constructed the railway tracks and hauled earth in cars both north and south from the borrow pit at a saving in labor and time.

It may be accepted as settled that an employer is liable for losses sustained by a contractor as the result of misrepresentations of fact in specifications upon which the contractor relied in contracting to do the work. Hollerbach v. United States, 233 U. S. 165, 34 S. Ct. 553, 58 L. Ed. 898. But it is also settled that the employer cannot be held responsible for statements of expectation, opinion or judgment, honestly entertained. Connecticut Mut. Life Ins. Co. v. Luchs, 108 U. S. 498, 508, 2 S. Ct. 949, 27 L. Ed. 800; Southern Development Co. v. Silva, 125 U. S. 247, 250, 8 S. Ct. 881, 31 L. Ed. 678; Johansson v. Stephanson, 154 U. S. 625, 14 S. Ct. 1180, 23 L. Ed. 1009.

Appellee’s claim of misrepresentation as to the dates the bridge structures would" be completed and ready for its use is founded upon the following provisions of the specifications :

“Backfilling of Abutments. The contractor shall backfill all abutments within the limits of this work constructed by other contractors. It is anticipated that the abutments will be ready for backfilling about April 1, 1928. The materials used in backfilling these structures shall be obtained from the borrow pit at Station 4398 to Station 4420. The date shown above is as close as can be determined at this time and the railroad will make every effort to have the structures ready at the date specified or within reasonable length of time thereafter, but does not guarantee that they will be. The bridge at Station 4429 will be the first of the three (3) Turkeyfoot Creek bridges completed. * * *
“Masonry Structures. The railroad has contracted for the completion of all masonry structures at dates that should not interfere with the contractor’s operations. In ease of non-completion at the dates contracted for the ■railroad will take such measures, with the contractor’s co-operation that will permit him to carry on his work with the m.inimirm of delay and expense.”

In the first of these provisions it was stated that it was anticipated the abutments would be ready for backfilling April 1. This was not a representation of fact but an expression of an opinion or expectation. Furthermore, it was qualified by the further statement that the date indicated was as close as could be determined at that time, and that appellant would make every effort to have the structures ready on that date or within a reasonable time thereafter, but did not guarantee that they would be ready. There is nothing in the provision, as we read it, justifying the contention that it contains a statement of fact as to the date the abutments would be ready for backfilling.

The second provision stated that the railroad company had contracted for the completion of the bridges at dates that should not interfere with the contractor’s operations. The statement did not purport to give the dates of completion according to contract. The proofs show that the appellant had contracted for the completion of the Turkeyfoot Creek bridges by May 1 and the substructure of the Maumee Bridge by June 15, and there is no representation in the specifications to the contrary. The statement that the dates contracted for were such as should not interfere with the contractor’s operation was not a statement of a fact but an expression of an opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
72 F.2d 126, 1934 U.S. App. LEXIS 4468, Counsel Stack Legal Research, https://law.counselstack.com/opinion/detroit-i-r-co-v-a-guthrie-co-ca6-1934.